All companies are currently governed by the Companies Act, 1956. The Act has been amended 24 times since then. Three committees were formed in the last ten years, chaired by Justice V B Eradi (2001), Naresh Chandra (2002) and J J Irani (2005) to look into various aspects of corporate governance and company law. The Companies Bill, 2009 incorporates some of these recommendations. Main features The major themes of the Bill are as follows: It moves a number of issues that are currently specified in the Act (and its schedules) to the Rules; this change will make the law more flexible, as changes can be made through government notification, and would not require an amendment bill in Parliament. On a number of issues, the Bill moves the onus of oversight towards shareholders and away from the government. It also requires a super-majority of 75 percent shareholder votes for certain decisions. The powers of creditors have been enhanced in cases where a company is in financial distress. It has new provisions regarding independent directors and auditors in order to strengthen corporate governance. Finally, the bill increases penalties, and provides for special courts. Types of companies The Bill provides for six types of companies. Public companies need to have at least seven shareholders, and private companies between two and 50 shareholders. Charitable companies should have at least one shareholder, may have only certain specified objectives, and may not distribute dividend. Three new types of companies have been defined, which have less stringent provisions. These are one-person companies, small companies (private companies with capital less than Rs 50 million and turnover below Rs 200 million), and dormant companies (formed for future projects, or no operations for two years). Corporate Governance The Bill defines the duties of directors and norms for composition of boards. The number of directors is capped at 12. At least one director should be resident in India for at least 183 days in a calendar year and at least a third of the board should consist of independent directors. The Bill also sets guidelines for auditors. Certain related persons such as creditors, debtors, shareholders and guarantors cannot be appointed as auditors. Certain services such as book-keeping, internal audit and management services may not be undertaken by the auditors. Removal of an auditor before completion of term requires approval of 75 percent of the shareholders. Adjudication The Bill provides for a National Company Law Tribunal (NCLT) to adjudicate disputes between companies and their stakeholders. It also establishes an Appellate Tribunal. The NCLT may ask the government to investigate the working of a company on an application made by 100 shareholders or those who hold 10 percent of the voting power. Arrangements All arrangements such as mergers, takeovers, debt split, share splits and reduction in share capital must be approved by 75 percent of creditors or shareholders, and sanctioned by the NCLT. Standing Committee’s Recommendations The Parliamentary Standing Committee on Finance has submitted its report, and suggested several significant amendments. Corporate governance Substantive matters covered in various corporate governance guidelines should be contained in the Bill. These include: separation of offices of Chairman and Chief Executive Officer; limiting the number of companies in which an individual may become director; attributes for independent directors; appointment of auditors. Delegated legislation The Committee noted that the Bill provided excessive scope for delegated legislation. Several substantive provisions were left for rule-making and the Ministry was asked to reconsider provisions made for excessive delegated legislation. The Ministry has agreed to make some changes to include the following provisions in the Act: the definition of small companies; the manner of subscribing names to the Memorandum of Association; the format of Memorandum of Association to be prescribed in the Schedule; the manner of conducting Extraordinary General Meetings; documents to be filed with the Registrar of Companies. The Committee recommended that provisions relating to independent directors in the Bill should be distinguished from other directors. There should be a clear expression of their mode of appointment, qualifications, extent of independence from management, roles, responsibilities, and liabilities. The Committee also recommended that the appointment process of independent Directors should be made independent of the company’s management. This should be done by constituting a panel to be maintained by the Ministry of Corporate Affairs, out of which companies can choose their requirement of independent directors. Investor protection The Ministry, in response to the Committee’s concerns for ensuring protection of small investors and minority shareholders, indicated new proposals. These include: enhanced disclosure requirements at the time of incorporation; shareholder’s associations/groups enabled to take legal action in case of any fraudulent action by the company; directors of a company which has defaulted in payment of interest to depositors to be disqualified for future appointment as directors. The Ministry also made some suggestions on protection of minority shareholders/small investors, which the Committee accepted, including the source of promoter’s contribution to be disclosed in the Prospectus; stricter rules for bigger and solvent companies on acceptance of deposits from the public; return to be filed with Registrar in case of promoters/top ten shareholders stake changing beyond a limit. Corporate Delinquency Recommendations include: subsidiary companies not to have further subsidiaries; main objects for raising public offer should be mentioned on the first page of the prospectus; tenure of independent director should be provided in law; the office of the Chairman and the Managing Director/CEO should be separated. The Committee emphasised that the procedural defaults should be viewed in a different perspective from fraudulent practices. Shareholder democracy The Committee recommended that the system of proxy voting should be discontinued. It also stated that the quorum for company meetings should be higher than the proposed five members, and should be increased to a reasonable percentage. Foreign companies The Bill requires foreign companies having a place of business in India and with Indian shareholding to comply with certain provisions in the proposed Bill. The Committee observed that the Bill does not clearly explain the applicability of the Bill to foreign companies incorporated outside India with a place of business in India. It recommended that all such foreign companies should be brought within the ambit of the chapter dealing with foreign companies. Next steps The report of the Standing Committee indicates that the Ministry has accepted many of its recommendations. It is likely that the government will take up the Bill for consideration and passing during the winter session, which starts on 9th November. This article was published in PRAGATI on November 1, 2010

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.