The Insolvency and Bankruptcy Code, 2016 is listed for passage in Rajya Sabha today. Last week, Lok Sabha passed the Code with changes recommended by the Joint Parliamentary Committee that examined the Code.[1],[2] We present answers to some of the frequently asked questions in relation to the Insolvency and Bankruptcy Code, 2016. Why do we need a new law? As of 2015, insolvency resolution in India took 4.3 years on an average. This is higher when compared to other countries such as United Kingdom (1 year) and United States of America (1.5 years). Figure 1 provides a comparison of the time to resolve insolvency for various countries. These delays are caused due to time taken to resolve cases in courts, and confusion due to a lack of clarity about the current bankruptcy framework. What does the current Code aim to do? The 2016 Code applies to companies and individuals. It provides for a time-bound process to resolve insolvency. When a default in repayment occurs, creditors gain control over debtor’s assets and must take decisions to resolve insolvency within a 180-day period. To ensure an uninterrupted resolution process, the Code also provides immunity to debtors from resolution claims of creditors during this period. The Code also consolidates provisions of the current legislative framework to form a common forum for debtors and creditors of all classes to resolve insolvency. Who facilitates the insolvency resolution under the Code? The Code creates various institutions to facilitate resolution of insolvency. These are as follows:
What is the procedure to resolve insolvency in the Code? The Code proposes the following steps to resolve insolvency:
What are some issues in the Code that require consideration?
A version of this blog appeared in the Business Standard on May 7, 2016.
There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the implementation of such projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:
The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded
Sector | No. of projects accorded EC |
Industry (Steel & Cement) |
88 |
Thermal Power |
29 |
River Valley and Hydro-electric |
6 |
Coal Mining |
29 |
Non-Coal Mining |
25 |
National Highways |
32 |
Total |
209 |
Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.
[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,