Highlights

  • Coal-based plants account for 43% of installed capacity and generate 71% of electricity.  Solar and wind generate 13% of electricity with a 37% share in installed capacity.  Their intermittent nature means that increasing their share in generation needs to be carefully sequenced to maintain grid stability.

  • In 2024-25, 58% of targeted transmission lines were added.  The sector remains import-dependent for critical materials used in transmission infrastructure.

  • Distribution utilities continue to incur losses, although losses have come down in recent years.  Losses are due to factors such as underpricing of tariffs and higher technical and commercial losses.

Power is under the concurrent list of the Constitution.[1]  Both the central and state government implement programmes and schemes on the subject.  The Ministry of Power is responsible for policy formulation and implementation for the electricity sector at the central level.[2]  The Ministry of New and Renewable Energy (MNRE) works towards promotion and development of renewable sources such as solar and wind.[3] 

These Ministries also administer several public sector undertakings.  As of December 2025, 23% of the generation capacity is owned by the central PSUs such as NTPC and NHPC.[4]   Another 22% is owned by the state government-owned entities.4  In 2024-25, 93% share of the distribution by both revenue earned and volume of energy sold was undertaken by state government-owned entities.[5]  This note analyses budgetary allocation and expenditure trends of the two ministries and discusses key issues.

Overview of Finances

Ministry of Power:  In 2026-27, the Ministry of Power has been allocated Rs 29,997 crore, an increase of 39% over the revised estimate of 2025-26.[6]  About 1% of this allocation is towards capital expenditure.6  60% of the total expenditure has been allocated towards the Revamped Distribution Sector Scheme (RDSS).6  This scheme was launched in 2021 to provide support to distribution companies for improving financial and operational performance.[7]  A key component of RDSS is the assistance for installation of prepaid smart meters.  Other key heads of allocation are: (i) assistance to central public sector undertakings for power projects (25% of the allocation), (ii) transfers to Power System Development Fund (PSDF) (4%), which is utilised for creating transmission systems,

Key announcements in Budget Speech 2026-27

  • Custom duty exemptions:  The central government will exempt basic customs duty on capital goods used in cells of battery energy storage.  Also, duty exemptions for nuclear power project imports is extended till 2035.

  • Restructuring of PFC and RFC:  Power Finance Corporation (PFC) and Rural Electrification Corporation (REC) will be restructured in accordance with the Viksit Bharat vision for Non-Banking Financial Corporations.

  • Dedicated rare-earth corridors:  The central government will establish rare-earth corridors to promote mining, processing, research, and manufacturing.

  • Carbon Capture Utilisation and Storage:  An outlay of Rs 20,000 crore is proposed for the Carbon Capture Utilisation and Storage (CCUS) technologies over the next five years.  

and (iii) viability gap funding for development of battery energy storage system (3%).6

Ministry of New and Renewable Energy:  In 2026-27, the Ministry of New and Renewable Energy (MNRE) has been allocated Rs 32,915 crore, an increase of 30% from the revised estimate of 2025-26.[8]  The increase is driven by higher allocations towards PM Surya Ghar Muft Bijli Yojana (an increase of Rs 5,000 crore).8  The scheme was approved in February 2024. [9]  It provides financial assistance to households for installing rooftop solar.9

 Table 1: Allocations towards Ministries of Power and New & Renewable Energy (in Rs crore) 

Head

2024-25 Actuals

2025-26 RE

2026-27 BE

% change (25-26 RE to 26-27 BE)

Power

19,714

21,588

29,997

39%

of which

 

 

 

 

RDSS

12,974

15,671

18,000

15%

Assistance to PSUs

2,980

2,732

7,401

171%

Power System Development Fund

1191

1100

1103

0%

MNRE

18,627

25,301

32,915

30%

of which

 

 

 

 

PM Surya Ghar

7,818

17,000

22,000

29%

Solar Power (Grid)

6,583

1,000

1,775

78%

PM KUSUM

2,560

5,000

5,000

0%

Wind Power (Grid)

800

500

500

0%

Green Hydrogen

301

300

600

100%

Note: BE: Budget Estimates; RE: Revised Estimates.
Sources: Demand No. 71 and 79, Expenditure Budget, Union Budget 2026-27; PRS.

Trends in fund utilisation over the years

Ministry of Power:  The fund utilisation by the Ministry of Power has seen wide fluctuations over the last decade (see Figure 1).  In 2022-23, the actual expenditure by the Ministry was 42% lower than budgeted.  This was mainly driven by lower fund utilisation under RDSS (64%).  In the previous year (2021-22), the actual expenditure was 41% higher than the budget expenditure.  This was due to higher expenditure on multiple schemes such as Integrated Power Development Scheme (IPDS), Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGY), and programmes including those on strengthening of power systems.  In 2025-26, as per revised estimates, the overall expenditure by the Ministry of Power is 1% lower than budgeted.

Figure 1: Fund utilisation by Power Ministry

Note: For 2025-26, revised estimate taken as actuals. 
Source: Demands for Grants of Ministry of Power for various years; PRS.

Ministry of New and Renewable Energy:   Over the last decade, actual expenditure by MNRE has generally been lower than the budget estimate, except in 2021-22 and 2022-23.  In 2023-24, the overall expenditure by MNRE was 22% lower than budgeted.  For the subsequent year, 2024-25, underutilisation decreased (2%).  In 2025-26, as per the revised estimates, spending by the Ministry is estimated to be 5% lower than budgeted.  Expenditure under PM-KUSUM is expected to be 92% higher than budgeted in 2025-26.  Expenditure under PM Surya Ghar is estimated to be 15% lower than the budget estimate.  PM-KUSUM provides for solarisation of agricultural pumps and feeders (see next page for more discussion on these schemes).[10]

Figure 2: Fund utilisation by MNRE

Note: For 2025-26, revised estimate taken as actuals.  
Source: Demands for Grants of MNRE for various years; PRS.

Key Schemes

Revamped Distribution Sector Scheme

The Revamped Distribution Sector Scheme (RDSS) was launched in 2021.[11]  It aims to strengthen the distribution infrastructure and reduce the aggregate technical and commercial (AT&C) losses to pan-India level of 12-15%.[12]  AT&C losses refer to the ratio of power for which the distribution company (discom) did not receive any payment to the total electricity procured by the discom. 

