Earlier this week, Rajya Sabha passed the Airports Economic Regulatory Authority of India (Amendment) Bill, 2019, and the Bill is now pending in Lok Sabha.  The Bill amends the Airports Economic Regulatory Authority of India Act, 2008.  The Act established the Airports Economic Regulatory Authority of India (AERA).  AERA regulates tariffs and other charges for aeronautical services provided at civilian airports with annual traffic above 15 lakh passengers.  It also monitors the performance standard of services across these airports.  In this post, we explain the amendments that the Bill seeks to bring in and some of the issues around the functioning of the regulator.

Why was AERA created, and what is its role?

Few years back, private players started operating civilian airports.  Typically, airports run the risk of becoming a monopoly because cities usually have one civilian airport which controls all aeronautical services in that area.  To ensure that private airport operators do not misuse their monopoly, the need for an independent tariff regulator in the airport sector was felt.  Consequently, the Airports Economic Regulatory Authority of India Act, 2008 (AERA Act) was passed which set up AERA. 

AERA regulates tariffs and other charges (development fee and passenger service fee) for aeronautical services (air traffic management, landing and parking of aircraft, ground handling services) at major airports.  Major airports include civilian airports with annual traffic above 15 lakh passengers.  In 2018-19, there were 32 such airports (see Table 1).  As of June 2019, 27 of these are being regulated by AERA (AERA also regulates tariffs at the Kannur airport which was used by 89,127 passengers in 2018-19).  For the remaining airports, tariffs are determined by the Airports Authority of India (AAI), which is a body under the Ministry of Civil Aviation that also operates airports. 

What changes are being proposed in the Bill?

The Bill seeks to do two things:

Definition of major airports:  Currently, the AERA Act defines a major airport as one with annual passenger traffic over 15 lakh, or any other airports as notified by the central government.  The Bill increases the threshold of annual passenger traffic for major airports to over 35 lakh. 

Tariff determination by AERA:  Under the Act, AERA is responsible for determining the: (i) tariff for aeronautical services every five years, (ii) development fees, and (iii) passengers service fee.  It can also amend the tariffs in the interim period.  The Bill adds that AERA will not determine: (i) tariff, (ii) tariff structures, or (iii) development fees, in certain cases.  These cases include those where such tariff amounts were a part of the bid document on the basis of which the airport operations were awarded.  AERA will be consulted (by the concessioning authority, the Ministry of Civil Aviation) before incorporating such tariffs in the bid document, and such tariffs must be notified.

Why is the Act getting amended?

The Statement of Objects and Reasons of the Bill states that the exponential growth of the sector has put tremendous pressure on AERA, while its resources are limited.  Therefore, if too many airports come under the purview of AERA, it will not be able to perform its functions efficiently.  If the challenge for AERA is availability of limited resources, the question is whether this problem may be resolved by reducing its jurisdiction (as the Bill is doing), or by improving its capacity. 

Will the proposed amendments strengthen the role of the regulator?

When AERA was created in 2008, there were 11 airports with annual passenger traffic over 15 lakh.  With increase in passenger traffic across airports, currently 32 airports are above this threshold.  The Bill increases the threshold of annual passenger traffic for major airports to over 35 lakh.  With this increase in threshold, 16 airports will be regulated by AERA.  It may be argued that instead of strengthening the role of the regulator, its purview is being reduced. 

Before AERA was set up, the Airports Authority of India (AAI) fixed the aeronautical charges for the airports under its control and prescribed performance standards for all airports and monitored them.  Various committees had noted that AAI performed the role of airport operator as well as the regulator, which resulted in conflict of interest.  Further, there was a natural monopoly in airports and air traffic control.  In order to regulate the growing competition in the airline industry, and to provide a level playing field among different categories of airports, AERA was set up.  During the deliberations of the Standing Committee examining the AERA Bill, 2007, the Ministry of Civil Aviation had noted that AERA should regulate tariff and monitor performance standards only at major airports.  Depending upon future developments in the sector, other functions could be subsequently assigned to the regulator.

