The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on may 7, 2010.  The following is PRS’s summary of the Bill (The Bill summary and the Bill along with related media articles can also be accessed on the PRS Website):

The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.

he Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010. The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

§ Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

§ The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

§ The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

§ The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

§ The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

§ Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

§ The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.

Source: www.pib.nic.in Source: www.pib.nic.in

 

Yesterday the Prime Minister reshuffled his Cabinet and inducted four cabinet ministers and four ministers of state.  Since the beginning of the UPA II government, there have been three major Cabinet reshuffles and a number of minor readjustments in the portfolios of ministers. Analysing changes in the portfolios of ministers gives an insight into the churn in the political leadership of the different ministries of the government of India. Until recently there was no central online resource where information could be collated about cabinet reshuffles. The information was scattered between the websites of the President, the Prime Minister and the Press Information Bureau. Since 2012, the Cabinet Secretariat has started putting details about changes in the portfolio of the council of ministers in the public domain. However analysing this information becomes difficult as the information is split into different files and details about the Cabinet reshuffle do not go back till 2009. We have tried to collate data about changes in Cabinet portfolios since May 2009, so that it becomes easily accessible and can be analysed by interested individuals.  The raw data file can be accessed here. This data could be analysed to see which Ministers have shifted across ministries or the average length of tenure of Ministers in different ministries. If you spot interesting trends in the raw data above, please share them with us on twitter@prslegislative We have done a preliminary analysis of the data to see which ministries have had the most changes in Cabinet Ministers since May 2009: - Railway Ministry portfolio has been held by six different Cabinet Ministers [Mamata Banerjee, Dinesh Trivedi, Mukul Roy, C P Joshi (twice), Pawan Kumar Bansal and now Mallikarjun Kharge] - Ministry of Law and Justice, Corporate Affairs and Science and Technology: Four Cabinet Ministers. - Ministry of Petroleum and Natural Gas, Civil Aviation, Rural Development, Tourism and Youth and Sports:  Three Cabinet Ministers. - Ministries like Finance, Home, External Affairs, Communications and Information Technology, Human Resource Development:  Two Cabinet Ministers. - Ministries like Agriculture and Non Conventional Energy Sources have the same Ministers from May 2009. This data also helped us put together a brief chronology of Cabinet reshuffles since the beginning of the term of the UPA II government:

23 & 28- May-09 Cabinet sworn in.
31-May-09 Meria Kumar resigns as Minister of Water Resources to become Speaker of Lok Sabha.
19-Apr-10 Shashi Tharoor resigns as Minister of State from the Ministry of External Affairs.
15-Nov-10 A Raja resigns as Minister of Communications and Information Technology. Kapil Sibal gets additional charge of the ministry.
19-Jan-11 First major cabinet reshuffle. Most ministries affected.
12-Jul-11 Second major Cabinet reshuffle. Dinesh Trivedi assumes charge of Railway Ministry after Mamata Banerjee, Salman Khursheed becomes Law Minister, Jairam Ramesh moves to Rural Development. New Ministers like Rajeev Shukla (Parliamentary Affairs) and Jayanthi Natarajan (Environment and Forest) get inducted.
18-Dec-11 RLD joins UPA. Ajit Singh inducted as Minister of Civil Aviation.
20-Mar-12 Dinesh Trivedi resigns and Mukul Roy becomes Railway Minister.
27-Jun-12 Pranab Mukherjee resigns as Finance Minister to fight the presidential election.
31-Jul-12 P Chidambaram moves from Home to Finance Ministry and Sushil Kumar Shinde moves from Power to Home Ministry.
22-Sep-12 Trinamool withdraws support to UPA. All TMC ministers resign. C P Joshi assumes additional charge of Railway Ministry.
28-Oct-12 Third major reshuffle. S M Krishna resigns from Ministry of External Affairs and Salman Khursheed takes over. Ashwani Kumar comes in place of Salman Khursheed in Law and Justice. Ambika Soni resigns and Manish Tiwari takes charge of Ministry of Information and Broadcasting. Ajay Maken moves from Ministry of Youth Affairs and Sports to Housing and Urban Poverty Alliviation.
21-Mar-13 DMK withdraws support. All DMK Ministers resign.
11-May-13 Ashwani Kumar and Pawan Kumar Bansal resign. Kapil Sibal takes charge of Ministry of Law and Justice and C P Joshi takes charge of Railways.
16-Jun-13 Ajay Maken and C P Joshi resign.