A key part of RDSS is the provision of financial assistance to discoms for prepaid smart consumer and system metering.12  This assistance is to be based on meeting a stipulated pre-qualifying criteria and achieving a basic minimum benchmark in reforms.12  Most of the smart meters under RDSS are installed and maintained by private entities called Advanced Metering Infrastructure Service Providers (AMISPs) under long-term contracts with discoms.13  Smart meters are being installed at consumer as well as system level.12  However, there has been limited rollout of smart meters under the scheme.  The scheme targeted to install 10 crore smart meters in its first phase.7  As of January 8, 2025, 22 crore consumer meters have been sanctioned under RDSS.[13]  Contracts have been awarded for 15 crore consumer meters and five crore consumer meters have been installed.13  In six states, consumer meters have been sanctioned but deployment is yet to begin.13  Further, in states such as Andhra Pradesh, Gujarat, and Tamil Nadu, not all installed meters are connected to the system.[14]   

Table 2: Status of Smart metering across India (as of December, 2025)

Type

Sanctioned

Achievement

In number

In %

Consumer Meters

22 crore

5 crore

23%

Distribution Transformer Meters

53 lakh

13 lakh

25%

Feeder Meters

2 lakh

1.6 lakh

77%

Source: All India Smart Metering Status, Website of National Smart Grid Mission of Ministry of Power, as accessed on December 31, 2025; PRS.

One of the reasons for low number of installed smart meters may be their high costs.  Under this scheme, central government provides a performance-linked grant to discoms for smart metering.[15]  This grant is at the rate of 15% of the cost per smart meter (or 22.5% for special category states).15  The grant is subject to a maximum of Rs 900 per smart meter (or Rs 1,350 for special category states).15  However, the cost of smart meters in several states discovered during the bidding process ranges between Rs 7,000-Rs 16,000.14  Discoms with financial issues may be unable to cover the remaining costs which may contribute to delays in installations.  The recovery of smart meter costs from low-consumption and subsidised consumer categories may be also limited, as revenue from such consumers are low.   

Delays have also been observed in implementation phases of smart metering.  These include: (i) delays in issue of tenders and establishment of direct debit facilities and (ii) delays in field testing and approvals.[16]  Smart meters can also facilitate large scale integration of renewable power and enable time of day tariffs.[17]  However, states such as Gujarat and Tamil Nadu that have high variable renewable energy (such as solar and wind), have made limited progress in smart meter rollouts (see Table 6 in Annexure).13,[18]    

PM KUSUM Scheme

The scheme aims to provide financial support for the installation of small solar power plants on barren agricultural land, and solarisation of agriculture pumps.[19]  It seeks to achieve a solar capacity of 35 GW.19  Originally, this capacity was to be added by 2022.3  The target has been revised to 2025-2026.[20]  The Standing Committee on Estimates (2025) observed delays in capacity additions.[21]  Some of the reasons for poor adoption include: (i) limited availability of low-cost finance, (ii) absence of central financial assistance for small solar plants, and (iii) lack of subsidy for solar pumps with capacities above 7.5 horsepower.21  Higher capacity pumps are used in regions with low groundwater.21

Table 3: Sanctioned vs Installed under the PM-KUSUM Scheme (as of February 2026)

Parameter

Sanctioned

Installed

In unit

In %

Grid-connected decentralised solar power plants

10,000 MW

765 MW

8%

Stand-alone solar pumps

13 lakh

10 lakh

76%

Grid-connected solar pumps

55,392

12,311

22%

Source: Achievement Dashboard, National Portal PM-KUSUM, as accessed on February 9, 2026; PRS.

PM Surya Ghar Scheme  

PM-Surya Ghar Muft Bijli Yojana was approved in February 2024 with the aim of installing rooftop solar in one crore households by 2026-27.9,[22]  Under this scheme, financial assistance is provided in the form of central financial assistance (CFA) and a collateral free loan.  As of December 9, 2025, rooftop solar systems have been installed in 24 lakh households (24% of the target met).22 

Key reasons for slow progress under the scheme include: (i) high rejection rate of loan applications particularly due to unclear house ownership status, (ii) limited consumer awareness about the scheme, and (iii) inadequate availability of empanelled vendors responsible for facilitating approvals and installations.21,[23]  Further, the scheme has made it mandatory to install solar modules manufactured in the country to avail financial support.21  However, Standing Committee on Estimates (2025) noted that domestic manufacturing capacity is insufficient.21

National Green Hydrogen Mission

The Mission aims to build domestic capabilities to produce green hydrogen and reduce dependence on fossil fuels.[24]  Green Hydrogen is hydrogen produced using renewable energy, such as solar power.25  The Mission seeks to provide a scalable fuel alternative for sectors such as steel.24,[25]  It targets annual production of five million metric tonnes (MMT) of green hydrogen by 2030.25  As of December 16, 2025, 18 companies have been awarded a cumulative production capacity of 0.86 million tonnes per annum.[26]

There are certain issues with development of green hydrogen.  First, producing green hydrogen requires fresh water.24  More than 35% of the global green and blue hydrogen (blue hydrogen is produced using fossil fuels) production capacity (in operation and planned) is located in highly-water stressed regions.[27]  India is estimated to have 99% of its hydrogen capacity in extremely water-stressed areas by 2040.27  While sea water can also be used, it requires development of processing infrastructure.24 

Production of green hydrogen is also an expensive process.24  The price of grey hydrogen (fossil fuels are used to produce grey hydrogen) in 2025 ranges between USD 1.5 to 3 per kg compared to USD 3 to 6 per kg for green hydrogen.[28]  High costs are partly due to components such as electrolysers used in the production of green hydrogen.[29]  The cost of the electrolysers has increased in the last few years due to higher prices of input materials and slower deployment of the technology.29,[30]  Although technology advancements, and falling solar and wind prices is expected to bring down the prices.29,[31] 

Hydrogen (including green hydrogen) also has a low volumetric energy density.[32]  This means that storing and transporting hydrogen requires larger tanks or additional compression or liquefaction compared to other fuels.  The costs of hydrogen distribution and storage can increase the production cost by three times when developed and utilised for individual projects in industries.28  Thus, hydrogen storage for various applications remains a challenge.[33]

Issues for Consideration

Generation capacity

In India, various sources of energy are used to generate power.[34]  These include fossil fuels (such as coal and natural gas), nuclear energy, and renewable sources (such as solar and wind).34  The energy sector is heavily reliant on non-renewable thermal sources (such as coal and natural gas), which together account for largest share of the country’s electricity generation capacity.34  Coal accounted for about 43% of total installed capacity as of December, 2025.4  The share of coal during 2024-25 in total electricity generation was about 71%.[35],[36]  Renewable sources (solar, wind, and hydro) accounted for 22% of total electricity generation.35  

As per its climate change related commitments, India also aims to achieve: (i) 500 GW of installed electricity capacity from non-fossil fuel sources by 2030 and (ii) 50% of its energy requirements from renewable energy by 2030.[37]  The Central Electricity Authority (CEA) (2023) projected that much of the renewable energy capacity will come from solar and wind.39  44% of the total generation is expected to be met from these two sources by 2031-32.39  To meet these targets, installed capacity as well as related storage capacity needs to be increased.