How would the Bill affect the regulatory regime?

Currently, there are 32 major airports (annual traffic above 15 lakh), and AERA regulates tariffs at 27 of these.  As per the Bill, AERA will regulate 16 major airports (annual traffic above 35 lakh).  The remaining 16 airports will be regulated by AAI.  Till 2030-31, air traffic in the country is expected to grow at an average annual rate of 10-11%.  This implies that in a few years, the traffic at the other 16 airports will increase to over 35 lakh and they will again fall under the purview of AERA.  This may lead to constant changes in the regulatory regime at these airports.  The table below provides the current list of major airports:

Table 1: List of major airports in India (as on March 2019) 

Airports with annual traffic above 35 lakh Airports with annual traffic between 15 and 35 lakh

Ahmedabad

Goa

Mumbai

Amritsar

Madurai*

Srinagar

Bengaluru

Guwahati

Patna

Bagdogra

Mangalore

Trichy*

Bhubaneswar

Hyderabad

Pune

Calicut

Nagpur

Varanasi

Chennai

Jaipur

Thiruvananthapuram

Chandigarh

Port Blair*

Vishakhapatnam

Cochin

Kolkata

 

Coimbatore

Raipur*

 

Delhi

Lucknow

 

Indore

Ranchi*

 

* - AERA does not regulate tariffs at these airports currently. 

Sources: AAI Traffic News; AERA website; PRS.

On March 14, 2022 Rajya Sabha discussed the working of the Ministry of Development of North Eastern Region (DoNER).  During the discussion, several issues around budgetary allocation, implementation of schemes and connectivity with the North Eastern Region were discussed.  The Ministry of DoNER is responsible for matters relating to the planning, execution and monitoring of development schemes and projects in the North Eastern Region.  In this blog post, we analyse the 2022-23 budgetary allocations for the Ministry and discuss related issues.  

A new scheme named PM-DevINE announced to boost infrastructure and social development

In 2022-23, the Ministry has seen a 5% increase in allocation from the revised estimates of 2021-22.  The Ministry has been allocated Rs 2,800 crore which will be used for various development schemes, such as the North East Special Infrastructure Development Scheme and North East Road Sector Development Scheme.  A scheme-wise break-up of the budget allocation for the Ministry is given below in Table 1.  

One of the key highlights of the Finance Minister’s Budget Speech was the announcement of a new scheme named the Prime Minister’s Development Initiative for North East (PM-DevINE).  It will be implemented through the North East Council (nodal agency for the economic and social development of the North Eastern Region).  PM-DevINE will fund infrastructure and social development projects in areas such as road connectivity, health, and agriculture.  The scheme will not replace or subsume existing central sector or centrally sponsored schemes.  The Scheme will be given an initial allocation of Rs 1,500 crore.

Table 1: Break-up of allocation to the Ministry of DoNER (in Rs crore)

Major Heads

2020-21 Actuals

2021-22 BE

2021-22 RE

2022-23 BE

% change from 2021-22 RE to 2022-23 BE

North East Special Infrastructure Development Scheme

446

675

674

1,419

111%

Schemes of North East Council

567

585

585

702

20%

North East Road Sector Development Scheme

416

696

674

496

-26%

Central pool of resources for North East and Sikkim

342

581

581

-

-

Others

270

322

344

241

-30%

Total

1,854

2,658

2,658

2,800

5%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: BE – Budget Estimate; RE – Revised Estimate; Schemes for North East Council includes Special Development Projects.

Sources: Demand No. 23 of Union Budget Documents 2022-23; PRS. 

Allocation towards capital outlay less than demand

The Standing Committee on Home Affairs (2022) noted that the amount allocated at the budget stage in 2022-23 (Rs 660 crore) was 17% less than the demand by the Ministry (Rs 794 crore).  Capital expenditure includes capital outlay which leads to the creation of assets such as schools, hospitals, and roads and bridges.  The Committee observed that this may severely affect the implementation of several projects and schemes that require capital outlay.  It recommended the Ministry to take up this matter with the Finance Ministry and demand additional assistance at the revised stage of the 2022-23 financial year.

