TRAI released its recommendations on auction of spectrum on April 23, 2012.   The recommendations are in pursuance of the Supreme Court order cancelling 122 telecom licences.  The cancellation was ordered on grounds of procedural irregularities and arbitrariness in the first-cum-first-serve policy for allocation of spectrum.   The recommendations, if adopted by the Department of Telecommunications, would change various aspects of the present telecom policy, including (a) relationship between a telecom licence and spectrum; (b) procedure for allocation of spectrum; (c) pricing of spectrum; (d)  limits on spectrum allocation; and (e) use of spectrum. Relationship between telecom licences and spectrum Previously, under the Telecom Policy 1994 (updated in 1999), spectrum was tied in with telecom licences.  Since 2003, licence conditions provided for award of two blocks of 6.2 MHz of spectrum for GSM technology and two blocks of 5 MHz for CDMA technology.  As per the government’s decision of January 17, 2008 (as explained in TRAI's consultation paper, see page 3 paragraph 7) additional spectrum would be awarded on the basis of increment in the number of subscribers.  Service providers had to pay a licence fee (on obtaining the licence), an annual licence fee and a spectrum usage charge determined on the basis of their adjusted gross revenue. TRAI has recommended that telecom licences and spectrum should be de-linked.  The service provider would thus pay separately for the value of the licence and the spectrum.  With this formulation an entity that does not hold a licence, but is eligible to secure one, may also procure spectrum.  This would help in avoiding situations where licence holders have to wait to secure spectrum or offer wire line services in the absence of spectrum. Procedure for allocation of spectrum TRAI has recommended that spectrum be auctioned by means of a simultaneous multiple round ascending auction (SMRA).  This means that the service providers would bid for spectrum in different blocks simultaneously.  In the first round of auction a reserve price (base price) set by the government is used. Reserve price for auction and payment mechanism A reserve price indicates the minimum amount the bidder must pay to win the object.  In case it is too low, it may reduce the gains made by the seller and lead to a sub-optimal sale.  If it is too high, it may reduce the number of bidders and the probability of the good not being sold. Various countries have adopted a reserve price of 0.5 times the final price.  TRAI has recommended that the reserve price should be 0.8 times the expected winning bid.  It has also recommended that telecom companies pay 67% to 75% of the final price in installments over 10 years, depending on the spectrum band. TRAI has reasoned that a higher price would reduce the possibility of further sales upon bidders securing spectrum.  However, this may lead to fewer bidders and ultimately fewer service providers.  It is argued in news reports that this may increase investments to be made by the service providers and eventually an increase in tariffs. Spectrum blocks and caps TRAI has recommended that the spectrum cap should be determined on the basis of market share.  A service provider can now secure a maximum of 50% of spectrum assigned in each band in each service area.  However, a service provider cannot hold more than 25% of the total spectrum assigned in all the bands across the country. As per the January 2008 decision, additional spectrum could be awarded to telecom companies when they reached incremental slabs of subscribers.  This could extend to two blocks of 1 MHz for GSM technology, and two blocks of 1.25 MHz for CDMA, for each slab of subscribers. TRAI has recommended that spectrum should be auctioned in blocks of 1.25 MHz.  Each auction would at least offer 5 MHz of spectrum at a time.  Smaller blocks would ensure that service providers who are nearing the spectrum cap may secure spectrum without exceeding the cap.  However, experts have argued that 1.25 MHz block may be too limited for launching services.  Also, TRAI in the recommendation has noted that a minimum of 5 MHz of contiguous spectrum is required to launch efficient services with new technologies. Use of spectrum TRAI has recommended that the use of spectrum should be liberalised.  This implies that spectrum should be technology neutral.  Telecom companies would now be free to launch services with any technology of their choice.

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.