Demand is projected to grow from the all-India peak electricity demand of 250 GW in 2024-25 to 366 GW in 2031-32.[38],[39]  CEA estimates that in order to meet the estimated electricity demand by 2031-32, coal and lignite based installed capacity would also need to be increased to support the base load requirements.[40]  The following sections discusses certain issues related to different sources of power.        

Table 4: All-India installed capacity and electricity generation

Source

Generation (in BU)

Installed Capacity (in GW)

2024-25

December 2025

March 2032 Projected

 

In %

 

In %

 

In %

Solar

144

8%

136

26%

365

42%

Coal and Lignite

1,332

73%

226

44%

260

30%

Wind

83

5%

55

11%

122

14%

Large Hydro
(>25 MW)

149

8%

51

10%

62

7%

Gas

31

2%

20

4%

25

3%

Nuclear

57

3%

9

2%

20

2%

Biomass

16

1%

12

2%

16

2%

Small Hydro
(<=25 MW)

12

1%

5

1%

5

1%

Diesel

0.4

0%

1

0%

-

-

Total

1,824

 

515

-

875

-

Source:  Monthly Renewable Energy Generation Report (March 2025), Central Electricity Authority (CEA); Installed Capacity Report for November 2025, CEA; National Electricity Plan, Vol I, March 2023, CEA; PRS.      

Figure 3: 75% of electricity generation in 2023-24 was from coal 

Source: India Energy Statistics 2025, MoSPI; India Climate and Energy Dashboard, Niti Ayog; PRS.

Thermal power

Declining coal power plant utilisation  

In 2009-10, plant load factor (PLF) for coal and lignite plants was 84%, which has come down to 69% in 2024-25.[41],[42]  PLF is a measure of the output of a power plant compared to the maximum output it could produce.  The decrease in PLF may be due to: (i) availability of surplus capacity in certain regions, (ii) low demand for power, (iii) demand being met from other sources such as renewables, and (iv) unavailability of fuel.  Poorer capacity utilisation may increase the unit cost of electricity generation from these plants and may also present the challenge of financial viability for them.  CEA has projected that PLF of coal-based power plants will be around 58-59% till 2031-32.39

Thermal power capacity addition targets missed

The central government has proposed to set up additional 80 GW of coal based thermal power capacity between 2024-25 and 2031-32 to meet projected demand.40  However, the capacity additions for thermal power between 2021-22 to 2024-25 have been below target (see Figure 4).  Key reasons for shortfall include: (i) frequent litigations related to land compensation, and (ii) non-performance of sub-contractors at site and re-tendering of some Balance of Plant (BoP).[43]  BoP refers to all auxiliary systems and equipment, apart from the core components such as boiler, required for the operation of a power plant. 

As of 2025, the total thermal capacity on hold or unlikely to be commissioned is about 21 GW.[44]  The vast majority belongs to the private sector.44  Delays in projects may lead to cost overruns.  There are multiple reasons for these delays or dropouts.  These include: (i) withdrawal of Power Purchase Agreements (PPAs) by discoms due to land-related issues at associated mines which increased costs and electricity prices, and (ii) delays by Engineering, Procurement, and Construction (EPC) contractors.44

Figure 4: Thermal capacity additions missed in the past five years (in MW)

 

Source: Thermal Broad Status Report 2025, CEA; PRS.

Nuclear Energy

The central government launched the Nuclear Energy Mission in February 2025.[45]  It aims to achieve 100 GW of nuclear power capacity by 2047 through deployment of new nuclear reactors.45  As of November 2025, India operates 24 nuclear reactors with the total installed capacity of 8.8 GW.[46] It’s share in the total electricity generation has remained stable at around 2-3% between 2014-15 to 2024-25.46,[47]  In December 2025, parliament passed a Bill to enable private participation in nuclear power plant operation and handling of nuclear fuel.46  Some challenges associated with nuclear energy industry include limited uranium reserves, high upfront capital costs, longer lead times, and safety concerns in transportation, storage and disposal of used fuels.[48],[49] 

Renewable energy

Fossil fuels such as coal are the major source of power used in the country.34  Coal has a 43% share in the total installed power generation capacity.4        For 2024-25, the share of coal in generation was 71%.36,[50]  In comparison, solar and wind, the two major sources of renewable energy, had a share of 37% in total installed capacity.4  However, in 2024-25, they contributed only 13% of the total electricity generation.35,50  This may be because solar energy can be generated only during sunny days and wind energy generation is intermittent based on wind conditions such as wind speed.

As of December 2025, installed capacity of solar and wind stood at 136 GW and 55 GW, respectively.[51]  In December 2025, the Ministry noted that another 69 GW of solar and 30 GW of wind capacity is under implementation.[52]  A further 35 GW of solar and 1.8 GW of wind capacity has been tendered.52

The Economic Survey (2025-26) observed that higher share of renewable energy may pose challenges to grid stability and increase cost of maintaining dispatchable thermal capacity.[53] 

Figure 5: Capacity Addition since 2022-23: Projected vs Actual (in GW)

Source: Installed Capacity Report, Central Electricity Authority; National Electricity Plan, Central Electrical Authority; PRS.

Pending sale agreements for solar

The Renewable Energy Implementing Agencies (REIAs) such as SECI signs PPAs with power developers to procure renewable energy.[54]  It then signs a Power Sale Agreement (PSA) with power purchasers such as discoms.54  As of September 2025, about 44 GW of solar capacity that was awarded through bids by REIAs remains without signed PSA.[55]  Delays in the signing of PSA may slow down the use of solar capacity awarded.  Key reasons for unsigned PSA include: (i) limited procurement of renewable power despite Renewable Purchase Obligation (RPO) (RPO mandates discoms to procure a certain percentage of electricity from renewables), (ii) steep increase in the renewable energy bids by REIAs since 2023-24, and (iii) state discom’s expectation for decrease in renewable energy tariffs in future bids.23 

Import dependence in components of solar panels

As of June 2025, the total solar panel manufacturing capacity in India stood at 91 GW.23  Domestic manufacturing of components used in solar panels manufacturing such as polysilicon, ingots, and wafers remains limited.23  In the case of polysilicon, which is a critical component in development of solar panels, the Standing Committee on Energy (2025) noted that the country has no manufacturing capability.23  In the absence of adequate domestic production of these components, there is heavy dependence on imports from countries such as China.[56],[57]  Some of the reasons for lack of domestic capacities include the capital-incentive nature of production and lack of skilled manpower to manufacture components such as polysilicon.[58] 

