The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on may 7, 2010.  The following is PRS’s summary of the Bill (The Bill summary and the Bill along with related media articles can also be accessed on the PRS Website):

The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.

he Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010. The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

§ Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

§ The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

§ The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

§ The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

§ The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

§ Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

§ The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.

By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:

  • Mobility (including purchase of bullet proof and mine proof vehicles)
  • Weaponry
  • Communication Systems
  • Training
  • Forensic Science Laboratory/ Finger Printing Bureau
  • Equipments
  • Buildings

Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the MHA were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan.

c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower.

Weapons

§ Police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006.

c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower.

Weapons

§ It was observed that the police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.