Underutilisation of funds over the years

Since 2011-12 (barring 2016-17), the Ministry has not been able to utilise the funds allocated to it at the budgeted stage (See Figure 1).  For instance, in 2020-21, fund utilisation in case of the North East Road Sector Development Scheme was 52%, whereas only 34% of funds were utilised under the North East Special Infrastructure Development Scheme (for infrastructure projects relating to water supply, power, connectivity, social infrastructure).  Key reasons for underspending highlighted by the Ministry include late receipt of project proposals and non-receipt of utilisation certificates from state governments.

Figure 1: Underutilisation of funds by the Ministry since 2011-12

image
 Note: Revised Estimate has been used as the Actual Expenditure for 2021-22.
 Sources: Union Budget Documents (2011-12 to 2022-23); PRS
.

Delay in project completion

The Ministry implements several schemes for infrastructural projects such as roads and bridges.  The progress of the certain schemes has been inadequate.   The Standing Committee (2022) observed that the physical progress of many road sector projects under the North East Road Sector Development Scheme is either at zero or in single digit percent in spite of release of the amount for the project.  Similarly, projects under the Karbi Anglong Autonomous Territorial Council (autonomous district council in Assam) and Social and Infrastructure Development Fund (construction of roads, bridges, and construction of schools and water supply projects in the North Eastern Region) have seen inadequate progress.

Need to address declining forest cover

The Standing Committee (2021) has also recommended the Ministry of DoNER to work towards preserving forest cover.  The Committee took note of the declining forest cover in the North East India.  As per the India State of Forest Report (2021), states showing major loss of forest cover from 2019 to 2021 are: (i) Arunachal Pradesh (loss of 257 sq km of forest cover), (ii) Manipur (249 sq km), (iii) Nagaland (235 sq km), (iv) Mizoram (186 sq km), and (v) Meghalaya (73 sq km).  The loss of forest cover may be attributed to shifting cultivation, cutting down of trees, natural calamities, anthropogenic (environmental pollution) pressure, and developmental activities.  The Committee recommended that various measures to protect the forest and environment must be given priority and should implemented within the stipulated timeline.  It also suggested the Ministry to: (i) carry out regular plantation drives to increase forest cover/density, and (ii) accord priority towards the ultimate goal of preserving and protecting the forests under various centrally sponsored initiatives.

Key issues raised by Members during discussion in Rajya Sabha

The discussion on the working of the Ministry of DoNER took place in Rajya Sabha on March 14, 2022.  One of the issues highlighted by members was about the Ministry not having its own line Department.  This leads to the Ministry being dependent on the administrative strength of the states for implementation of projects.  Another issue highlighted by several members was the lack of connectivity of the region through railways and road networks which hampers the economic growth of region.  The DoNER Minister in his response to the House assured the members that the central government is making continuous efforts towards improving connectivity to the North East region through roads, railways, waterways, and telecommunication.         

Allocation by Union Ministries to the North East 

Union Ministries allocate 10% of their budget allocation for the North East (See Figure 2 for fund allocation and utilisation).  The Ministry of DoNER is the nodal Ministry that monitors and keeps track of the allocation done by various Ministries.  In 2022-23, Rs 76,040 crore has been allocated by all the Ministries for the North Eastern region.  The allocation has increased by 11% from the revised estimate of 2021-22 (Rs 68,440 crore).   In 2019-20 and 2021-21 the actual expenditure towards North Eastern areas was lower than budget estimates by 18% and 19% respectively.  

Figure 2: Budgetary allocation by all Union Ministries for the North East (amount in Rs crore)

image   

Source: Report No. 239: Demand for Grants (2022-23) of Ministry of Development of North Eastern Region, Standing Committee on Home Affairs; PRS.