Availability of critical minerals

Critical minerals such as lithium, copper, and silver are used in the manufacturing of materials such as solar panels and energy storage systems.53  For example, solar panels with a power capacity of 1 GW require approximately 19 tons of silver.53  Wind turbines of 1 GW capacity require 2,866 tons of copper.53  India imports a large amount of minerals such as copper and silver.[59]  The Economic Survey 2025-26 observed that prices of metals such as copper is becoming highly price-volatile due to mine outages in multiple countries amidst the growing demand.53  Further, affordability of materials using these minerals can be adversely impacted due to increased mineral prices and absence of parallel financial support and capacity building.53

The central government notified a National Critical Mineral Mission in June 2025.[60]  It aims to strengthen India’s critical mineral supply chain by ensuring availability domestically and from abroad.  Under the Mission, the government seeks to launch 1,200 exploration projects and auction over 100 mineral blocks to increase domestic supply.[61]  As of December 3, 2025, the central government auctioned 34 blocks of critical minerals.[62]  The total exploration projects under Geological Survey of India were 230 in 2025-26 across the country (up to December 3, 2025).62  

Slower wind capacity growth

India had set a target of achieving installed capacity of 60 GW of wind power by 2022.[63]  CEA has projected the addition of another 33 GW of wind power between 2022-23 and 2026-27.39  As of December 2025, the wind capacity stood at 55 GW.4  The Standing Committee on Energy (2022) had noted the following as key reasons for slow capacity addition in wind: (i) the shift in tariff system from feed-in-tariff (guaranteed above market price for producers) to tariff determination by competitive bidding, and (ii) aggressive bidding by some developers, who decrease prices to unsustainable levels and eventually back out of the project.[64]

Out of the total estimated potential more than 95% of commercially exploitable wind resources are concentrated in seven states.39  CEA (2023) observed that the land resources required for large scale production of onshore wind projects are gradually becoming a major constraint.39  Offshore wind power is seen as an alternative in such a scenario.39  Absence of any obstruction in the sea offers better quality of wind power and its conversion to electrical energy.39  Offshore wind turbines are much larger in size (in range of 5 to 10 MW per turbine) as against 2-3 MW of an onshore wind turbine.39  However, the cost per MW for offshore turbines are also higher because of requirement of stronger structures and foundations to operate in a marine enviroment.39   In 2024, the central government launched a viability gap funding scheme for offshore wind energy projects.[65]  The scheme aims to reduce the cost of power from offshore wind projects through financial assistance.65  

Insufficient storage capacity for renewables

The variability and uncertainty in generation from solar and wind may lead to a mismatch between demand and supply.  Higher integration of Variable Renewable Energy (VRE) in grid leads to challenges such as variable grid voltage.[66]  To maintain grid stability, power is curtailed (reduction of electricity generated below the maximum potential of a generator).[67]  Storage systems can be used to bring down the variability of renewable energy generation and reduce power curtailments.[68]  Battery Energy Storage Systems (BESS) and pump storage are expected to be two primary options for storage in India.39  BESS can store excess solar energy during the day and use that for peak demand during non-solar hours.  In pump storage, water is pumped and stored upstream, which can later be used to run turbines to produce energy.  

As of June 2025, the total storage capacity was about 5 to 5.5 GW.23  CEA has projected that about 16 GW of storage capacity will be required in 2026-27.39  The Forum of Regulators (2025) noted that issues such as power curtailment are likely to intensify with higher renewable penetration in the absence of sufficient storage.67  One of the key reasons for slow development of storage systems in India is its high costs particularly for certain technologies such as BESS.23  Although, higher costs are expected to reduce.  By 2030, solar energy with battery storage is expected to be competitive with existing coal capacity driven by factors such as the decline in prices of batteries and solar panels.[69] 

In September 2023, the Cabinet approved a viability gap funding scheme for battery energy storage systems.16  Under the scheme, financial support is provided for the development of BESS approved during 2023-26.[70]  It seeks to develop 4,000 GWh of storage capacity by 2030-31.[71]  However, the fund utilisation under this scheme has remained low in recent years, with zero expenditure in 2024-25.16  Under the scheme, fund disbursement occurs in five tranches.  These are tied to a project milestone such as 10% upon financial closure of the project.70  In 2024-25, none of the projects could achieve financial closure leading to zero funds being disbursed.16  As of February 2026, 10 GW of BESS capacity is under construction, and another 20 GW under tendering.72

As of February 2026, Pumped Storage Plant (PSP) projects of 12 GW capacity are also under construction.[72]  Further, about 7 GW of PSPs are concurred but yet to be taken up for construction.72  Forum of Regulators (2025) noted certain issues in pumped storage such as delays in grant of clearances, uncertainty in tariffs, limited number of civil contractors, and exclusion of off-stream pumped storage projects from White category classification.67  White category includes non-polluting industries (such as solar power) and has simplified approval process.67 

Inadequate investments in renewables

Renewable energy projects are capital intensive and require significant upfront investment.[73]  India’s cost of capital for grid-scale renewable energy is one of the lowest among developing economies, however, it is 80% higher than in advanced economies.[74]  International Energy Agency (2025) observed that higher financing costs affect the financial viability of projects, leading to higher energy prices.74  The Economic Survey (2025-26) noted India’s reliance on international climate finance as one of the reasons for the high cost of capital.53  The Survey stated that global capital does not flow at scale to developing countries due to structural features of the international financial system and risk perceptions, resulting in high costs.53

Financing in renewable energy infrastructure in India in the form of debt and equity.[75]  These come from sources such as banks, private Non-Banking Financial Companies (NBFCs), bond markets, and international lenders.75  MNRE noted that although the investment in the sector has increased, higher mobilisation of renewable energy finance is needed to meet national targets, particularly in certain segments.[76]  These segments include energy storage, green hydrogen, and offshore wind.76 

It is estimated that Rs 30.5 lakh crore of financing is required from 2023-24 till 2029-30 to achieve 500 GW of non-fossil fuel-based power capacity (an average of Rs 4.4 lakh crore per year).76  The investment in 2024-25 was only about 2.68 lakh crore.76  Some reasons affecting financing include: (i) limited availability of reliable and standardised data for investors to assess risk, (ii) lack of domestic off-takers for emerging energy segments such as green hydrogen, and (iii) higher financing costs due to technological and market uncertainities.23,[77]

