Recently there have been news reports about the NITI Aayog submitting its recommendations on improving the financial health of Air India to the Ministry of Finance.[1],[2]  The Civil Aviation Ministers have also mentioned that the Ministry will soon propose a roadmap for the rejuvenation of the national airline.  While the NITI Aayog report is not out in the public domain yet, we present a few details on the financial health of the airline.

Finances of Air India

In 2015-16, Air India earned a revenue of Rs 20,526 crore and registered losses of Rs 3,837 crore.  As of March 31, 2015, the total debt of Air India was at Rs 51,367 crore.[3]  This includes Rs 22,574 crore outstanding on account of aircraft loans.  The figure below shows the losses incurred by Air India in the last few years (2007-16).

image(1)

According to the Ministry of Civil Aviation, reasons for Air India’s losses include: (i) the adverse impact of exchange rate variation due to the weakening of Indian Rupee, (ii) high interest burden, (iii) increase in competition, especially from low cost carriers, and (iv) high fuel prices.[4]  The National Transport Development Policy Committee (NTDPC), in its report in 2013, had observed that with the increase in the number of airlines in the market, Air India has been struggling to make a transition from a monopoly market to a competitive one.[5]  These struggles have been primarily regarding improving its efficiency, and competing with the private airlines.

Turnaround Plan and Financial Restructuring

In order to bail out the company, the government had approved the Turnaround Plan (TAP) and Financial Restructuring Plan (FRP) of Air India in April 2012.[6]  Under the plans, the government would infuse equity into Air India subject to meeting certain milestones such as Pay Load Factor (measures capacity utilisation), on time performance, fleet utilisation, yield factor (average fare paid per mile, per passenger), and rationalisation of the emolument structure of employees.7  The equity infusion included financial support towards the repayment of the principal, as well as the interest payments on the government loans for aircraft acquisition.  Under the TAP/FRP, the central government was to infuse Rs 30,231 crore till 2020-21.  As of 2016-17, the Ministry has infused an equity amount of Rs 24,745 crore.[7]

In 2017-18, the Ministry has allocated Rs 1,800 crore towards Air India which is 67% of the Ministry’s total budget for the year.[8]  However, this amount is 30% lower than the TAP commitment of Rs 2,587 crore.3  In 2016-17, while Air India had sought and equity infusion of Rs 3,901 crore, the government approved Rs 2,465 crore as the equity infusion.[9]  The Standing Committee on Transport, Tourism, and Culture examining the 2017-18 budget estimates noted that reducing the equity infusion in Air India might adversely affect the financial situation of the company.[10]  It recommended that the government must allocate the amount committed under TAP.  The Ministry had also observed that due to reduction of equity infusion, Air India has to arrange funds through borrowing which costs additional amount of interest to be paid by the government.[11]

As per the Ministry, Air India has achieved most of the targets set out in TAP.[12]  Despite running into losses, it achieved an operating profit of Rs 105 crore in FY 2015-16.[13]  Air India’s performance in some of the segments are provided in the table below.

Table 1: Air India’s performance

  2011-12 2014-15
Overall Network On Time Performance (measures adherence to time schedule) 68.2% 72.7%
Passenger Load Factor (measures capacity utilisation of the airline) 67.9% 73.7%
Network Yield achieved (in Rs/ RPKM)* 3.74 4.35
Number of Revenue Passengers (in million) 13.4 16.9
Operating Loss (in Rs crore) 5,139 2,171

* Note: RPKM or Revenue Passenger Kilometre performed refers to number of seats for which the carrier has earned revenue.

Sources: Lok Sabha Questions; PRS.

