Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified. Last date for submitting the applications is December 21, 2024.

According to news reports, the Supreme Court stayed a Calcutta High Court judgement on the Singur Land Rehabilitation and Development Act, 2011 [Singur Act] on August 24, 2012. The apex court also issued a notice to Tata Motors seeking its response within four weeks, on the West Bengal government's petition challenging the High Court order. In 2008, the Left Front government acquired land in Singur under the Land Acquisition Act, 1894, for Tata Motors to build a Nano car factory.  In its first year of coming to power in West Bengal, the Trinamool Congress (TMC) led government notified the Singur Act through which it sought to reclaim this land to return a portion of it to farmers. On June 22, 2012, a Division bench of the Calcutta High Court struck down the Singur Act terming it unconstitutional and void.  In its judgment, the Court found some sections of the Singur Act to be in conflict with the central Land Acquisition Act, 1894.  As land acquisition is a Concurrent List subject under the Constitution, both Parliament and state legislatures have the power to make laws on it.  However, if provisions in the state law conflict with provisions in the central law, then the state law cannot prevail unless it receives Presidential assent.  The Calcutta High Court held the Singur Act to be unconstitutional because: (a) it was in conflict with the central Land Acquisition Act, 1894, and (b) Presidential assent was not obtained for the Act to prevail in West Bengal. The central Act mentions that for the government to acquire land, it has to demonstrate: (1) that land is being acquired for a public purpose,[i] and (2) that the government will provide compensation to persons from whom land is being acquired.  Provisions in the Singur Act that relate to public purpose and compensation were found to be in conflict with the corresponding provisions in the central Act.  The Court was of the opinion that transfer of land to the farmers does not constitute ‘public purpose’ as defined in the central Act.  As argued by the Tata Motors’ counsel, return of land to unwilling owners is a ‘private purpose’ or in ‘particular interest of individuals’ rather than in the ‘general interest of the community’.  Second, clauses pertaining to compensation to Tata Motors for their investment in the Nano project were found to be vague.  The Singur Act only provides for the refund of the amount paid by Tata Motors and the vendors to the state government for leasing the land.  It does not provide for the payment of any other amount of money for acquiring the Tata Motors’ land nor the principles for the determination of such an amount.  The High Court ordered that these provisions tantamount to ‘no compensation’ and struck down the related provisions. The matter will come up for consideration in the Supreme Court next on October 15, 2012.


[i] According to Section 3 of the Land Acquisition Act, 1894, acquisition of land for ‘public purpose’ includes, among others: provision or planned development of village sites; provision of land for town or rural planning; the provision of land for planned development of land from public funds in pursuance of a scheme or policy of the Government; and the provision of land for a corporation owned or controlled by the State.

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.