Hydropower below potential

Hydropower can support grid flexibility by helping manage the variations in electricity generation from renewable energy sources such as solar and wind.67 They have higher storage capabilities and can rapidly increase or decrease output, with ramp rates of 80–100% of power output per minute (compared to 1-2% for a coal-fired plant).67  Higher ramp rate signify that they can move from near-zero to full output within a short time.67  As per the CEA study, the exploitable large hydro potential in the country is about 133 GW.67  As of December 2025, only 51 GW of large hydro plants (>25 MW) are installed.4  About 13 GW of hydropower projects are under construction and 4 GW of projects are under various stages of planning.72  These are targeted to be completed by 2031-32.72  The untapped potential may be due to reasons involving adverse geological conditions or difficult terrain.67  Other issues that cause delay in hydro power development include issues around resettlement of local communities and uncertainty regarding tariff determination.67 

Further, hydropower projects are typically required to provide free power to the home state.67  However, in some cases, states have changed the terms of the agreements midway for various reasons, impacting the financial stability of the hydro projects.67  Additionally, the waiver of the Inter-State Transmission System (ISTS) charges for hydro and related pumped storage projects is limited to projects commissioned by June 30, 2025.67  While similar cut-off dates apply to solar and wind projects, they have a significantly shorter construction timelines unlike hydro and pumped storage projects which have much longer gestation periods.67,[78]

Low compliance with RPO

Certain entities such as discoms are mandated to procure a specific percentage of electricity from renewable sources.  This is referred to as renewable purchase obligations.  The Ministry of Power specified the RPO trajectory for different obligated entities.  This has now been replaced by a minimum Renewable Energy Consumption obligation (RCO) for the entities.[79]  As per the notification issued by the Ministry of Power, the minimum share of renewable energy consumption for entities such as discoms is set at about 36% for 2026-27 rising to 43% in 2029-30.79 

In 2022-23, the RPO compliance across states varied from 7% in Puducherry to 88% in Sikkim (see Table 10 in the annexure).[80] Only 15 states met their RPO obligation.  The Union Ministry of Power (2022) had observed that discoms perceive renewable energy to be expensive and having additional costs towards integration.[81]  Discoms can also fulfil their RPO obligations by purchasing Renewable Energy Certificates (RECs).[82]  The government circulated a draft Electricity (Amendment) Bill, 2025 for comments.  This Bill introduces a penalty for non-compliance with the obligations.

Geothermal Energy in India

The central government notified a National Policy on Geothermal Energy on September 15, 2025.[83]  It aims to promote the exploration, development, and deployment of geothermal resources in the country.[84]  According to the Geological Survey of India (2022), India’s estimated theoretical geothermal resource potential is around 11 GW.83  However, despite this assessed potential, participation in geothermal energy development remains limited, with most activities in pilot project stage.84   This is due to reasons including high upfront costs, risks associated with exploration, and limited domestic technical capabilities.[85]

Transmission

Addition of transmission lines

Transmission systems require augmentation to support the integration of new generation capacity and rising demand.87  CEA projects that India will need to add 1,23,577 circuit kilometre (ckm) of transmission lines between 2022-23 and 2026-27 (an average of 24,715 ckm per year).87  In 2024-25, achievement on addition of transmission lines (220 kV and above) was below target (Figure 6).  In case of transmission projects, the Standing Committee on Energy (2024) noted the following key reasons for delay: (i) issues with right-of-way permissions, (ii) delay in land acquisition, (iii) contractual disputes, and (iv) unexpected route diversions to protect endangered species and coal mining areas.43  Further, poor availability of required steel quality and limited number of High Voltage Direct Current (HDVC) systems has led to delayed supply.16  

Figure 6: Transmission lines (of 220 kV and above): Target vs Achievement (in ckm)

Source: Executive Summary Report (of various years), Central Electrical Authority; PRS.

Under the Green Energy Corridor (GEC), the central government funds laying of transmission lines to evacuate power from Renewable Energy (RE) projects.[86]  It has multiple phases.86  The Phase-I of GEC is under implementation in eight states.86  It aims to facilitate grid integration and power evacuation of 24 GW of RE in RE-rich states such as Gujarat, Rajasthan, and Tamil Nadu.86  The Phase-I (Intra-state) of GEC faced delays in some states such as Andhra Pradesh, Himachal Pradesh and Gujarat.86  The delay was due to issues related to land acquisition, right-of-way, and forest clearances.86

Import dependence for equipment

Transmission is carried out primarily by central and state-owned companies and largely remains a government-controlled activity.[87]  Key materials and equipment used for transmission infrastructure include Cold Rolled Grain Oriented (CRGO) Steel and HDVC systems.23   CRGO steel is used in transformers and reactors and HVDC based transmission lines and transformers are required for transmission of power over long distances.23  India has been lagging in manufacturing of these materials and equipment due to the need for large capital, advanced technology, and adequate testing infrastructure.23  The central government has launched a Production-Linked Incentive Scheme for Speciality Steel including CRGO in 2021.[88]  The scheme aims to bring an investment of about Rs 40,000 crore and add 25 million tonnes of manufacturing capacity of speciality steel.88  As of October 2025, the PLI scheme has attracted investments of about Rs 23,022 crore and 2.3 million tonnes of speciality steel production.[89]     

Distribution

In most states, electricity distribution is carried out by a single company, typically a state government-owned entity that serves all consumers in a given area.5  Private sector discoms supply electricity in a few places such as Delhi and Mumbai.5  A persistent challenge for the electricity sector has been the poor financial performance of discoms.5,[90]  In seven years between 2018-19 and 2024-25, cumulative losses of distribution utilities were Rs. 3.6 lakh crore.[91] 

In 2024-25, on average, discoms spent Rs 7.10 per unit to earn Rs 7.04 (based on actual subsidy received and excluding regulatory income which are receivable in future), resulting in revenue gap of six paise per unit.5  In 2023-24, this gap was 20 paise per unit.5  In the past, discoms have required government support to be bailed out from losses.90  For instance, in 2015, under UDAY scheme, state governments had to take over 75% of the debt of their discoms worth Rs 2.3 lakh crore.[92]  Persistent financial problems result in payments delays and non-payment to generators impact their fuel suppliers, i.e., coal companies.

Figure 7: Discoms continue to make losses (in Rs crore)

Note:  Losses above are based on actual subsidy received and excluding revenue grant under UDAY to offset losses, and any regulatory income (recoverable in future).
Source: Reports on Performance of Power Utilities, Power Finance Corporation; PRS.

