The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on may 7, 2010.  The following is PRS’s summary of the Bill (The Bill summary and the Bill along with related media articles can also be accessed on the PRS Website):

The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.

he Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010. The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

§ Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

§ The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

§ The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

§ The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

§ The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

§ Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

§ The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.

  The Enforcement of Security Interest and Recovery of Debts Laws and Miscellaneous Provisions (Amendment) Bill, 2016 is listed for discussion in Rajya Sabha today.[i]  The Bill aims to expeditiously resolve cases of debt recovery by making amendments to four laws, including the (i) Recovery of Debts Due to Banks and Financial Institutions Act, 1993, and (ii) the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002. Recovery of Debts Due to Banks and Financial Institutions Act, 1993 The 1993 Act created Debt Recovery Tribunals (DRTS) to adjudicated debt recovery cases.  This was done to move cases out of civil courts, with the idea of reducing time taken for debt recovery, and for providing technical expertise.  This was aimed at assisting banks and financial institutions in recovering outstanding debt from defaulters. Over the years, it has been observed that the DRTs do not comply with the stipulated time frame of resolving disputes within six months. This has resulted in delays in disposal, and a high pendency of cases before the DRTs. Between March 2013 and December 2015, the number of pending cases before the DRTs increased from 43,000 to 70,000.  With an average disposal rate of 10,000 cases per year, it is estimated that these DRTs will take about six to seven years to clear the existing backlog of cases.[ii] Experts have also observed that the DRT officers, responsible for debt recovery, lack experience in dealing with such cases.  Further, these officers are not adequately trained to adjudicate debt-related matters.[iii] The 2016 Bill proposes to increase the retirement age of Presiding Officers of DRTs, and allows for their reappointment.  This will allow the existing DRT officers to serve for longer periods of time.  However, such a move may have limited impact in expanding the pool of officers in the DRTs. The 2016 Bill also has a provision which allows Presiding Officers of tribunals, established under other laws, to head DRTs.  Currently, there are various specialised tribunals functioning in the country, like the Securities Appellate Tribunal, the National Company Law Tribunal, and theNational Green Tribunal.  It remains to be seen if the skills brought in by officers of these tribunals will mirror the specialisation required for adjudicating debt-related matters. Further, the 1993 Act provides that banks and financial institutions must file cases in those DRTs that have jurisdiction over the defendant’s area of residence or business.  In addition, the Bill allows cases to be filed in DRTs having jurisdiction over the bank branch where the debt is due. The Bill also provides that certain procedures, such as presentation of claims by parties and issue of summons by DRTs, can now be undertaken in electronic form (such as filing them on the DRT website). Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 The 2002 Act allows secured creditors (lenders whose loans are backed by a security) to take possession over a collateral security if the debtor defaults in repayment.  This allows creditors to sell the collateral security and recover the outstanding debt without the intervention of a court or a tribunal. This takeover of collateral security is done with the assistance of the District Magistrate (DM), having jurisdiction over the security.  Experts have noted that the absence of a time-limit for the DM to dispose such applications has resulted in delays.[iv]  The 2016 Bill proposes to introduce a 30-day time limit within which the DM must pass an order for the takeover of a security.  Under certain circumstances, this time-limit may be extended to 60 days. The 2002 Act also regulates the establishment and functioning of Asset Reconstruction Companies (ARCs).  ARCs purchase Non-Performing Assets (NPAs) from banks at a discount.  This allows banks to recover partial payment for an outstanding loan account, thereby helping them maintain cash flow and liquidity.  The functioning of ARCs has been explained in Figure 1. Enforcement of security It has been observed that the setting up of ARCs, along with the use out-of-court systems to take possession of the collateral security, has created an environment conducive to lending.[iii]  However, a few concerns related to the functioning of ARCs have been expressed over the years.  These concerns include a limited number of buyers and capital entering the ARC business, and high transaction costs involved in the transfer of assets in favour of these companies due to the levy of stamp duty.[iii] In this regard, the Bill proposes to exempt the payment of stamp duty on transfer of financial assets in favour of ARCs.  This benefit will not be applicable if the asset has been transferred for purposes other than securitisation or reconstruction (such as for the ARCs own use or investment).  Consequently, the Bill amends the Indian Stamp Act, 1899. The Bill also provides greater powers to the Reserve Bank of India to regulate ARCs.  This includes the power to carry out audits and inspections either on its own, or through specialised agencies. With the passage of the Bankruptcy Code in May 2016, a complete overhaul of the debt recovery proceedings was envisaged.  The Code allows creditors to collectively take action against a defaulting debtor, and complete this process within a period of 180 days.  During the process, the creditors may choose to revive a company by changing the repayment schedule of outstanding loans, or decide to sell it off for recovering their dues. While the Bankruptcy Code provides for collective action of creditors, the proposed amendments to the SARFAESI and DRT Acts seek to streamline the processes of creditors individually taking action against the defaulting debtor.  The impact of these changes on debt recovery scenario in the country, and the issue of rising NPAs will only become clear in due course of time. [i] Enforcement of Security Interest and Recovery of Debts Laws and Miscellaneous Provisions (Amendment) Bill, 2016, http://www.prsindia.org/administrator/uploads/media/Enforcement%20of%20Security/Enforcement%20of%20Security%20Bill,%202016.pdf. [ii] Unstarred Question No. 1570, Lok Sabha, Ministry of Finance, Answered on March 4, 2016. [iii] ‘A Hundred Small Steps’, Report of the Committee on Financial Sector Reforms, Planning Commission, September 2008, http://planningcommission.nic.in/reports/genrep/rep_fr/cfsr_all.pdf. [iv] Financial Sector Legislative Reforms Commission, March 2013, http://finmin.nic.in/fslrc/fslrc_report_vol1.pdf.