The NTDPC had observed that with its excessive and unproductive manpower, failure to invest in the technology required to keep it competitive, and poor operations, Air India’s future looks risky.  It had also questioned the rationale for a national airline.  It had suggested that the government must frame a decisive policy with regard to Air India, and clarify its future accordingly.5  It had recommended that Air India’s liabilities should be written off and be dealt with separately, and the airline should be run on complete operational and financial autonomy.5

Need for competitive framework in the sector

With the entrance of several private players in the market, the domestic aviation market has grown significantly in the last decade.  The market share of an airline is directly related to its capacity share in the market.  While private carriers have added capacity in the domestic market, the capacity induction (adding more aircrafts) of Air India has not kept up with the private carriers.  This has resulted in decrease in market share of Air India from 17% in 2008-09 to 14% in 2016-17.[14]

The Committee looking at the competitive framework of the civil aviation sector had observed that the national carrier gets preferential treatment through access to government funding, and flying rights.[15]  It had recommended that competitive neutrality should be ensured between private carriers and the national carrier, which could be achieved by removing the regulations that provide such preferential treatment to Air India.  The NTDPC had also noted that the presence of a state-owned enterprise should not distort the market for other private players.6  It had recommended that the Ministry should consider developing regulations that improve the overall financial health of the airline sector.

While Air India’s performance has improved following the TAP, along with the equity infusion from government, its debt still remains high and has been gradually increasing.  In light of this, it remains to be seen what the government will propose with regard to the rejuvenation of the national airline, and ensure a competitive and fair market for all the players in the airline market.

[1] “Govt to prepare Air India revival plan within 3 months, amid calls for privatization”, Livemint, May 31, 2017, http://www.livemint.com/Politics/0koi5Hyidj1gVD3wOWTruM/Govt-says-all-options-open-for-Air-India-revival.html.

[2] “Air India selloff: Fixing airline’s future is more important than past”, Financial Express, May 31, 2017, http://www.financialexpress.com/opinion/why-fixing-air-indias-future-more-important-than-past/693777/.

[3] Lok Sabha Questions, Unstarred question no 382, Ministry of Civil Aviation, February 25, 2016, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=28931&lsno=16.

[4] Lok Sabha Questions, Unstarred question no 353, Ministry of Civil Aviation, November 17, 2016, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=40733&lsno=16.

[5] “Volume 3, Chapter 3: Civil Aviation”, India Transport Report: Moving India to 2032, National Transport Development Policy Committee, June 17, 2014, http://planningcommission.nic.in/sectors/NTDPC/volume3_p1/civil_v3_p1.pdf.

[6] “Government Approves Financial Restructuring and Turn Around Plan of Air India”, Press Information Bureau, Cabinet Committee on Economic Affairs (CCEA), April 12, 2012, http://pib.nic.in/newsite/PrintRelease.aspx?relid=82231.

[7] Lok Sabha Questions, Unstarred question no 472, Ministry of Civil Aviation, April 6, 2017, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=51752&lsno=16.

[8] Notes on Demands for Grants 2017-18, Demand no 9, Ministry of Civil Aviation, http://indiabudget.nic.in/ub2017-18/eb/sbe9.pdf.

[9] Lok Sabha Questions, Unstarred question no 4809, Ministry of Civil Aviation, March 30, 2017, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=51108&lsno=16.

[10] “244th report: Demand for Grants (2017-18) of Ministry of Civil Aviation”, Standing Committee on Transport, Tourism and Culture, March 17, 2017, http://164.100.47.5/newcommittee/reports/EnglishCommittees/Committee%20on%20Transport,%20Tourism%20and%20Culture/244.pdf.

[11] “218th report: Demand for Grants (2015-16) of Ministry of Civil Aviation”, Standing Committee on Transport, Tourism and Culture, April 28, 2015.

[12] Lok Sabha Questions, Unstarred question no 307, Ministry of Civil Aviation, February 25, 2016, http://164.100.47.190/loksabhaquestions/annex/7/AU307.pdf.

[13] Lok Sabha Questions, Unstarred question no 1566, Ministry of Civil Aviation, March 9, 2017, http://www.loksabha.nic.in/Members/QResult16.aspx?qref=47532.

[14] Lok Sabha Questions, Unstarred question no 312, Ministry of Civil Aviation, March 23, 2017, http://164.100.47.194/Loksabha/Questions/QResult15.aspx?qref=49742&lsno=16.

[15] Report of the Committee Constituted for examination of the recommendations made in the Study Report on Competitive Framework of Civil Aviation Sector in India, Ministry of Civil Aviation, June 2012, http://civilaviation.gov.in/sites/default/files/moca_001870_0.pdf.

 

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.