If the entire amount of subsidy billed was received and discoms also recovered the entire amount of regulatory income in the same year, discoms would register a profit of Rs 2,701 crore in 2024-25.5  However, this is mainly due to Rs 12,138 crore profit registered by the private sector discoms.5  The state-owned discoms would still register losses of Rs 9,437 crore.5

A variation in distribution losses in recent years may also be due to factors such as variance in fuel prices and release of subsidies by state governments.  In 2021-22, losses decreased due to higher subsidy payments.[93]  Subsidy payment was 10% higher than subsidy billed in that year, likely due to payment of dues for previous years.  In 2022-23, losses had increased due to a higher reliance on imported coal and higher price of imported coal amidst the record high global coal demand during that year.[94],[95]

AT&C losses have come down, however, remain above target in some states

AT&C losses have come down from 22% in 2018-19 to 15% in 2024-25.[96]  In 2024-25, on aggregate, distribution utilities billed 88% of the electricity they injected into the grid.5  Of which, they collected 97% of the amount they billed.5  AT&C losses vary significantly among states.  These range between as low as 8% in Delhi (state sector) to as high as 23% in Madhya Pradesh, 28% in Jharkhand, and 49% in Nagaland in 2024-25.5  These losses can be attributed to: (i) technical losses which include some unavoidable loss in energy transfer, (ii) inefficiencies in energy transfer due to sub-optimal condition of the network, and (iii) commercial losses such as theft or inadequate metering.

Draft Electricity (Amendment) Bill, 2025

The Draft Electricity (Amendment) Bill, 2025 was released by the Ministry of Power on October 8, 2025.  It seeks to propose measures to promote competition and improve financial viability of distribution utilities.  The Draft Bill allows network sharing among discoms operating in the same area.  Currently, each discom supply and distribute electricity through their own networks.  It requires tariffs to be cost-reflective and propose removal of cross-subsidies paid by manufacturing enterprises, railways, and metro railways within five years.  Further, the Bill establishes an Electricity Council comprising of union and state power ministers.  The Council will advise central and state governments on policy measures and coordinate implementation of sector reforms.

Underpricing of tariffs

Tariffs charged to consumers are regulated by State Electricity Regulatory Commissions (SERCs).  Often, tariffs are designed on a multi-year basis.  At times, they are designed such that the tariff is lower than the cost in initial years, and cost recovery is offloaded to upcoming years.  These costs, recoverable in future, are termed as regulatory income.  For instance, in 2024-25, Maharashtra state discoms booked a regulatory income of Rs 8,208 crore.5  However, non-recovery of costs would add up as annual losses for discoms.  In August 2025, the Supreme Court noted a disproportionate increase in regulatory assets.[97]  It directed the distribution companies (discoms) to clear the existing regulatory assets within four years.97  It also advised capping the regulatory asset at 3% of a discoms’ revenue.97

Power procurement costs

Power procurement costs constitute about 70%-80% of the total costs of discoms.[98]  Power procurement costs vary significantly across states, from as low as about Rs 3 per kWh in Sikkim, to as high as Rs 8.5 per kWh in Delhi.5  In many states, a high percentage of power demand is tied up in long-term contracts.[99]  Fixed costs will still have to be paid under these long-term contracts if the discom looks for alternative sources for procuring power.99

Delay in release of government subsidies

The state government may choose to provide subsidies to keep prices lower for certain categories of consumers.  While determining the retail tariff, regulators make adjustments for the subsidy.  However, states may not pay all the subsidies booked by discoms in the same financial year.  For example, in 2024-25, discoms received 99% of the subsidy they billed.5  Some state governments such as, Himachal Pradesh (57%), Punjab (82%), and Maharashtra (88%) released a relatively lower proportion of tariff subsidy in 2024-25.5  

 

Annexure

Table 5: Installed capacity (in MW) across states as of December 2025

State/UT

Thermal

Renewables

Nuclear

Coal

Lignite

Gas

Diesel

Large Hydro

Solar

Wind

Andaman and Nicobar

-

-

-

93

-

32

-

-

Andhra Pradesh

13,890

-

1,739

37

3,290

6,389

4,398

-

Arunachal Pradesh

-

-

-

-

1,365

15

-

-

Assam

750

-

597

-

346

376

-

-

Bihar

10,170

-

-

-

-

435

-

-

Chandigarh

-

-

-

-

-

79

-

-

Chhattisgarh

24,093

-

-

-

120

1,690

-

-

Dadra & Nagar Haveli and Daman & Diu

-

-

-

-

-

129

-

-

Delhi

-

-

2,100

-

-

389

-

-

Goa

-

-

-

-

-

71

-

-

Gujarat

14,692

1,400

6,580

-

1,990

25,529

14,821

1,840

Haryana

5,330

-

432

-

-

2,513

-

-

Himachal Pradesh

-

-

-

-

11,421

346

-

-

Jammu & Kashmir

-

-

-

-

3,360

79

-

-

Jharkhand

7,030

-

-

-

210

236

-

-

Karnataka

9,480

-

370

25

3,689

10,679

8,414

880

Kerala

-

-

360

160

2,008

2,032

72

-

Ladakh

-

-

-

-

89

11

-

-

Lakshadweep

-

-

-

27

-

7

-

-

Madhya Pradesh

21,170

-

-

-

2,235

5,818

3,548

-

Maharashtra

23,316

-

2,819

-

3,047

18,061

5,822

1,400

Manipur

-

-

-

36

105

18

-

-

Meghalaya

-

-

-

-

322

4

-

-

Mizoram

-

-

-

-

60

32

-

-

Nagaland

-

-

-

-

75

3

-

-

Odisha

9,950

-

-

-

2,155

763

-

-

Puducherry

-

-

33

-

-

74

-

-

Punjab

5,680

-

-

-

1,096

1,555

-

-

Rajasthan

9,244

1,580

1,023

-

413

36,658

5,229

1,780

Sikkim

-

-

-

-

2,282

8

-

-

Tamil Nadu

10,523

3,640

845

212

2,203

11,665

12,075

2,440

Telangana

11,043

-

-

-

2,406

5,052

128

-

Tripura

-

-

1,068

-

-

35

-

-

Uttar Pradesh

30,015

-

1,493

-

502

3,823

-

440

Uttarakhand

-

-

664

-

4,785

838

-

-

West Bengal

13,235

-

-

-

1,341

321

-

-

All-India

2,19,610

6,620

20,122

589

50,915

1,35,765

54,507

8,780

Source: Installed Capacity Reports, National Power Portal; PRS.

