Most legislative assemblies make Parliament look like a paragon of virtue A COUPLE of days ago, an MLA from Orissa made news for climbing on to the speaker's table in the assembly. Not so long ago, television screens beamed images of Karnataka MLAs snacking and sleeping all night in the assembly. But these are only indicative of the incidents of the raucous behaviour of several MLAs in the recent past across the country. And the poor behaviour of some MLAs is only one aspect of the pitiable state of several of our state legislatures. The other aspect of our state legislatures that goes largely unnoticed is how poorly the secretariats of legislatures are equipped and how several systems that are seen as essential in Parliament are nonexistent in states. Even to know the complete picture of how our legislatures function, you need data. And several state assemblies are notoriously poor at putting out data on the functioning of the institution or the MLAs. After one gets used to the quality of Parliament websites and the regularity of their updates, it would be shocking to see that there are some state legislatures that do not even have functional websites. It has been observed that some state legislatures are lagging behind by a couple of years in compiling the "resume of work" which summarises the work done in a session of the legislature. So the first bottleneck in several instances is the inability to access data of the assembly. From the data we have managed to access, it is obvious that state assemblies meet for very few days a year. A case in point is the Punjab assembly which has met for an average of 19 days per year for a 10-year period between 1997 and 2007. Delhi was only marginally better averaging 21 days per year during the same period. Kerala has averaged some 50 days a year for several years now. Some states like Karnataka have legislated that they should meet for at least 60 days a year, but since passing that legislation in 2005, they have not managed to do so for even one year. I am not even accounting for the time lost due to disruptions. Bills are passed with little or no discussion in many state legislatures. While in Parliament, referring bills to the standing committees is the norm, most state legislatures do not have standing committees. The only examination of a bill, if any, happens on the floor of the House. And if data from the Delhi assembly is anything to go by, the average debate on a bill before is passed is a little over half hour. There are any number of instances where bills are introduced and passed in state assemblies on the same day -so there is not even a pretence of the need for MLAs to read, understand and deliberate on the provisions of legislation they are supposedly passing. MLAs are often far more narrowly constituency-focused than MPs are. On average, MLAs have lower education levels than members of Parliament. There is no formal definition of a role of an MLA, and they mostly have no exposure to ideas such as the separation of powers between the executive and the legislature. In one particularly revealing conversation with an MLA, he said, "At the time of elections, each of the contestants represents his party. But after the elections, the chiefministerbecomestheleader of all MLAs in the House. If an MLAneedssomeadditionalprojects/ favours for his constituency he needs to be in the good books of the chief minister and his cabinet ministers. So where is the question of taking on the chief minister on the floor of the House on any issue?" There are many aspects of state legislatures that point to a steady and visible decline of these important institutions. But beyond the frequent highlighting of theatrics by some MLAs, there is almost no public discourse on this issue. It is necessary to ensure that the legislatures run smoothly, and the speaker, as first among equals, has the biggest responsibility to ensure this. If there are rules and everyone knows that those rules will never be used to enforce discipline, then the rules will be broken, and repeatedly so. This practice needs to be urgently reviewed. The larger question is whether our legislatures are the highest deliberating and policymaking bodies or whether they are being reduced to platforms for political theatrics. Policy can almost never be devoid of politics and public posturing. But if this means poor deliberation of critical policy issues and the woefully inadequate functioning of our legislatures, then we may need to come up with creative ways in which this problem can be addressed. This article appeared in the Indian Express on December 20, 2010.

In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.