The row over Bt Brinjal, a genetically modified version of the plant, provoked the government into imposing a moratorium on the commercial cultivation of the plant in India. The debate has revolved around issues of economic efficacy, human health, consumer choice and farmers’ rights. Jairam Ramesh, the Minister of State for Environment and Forests, made public his views on the subject, a gist of which is given below:
In order to understand the process followed by GEAC before giving the green signal to Bt Brinjal, we have made a timeline in which the plant was approved and the bodies involved in the process.
2000-2005 | Scientific tests carried out by Mahyco on Bt Brinjal |
2006 | Mahyco submits bio-safety data to GEAC (regulatory body under the Ministry of Environment and Forests). Seeks permission for large scale trials. |
Supreme Court stops ongoing field trials of GM crops due to a PIL filed by civil society representatives. | |
2007 | The expert committee 1 set up by GEAC, submits its report. Recommends seven more studies on bio-safety be repeated for reconfirmation of data generated during confined multi-location trials but approves large scale trials. |
Supreme Court lifts ban on GM crop field trials subject to conditions such as isolation distance etc. | |
As per GEAC direction, Indian Institute of Vegetable Research (IIVR) takes up the responsibility of large scale trails of Mahyco's Bt Brinjal trials at 10 research institutions across the country in 2007 and 11 in 2008. | |
2009 | Jan: IIVR submits the results of the large scale trails. Due to concerns raised by several stakeholders, GEAC constitutes another expert committee to look into adequacy of biosafety data generated as well as the concerns raised by all stakeholders. |
Oct 8: Expert-committee 2 submits its report. States benefits of Bt Brinjal far outweigh the perceived and projected risks. | |
Oct 14: GEAC approves the environmental release of Bt Brinjal containing the event EE1 (with one dissent note from P.M. Bhargava). | |
Oct 15: Jairam Ramesh announces a nationwide consultation in January and February of 2010 pending a final decision on this issue. | |
2010 | Jan 13 to Feb 6: Public meetings were organized on the Bt Brinjal issue. The summary of the consultations is available on the Ministry’s website. |
Many states announce ban on commercial cultivation of Bt Brinjal including Uttarakhand, Himachal Pradesh and Karnataka. | |
Feb 9: Jairam Ramesh decides to halt the commercialization of Bt Brinjal. |
According to news reports, the Supreme Court stayed a Calcutta High Court judgement on the Singur Land Rehabilitation and Development Act, 2011 [Singur Act] on August 24, 2012. The apex court also issued a notice to Tata Motors seeking its response within four weeks, on the West Bengal government's petition challenging the High Court order. In 2008, the Left Front government acquired land in Singur under the Land Acquisition Act, 1894, for Tata Motors to build a Nano car factory. In its first year of coming to power in West Bengal, the Trinamool Congress (TMC) led government notified the Singur Act through which it sought to reclaim this land to return a portion of it to farmers. On June 22, 2012, a Division bench of the Calcutta High Court struck down the Singur Act terming it unconstitutional and void. In its judgment, the Court found some sections of the Singur Act to be in conflict with the central Land Acquisition Act, 1894. As land acquisition is a Concurrent List subject under the Constitution, both Parliament and state legislatures have the power to make laws on it. However, if provisions in the state law conflict with provisions in the central law, then the state law cannot prevail unless it receives Presidential assent. The Calcutta High Court held the Singur Act to be unconstitutional because: (a) it was in conflict with the central Land Acquisition Act, 1894, and (b) Presidential assent was not obtained for the Act to prevail in West Bengal. The central Act mentions that for the government to acquire land, it has to demonstrate: (1) that land is being acquired for a public purpose,[i] and (2) that the government will provide compensation to persons from whom land is being acquired. Provisions in the Singur Act that relate to public purpose and compensation were found to be in conflict with the corresponding provisions in the central Act. The Court was of the opinion that transfer of land to the farmers does not constitute ‘public purpose’ as defined in the central Act. As argued by the Tata Motors’ counsel, return of land to unwilling owners is a ‘private purpose’ or in ‘particular interest of individuals’ rather than in the ‘general interest of the community’. Second, clauses pertaining to compensation to Tata Motors for their investment in the Nano project were found to be vague. The Singur Act only provides for the refund of the amount paid by Tata Motors and the vendors to the state government for leasing the land. It does not provide for the payment of any other amount of money for acquiring the Tata Motors’ land nor the principles for the determination of such an amount. The High Court ordered that these provisions tantamount to ‘no compensation’ and struck down the related provisions. The matter will come up for consideration in the Supreme Court next on October 15, 2012.
[i] According to Section 3 of the Land Acquisition Act, 1894, acquisition of land for ‘public purpose’ includes, among others: provision or planned development of village sites; provision of land for town or rural planning; the provision of land for planned development of land from public funds in pursuance of a scheme or policy of the Government; and the provision of land for a corporation owned or controlled by the State.