Table 6: Smart Metering Status as on Dec 31, 2025

State

Consumer Meters Sanctioned

Installed

Distribution Transformer Meters Sanctioned

Installed

Feeder Meters Sanctioned

Installed

In number

In %

In number

In %

In number

In %

Andaman and Nicobar

1,58,773

75,200

47%

1,148

0

0%

114

0

0%

Andhra Pradesh

56,10,846

21,58,269

38%

2,93,140

74,389

25%

17,358

8,192

47%

Arunachal Pradesh

2,87,446

47,941

17%

10,116

311

3%

688

263

38%

Assam

69,21,329

51,98,453

75%

94,547

70,265

74%

2,782

2,879

103%

Bihar

1,72,08,939

83,33,722

48%

2,50,726

1,82,145

73%

6,427

5,775

90%

Chandigarh

29,433

24,214

82%

-

-

-

 

 

 

Chhattisgarh

59,62,115

32,32,660

54%

2,10,644

66,023

31%

6,720

5,936

88%

Delhi

2,60,000

2,60,000

100%

766

0

0%

2,755

0

0%

Goa

7,41,160

0

0%

8,369

0

0%

827

0

0%

Gujarat

1,65,10,860

34,66,500

21%

3,00,487

1,28,600

43%

-

-

-

Haryana

10,00,000

8,47,467

85%

-

-

-

-

-

-

Himachal Pradesh

29,52,685

8,53,786

29%

39,012

22,054

57%

1,951

1,603

82%

Jammu and Kashmir

21,34,095

11,19,117

52%

1,08,831

28,880

27%

2,608

1,428

55%

Jharkhand

18,64,065

10,43,862

56%

39,936

17,299

43%

2,508

2,073

83%

Kerala

1,32,90,166

1,67,882

1%

87,615

111

0%

6,025

2,904

48%

Ladakh

58,930

55,580

94%

1,931

1,850

96%

54

79

146%

Madhya Pradesh

1,34,44,401

33,64,112

25%

4,24,856

1,30,348

31%

29,708

24,097

81%

Maharashtra

2,35,64,747

80,88,791

34%

4,10,905

2,52,106

61%

29,214

30,709

105%

Manipur

1,54,400

31,962

21%

11,451

589

5%

357

220

62%

Meghalaya

4,60,000

0

0%

11,419

0

0%

1,324

0

0%

Mizoram

2,90,039

26,492

9%

2,300

393

17%

398

295

74%

Nagaland

3,17,210

30,522

10%

6,276

845

13%

392

105

27%

Odisha

4,500

4,500

100%

-

-

-

180

0

0%

Puducherry

4,03,767

5,647

1%

3,105

1

0%

12,563

0

0%

Punjab

1,12,32,507

19,06,036

17%

1,84,044

0

0%

27,128

25,349

93%

Rajasthan

1,49,00,527

25,13,774

17%

4,34,608

23,834

5%

633

471

74%

Sikkim

1,44,680

78,582

54%

3,229

1,469

45%

18,392

9,864

54%

Tamil Nadu

3,01,40,849

1,29,641

0%

4,73,720

1,220

0%

1,951

1,603

82%

Telangana

8,882

8,882

100%

-

-

-

-

-

-

Tripura

4,47,489

1,40,240

31%

14,908

5,494

25%

473

473

100%

Uttar Pradesh

3,09,78,280

71,70,682

23%

15,26,801

2,44,830

3%

20,874

25,362

122%

Uttarakhand

15,87,870

4,11,358

26%

59,212

7,441

74%

2,602

2,486

96%

West Bengal

2,12,08,759

5,55,586

3%

3,05,419

44,589

73%

11,874

9,357

79%

All-India

22,42,79,749

5,13,51,460

23%

53,19,521

13,05,086

25%

2,08,880

1,61,523

77%

Source: All India Smart Metering Status, Website of National Smart Grid Mission of Ministry of Power, as accessed on December 31, 2025; PRS

Table 7: PM Surya Ghar Muft Bijli Yojana Progress across states as on January 10, 2026

State/UT

Applications

Installations

Households covered

In number

In %

Andaman and Nicobar

654

183

28%

202

Andhra Pradesh

11,75,634

87,984

7%

90,864

Arunachal Pradesh

88

1

1%

1

Assam

4,84,444

75,177

16%

75,883

Bihar

55,543

14,500

26%

15,148

Chandigarh

1,510

1,001

66%

1,001

Chhattisgarh

1,21,687

23,404

19%

24,825

Dadra & Nagar Haveli and Damand & Diu

1,949

496

25%

496

Delhi

17,149

5,589

33%

9,471

Goa

2,687

1,461

54%

1,814

Gujarat

6,17,917

5,24,808

85%

7,57,016

Haryana

1,04,038

49,473

48%

56,562

Himachal Pradesh

10,719

6,234

58%

6,235

Jammu and Kashmir

90,917

19,459

21%

19,467

Jharkhand

7,886

1,512

19%

1,514

Karnataka

1,55,643

15,292

10%

24,168

Kerala

2,43,706

1,80,783

74%

1,85,462

Ladakh

1,725

1,278

74%

1,278

Lakshadweep

1,144

752

66%

752

Madhya Pradesh

1,39,368

85,955

62%

89,367

Maharashtra

5,89,328

4,03,698

69%

6,50,742

Manipur

1,478

729

49%

729

Meghalaya

1,933

35

2%

35

Mizoram

954

787

82%

789

Nagaland

548

132

24%

132

Odisha

1,61,517

29,396

18%

29,744

Puducherry

3,209

2,286

71%

2,286

Punjab

18,866

10,906

58%

11,016

Rajasthan

2,49,987

1,23,248

49%

1,27,175

Sikkim

261

26

10%

26

Tamil Nadu

65,809

52,224

79%

60,831

Telangana

72,956

26,041

36%

37,155

Tripura

7,871

1,945

25%

1,956

Uttar Pradesh

10,45,349

3,35,182

32%

3,38,861

Uttarakhand

95,316

60,027

63%

60,189

West Bengal

12,112

1,145

9%

1,208

All-India

55,61,902

21,43,149

39%

26,84,400

Source: State/UT-wise progress (PMSG: MBY), PMSG: MBY National Portal; PRS.

