This month, PRS Legislative Research is 5 years old! The objective when we started out was to make the legislative process in India better informed, more transparent and participatory.  From what started off as an idea, we believe we have made some progress towards our objective. -       About 250 MPs across political parties have reached out to PRS for inputs on a range of issues that have come up in Parliament.  In addition, there are a number of MPs who use PRS material for their preparation in Parliament, even though they have not contacted PRS for further inputs. -       PRS has increasingly become a resource for the media as well.  Over the past year, PRS has been cited on nearly 400 occasions by leading newspapers and websites as the source of information about legislation and Parliament. These are some of the milestones that we feel happy to have reached.  But I want to really share are some of the learnings that we have had over these years. The first thing that we have learned is that many of us carry so many wrong perceptions about our MPs. Most of us don’t know that more than 80 percent of our MPs have college degrees.  Most of us don’t know that the average attendance rate in Parliament is close to 80 percent in the past year.  Most of us don’t know that Parliament has worked for more than 90 percent of the scheduled time in recent sessions, despite the undesirable disruptions in Parliament. There is a lot that is wrong with our politics, but we hope that some of these facts throw light about some lesser known aspects about our MPs. Laws are made for the really long term! That seems obvious, when we see examples such as our Indian Penal Code which was made in 1860, and the Land Acquisition Act that has haunted our country in recent years was passed in 1894.  And these are just some examples.  The fact is that if we do not debate our laws when they are being made, and citizens do not engage and provide inputs to this process, then we will be stuck with any issues that these laws might have for the next 100 years or more.  So it is critical to get the laws as close to ‘right’ as possible when they are being passed. It is not obvious to most people that so many MPs put in significant effort to engage effectively in Parliament. Clearly, there is a selection bias, statistically speaking – I am talking of MPs who have reached out to us.  Despite this selection bias, the point is that there are a number of MPs who take their work in Parliament seriously, even though they know that much of the work they do in Parliament has almost no bearing on their re-election prospects.  (By the way, in most informal polls that I have done when I meet with groups of people, most do not know the role of an MP – even amongst some of the well educated groups.) Why do so many MPs still work hard to prepare for their work in Parliament, despite knowing that this work has no bearing on their re-election prospects? On this, we can only hypothesize.  There are many MPs who understand their role as legislators and take it very seriously.  There are MPs who feel that making a good point on an issue on the floor of Parliament is a way to establish their grasp of a certain issue to their colleagues in Parliament, but also to the larger world.  For some others, it is a signalling device to their party colleagues about their interest and expertise in a certain subject area.  And we have had MPs who have said, that they feel very good when other MPs, especially from other parties, compliment them for making a good point.  All of these sound like good positive reasons for many MPs to want to be well prepared to speak in Parliament. We have begun to appreciate that the role of the MP in Parliament is very challenging. I can point to at least three reasons, which are independent of how educated or capable an MP might be: (a) The range of subjects in Parliament is so wide that no individual, however intelligent, can be fully conversant with all the subjects being discussed.  (b) MPs have no research staff whatsoever, and are expected to do all of their preparatory work on their own, and (c) The constituency pressure on the MPs is often very high, making it difficult for them to pay adequate attention to their work in Parliament. We most certainly want more from our MPs and our Parliament. We want our MPs to meet for more days, find better ways to raise issues in Parliament than to disrupt proceedings, debate in more detail the laws that they pass.  But what we have learned is that we cannot throw the baby out with the bath water.  So, I am not suggesting that we can’t do better or that our MPs or our Parliament are perfect.  The only way we will have a better Parliament is if we engage.  And more people engage – from all walks of life.  Policy making is not the exclusive preserve of either the expert or the policy maker.  The policy process can be greatly strengthened if we participate in the process and ensure that our MPs know that we want effective laws to govern us and our children. Parliament can be made more effective by addressing some of the current bottlenecks. And some of these issues are not even difficult to fix.  For example, can we have more people in the committee staff to support the work of the standing committees in Parliament so they can cover more ground in any given year?  Can we have qualified research staff working for MPs so that they can go better prepared for Parliament?  (Our Legislative Assistants to MPs – LAMPs programme has shown that it is hugely rewarding for young legislative assistants and the MPs if such a platform is created.)  Can we have recorded voting on all legislative votes, instead of voice votes – the electronic button system is already in place to do this!  These are just some examples… and we at PRS have a laundry list of ideas for strengthening Parliament – with varying degrees of difficulty.  We have raised some of these issues in our Annual Conference of Effective Legislatures, and will continue to do so in the years ahead. A very BIG thanks to each of you for making PRS possible over these past five years… We hope that you will continue to bless and support us in the years ahead to help shape a more robust policy making process in India. PRS PRODUCTS The Legislative Briefs are our flagship product.  Each Brief analyses one Bill pending in Parliament.  These are no longer than 6 pages and are sent to all MPs.  We then get calls from MPs asking for more information/ clarification. Since earlier this year PRS has begun a Wednesday morning Policy Dialogue series exclusively for MPs.  These are widely attended by MPs across parties. PRS is the knowledge partner to brief MPs in the Thursday morning Bill briefing sessions organised by the Constitution Club. PRS has reached out to about 1000 journalists across the country, through journalist workshops and direct engagement. PRS has started the Legislative Assistants to MPs (LAMPs) programme as a pilot initiative.  Under the programme, participating MPs get a trained legislative assistant for a period of three Parliament sessions. PRS produces Primers to demystify Parliamentary process for citizens. These are widely used in our interactions with civil society groups. The Vital Stats series is a crisp two page document that often highlights interesting aspects of Parliament.  They are very popular with journalists. PRS has nearly 1000 fans on Facebook and 2000 followers on Twitter, including some MPs. PRS has a Session Alert at the beginning of each session of Parliament.  On the last day of each session, PRS releases two reports on the just concluded session: Parliament Session Wrap and Plan vs. Performance. PRS hosts an Annual Conference of Effective Legislatures each year to highlight certain aspects of the functioning of Parliament. PRS has compiled a free online database of all state laws across the country.  This effort www.lawsofindia.org is the first effort of its kind in India. The PRS website www.prsindia.org has become an important resource for anyone tracking the Indian Parliament both within the country and abroad.

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.