The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on may 7, 2010.  The following is PRS’s summary of the Bill (The Bill summary and the Bill along with related media articles can also be accessed on the PRS Website):

The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.

he Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010. The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

§ Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

§ The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

§ The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

§ The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

§ The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

§ Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

§ The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.

Authored by Anil Nair and CV Madhukar PRS just concluded a workshop for MLAs from 50+ from more than a dozen states.  What an AMAZING experience this was, even though this is the sixth such workshop we have held in this past year! This three day workshop on 'Mastering the Budget' was designed to help MLAs understand how to work with budget documents and numbers, find trends, understand the most critical macro numbers to track, etc. The second day of the workshop was tailored to reflect on the big thematic issues that have an impact on state finances. The Fiscal Responsibility and Budget Management Act, the Goods and Services Tax, the pattern of quantum of funds flow from the Centre to the state and local governments, the 13th Finance Commission, etc. The final day was devoted to doing an inter-state comparison of states on important budget parameters, and gleaning lessons from them. The idea for this budget workshop germinated at a previous workshop held at IIM Bangalore. The participating MLAs requested PRS to organise a special session on 'Mastering the Budget'. So this workshop was being organised as a result of their feedback. The choice of location was easy -- this was held at the National Institute for Public Finance and Policy in Delhi, which is amongst India's foremost institutions working on state budgets and public finance issues. Invitations were sent out to MLAs in several states. Responses started coming in within a few days, with about 70 confirmations. But there is always an uncertainty on the participation until the very last minute because elected politicians have immense demands on their time, at least some of which are unpredictable. So it was heartening to see that more than 50 MLAs came to the workshop representing 15 states -- Bihar, Rajasthan, Odisha, Uttar Pradesh, Assam, Kerala, West Bengal, Andhra Pradesh, Meghalaya, Tamil Nadu, Madhya Pradesh, Himachal Pradesh, Gujarat, Haryana, Manipur. The participants ranged from first time MLAs (about 50%), to a sitting Minister, a sitting Speaker, former Ministers, and senior leaders of political parties from some states. But the best part about the interaction in this workshop was that even on seemingly complex issues being discussed in the classroom, the MLAs were not mere recipients of 'gyan' that was being dished out. They had important questions to raise, and well articulated points of disagreement with the faculty, and brought in practical perspectives that might not have otherwise come up in the discussions. They went beyond the scope of the workshop to engage the economists on discussions on subjects like FDI in retail, state of India’s economy… Based on our experience of several workshops with MLAs, we want to share some observations about the participating MLAs: -         There are MLAs in every state who want to understand substantive policy issues, and are willing to invest time and energy to do so. -         When the MLAs participate in these workshops, they choose to do so on their own, and are not compelled by anyone to do so. -         The sessions almost always begin and end on time, even in the freezing cold mornings in the Delhi winter. -         The MLAs are very engaged in the discussions, ask questions, and bring in their experiences into the classroom discussions. -         They keep partylines completely out of the substantive classroom discussions, and in the rare event that some new participant mentions anything partisan, other participants quickly ask him to avoid making any such mentions. In 2011, we have engaged with over 250 MLAs through these workshops and more. These workshops are just a starting point of what we hope will develop into a sustained, longer term engagement with MLAs on policy issues coming up in their states. In an important partnership with the Indian School of Business, Hyderabad, PRS has already conducted two workshops  at the world class facilities at the ISB campus, and is planning to hold more in 2012. Just as PRS engages with about 300 MPs in Parliament, the hope is that more MLAs will be able to derive value from the work of PRS in the years to come, thereby making their decisions better informed. Some feedback from MLAs from our earlier workshops can be seen here: http://www.youtube.com/watch?v=9XlgKCp2bvs or http://www.youtube.com/watch?v=01kLLTVtJOU&feature=related or http://www.youtube.com/watch?v=WA4NZqCj2xk&feature=related