Table 8: Performance of distribution utilities in 2024-25

State/UT

AT&C Losses

ACS

(Rs per unit)

As per subsidy billed

As per actual subsidy received and excluding regulatory income

ARR

(Rs per unit)

ACS-ARR
Gap
(Rs per unit)

ARR

(Rs per unit)

ACS-ARR
Gap
(Rs per unit)

State Sector

15.4%

7.12

7.07

0.05

7.02

0.11

Andaman & Nicobar Islands

24.1%

29.06

26.84

2.22

26.84

2.22

Andhra Pradesh

7.9%

8.11

8.13

-0.02

8.26

-0.15

Arunachal Pradesh

46.2%

6.28

6.28

-

6.28

-

Assam

15.4%

7.63

7.89

-0.26

7.89

-0.26

Bihar

15.5%

6.73

7.14

-0.41

7.14

-0.41

Chhattisgarh

14.3%

5.95

5.87

0.09

6.15

-0.19

Delhi

8.4%

10.43

11.29

-0.86

11.29

-0.86

Goa

10.4%

5.62

5.41

0.20

5.41

0.20

Gujarat

8.3%

6.02

6.42

-0.40

6.42

-0.40

Haryana

11.8%

6.23

6.23

0.01

6.13

0.10

Himachal Pradesh

19.4%

5.66

5.87

-0.22

5.43

0.23

Jharkhand

28.2%

7.01

5.94

1.07

6.06

0.95

Karnataka

11.9%

8.84

7.82

1.03

8.16

0.69

Kerala

6.6%

6.44

6.60

-0.17

6.60

-0.17

Ladakh

26.8%

6.87

7.76

0.89

7.76

-0.89

Madhya Pradesh

22.8%

5.87

5.62

0.25

5.91

-0.04

Maharashtra

17.7%

8.09

8.17

-0.07

7.53

0.56

Manipur

12.9%

6.97

7.02

-0.05

7.17

-0.20

Meghalaya

17.5%

8.56

8.43

0.13

8.43

0.13

Mizoram

32.3%

9.09

9.43

-0.34

9.43

-0.34

Nagaland

48.9%

7.46

7.96

-0.50

7.96

-0.50

Puducherry

14.7%

5.55

6.25

-0.70

6.19

-0.64

Punjab

19.2%

5.93

6.71

-0.78

6.23

-0.30

Rajasthan

15.2%

6.56

6.67

-0.11

6.61

-0.04

Sikkim

21.8%

5.73

5.40

0.33

5.40

0.33

Tamil Nadu

11.0%

8.60

8.78

-0.18

8.78

-0.19

Telangana

19.8%

7.37

7.09

0.27

7.09

0.27

Tripura

29.6%

7.66

6.25

1.40

6.25

1.40

Uttar Pradesh

19.5%

7.68

6.95

0.73

6.95

0.73

Uttarakhand

15.1%

6.06

6.03

0.04

6.00

0.06

West Bengal

17.2%

6.54

6.56

-0.02

6.57

-0.03

Private Sector

10.1%

6.78

7.96

-1.18

7.43

-0.65

Dadra & Nagar Haveli and Daman & Diu

-

-

-

-

-

-

Delhi

6.5%

7.17

9.69

-2.52

8.31

-1.13

Gujarat

3.6%

8.36

8.87

-0.50

8.78

-0.42

Maharashtra

5.0%

7.90

8.81

-0.91

9.95

-2.04

Odisha

17.8%

5.48

5.65

-0.16

5.30

0.18

Uttar Pradesh

8.5%

6.52

7.06

-0.54

6.67

-0.15

West Bengal

4.8%

5.04

5.08

-0.04

5.33

-0.30

All-India

15.0%

7.10

7.13

-0.03

7.04

0.06

Note: AT&C losses: Aggregate Technical and Commercial (AT&C) loss is the ratio of power for which the discom did not receive any payment to the total electricity procured by the utility.  *ACS: Average Cost of Supply; ARR: Average Revenue Realised.
Source: Report on Performance of Power Utilities 2024-25, Power Finance Corporation; PRS.

Table 9: Profit/Loss of distribution utilities in 2024-25

State/UT

Profit/Loss on subsidy billed basis

(Rs crore)

Profit/Loss with tariff subsidy received and excluding regulatory income (Rs crore)

State Sector

-9,437

-17,732

Andaman & Nicobar Islands

-91

-91

Andhra Pradesh

190

1,180

Arunachal Pradesh

-

--

Assam

308

308

Bihar

2,079

2,096

Chhattisgarh

-407

915

Delhi

170

170

Goa

-119

-119

Gujarat

3,310

3,310

Haryana

-46

-776

Himachal Pradesh

342

-365

Jharkhand

-1,928

-1,722

Karnataka

-8,869

-5,901

Kerala

574

574

Ladakh

26

26

Madhya Pradesh

-2,561

456

Maharashtra

1,292

-9,598

Manipur

5

26

Meghalaya

-36

-36

Mizoram

32

32

Nagaland

56

56

Puducherry

281

256

Punjab

6,216

2,415

Rajasthan

1,262

510

Sikkim

-37

-37

Tamil Nadu

2,073

2,144

Telangana

-2,462

-2,462

Tripura

-373

-373

Uttar Pradesh

-10,976

-10,796

Uttarakhand

-47

-94

West Bengal

120

167

Private Sector

12,138

6,461

Dadra & Nagar Haveli and Daman & Diu

-

-

Delhi

9,819

4,327

Gujarat

673

560

Maharashtra

1,031

2,317

Odisha

439

-791

Uttar Pradesh

171

11

West Bengal

4

38

All-India

2,701

-11,270

Source: Report on Performance of Power Utilities 2024-25, Power Finance Corporation; PRS

Table 10: Compliance with Renewable Purchase Obligation in 2022-23

State

Wind

Hydro

Others

Total

Target

Achievement

Target

Achievement

Target

Achievement

Target

Achievement

Andhra Pradesh

0.81%

3.30%

0.35%

0.00%

23.44%

25.10%

24.61%

28.50%

Arunachal Pradesh

0.81%

0.00%

0.35%

3.50%

23.44%

15.30%

24.61%

18.80%

Assam

0.81%

0.00%

0.35%

2.70%

23.44%

20.40%

24.61%

23.20%

Bihar

0.81%

0.10%

0.35%

0.10%

23.44%

15.90%

24.61%

16.00%

Chhattisgarh

0.81%

0.10%

0.35%

1.20%

23.44%

11.90%

24.61%

13.30%

Delhi

0.81%

0.00%

0.35%

0.60%

23.44%

23.80%

24.61%

24.40%

Goa

0.81%

0.80%

0.35%

0.40%

23.44%

16.10%

24.61%

17.30%

Gujarat

0.81%

3.50%

0.35%

0.20%

23.44%

16.50%

24.61%

20.30%

Haryana

0.81%

0.00%

0.35%

0.90%

23.44%

20.80%

24.61%

21.70%

Himachal Pradesh

0.81%

0.00%

0.35%

2.70%

23.44%

76.00%

24.61%

78.70%

Jammu & Kashmir & Ladakh UT

0.81%

0.00%

0.35%

0.00%

23.44%

56.90%

24.61%

56.90%

Jharkhand

0.81%

0.00%

0.35%

0.00%

23.44%

30.00%

24.61%

30.00%

Karnataka

0.81%

6.40%

0.35%

0.00%

23.44%

40.30%

24.61%

46.70%

Kerala

0.81%

0.00%

0.35%

0.00%

23.44%

36.30%

24.61%

36.30%

Madhya Pradesh

0.81%

0.10%

0.35%

0.00%

23.44%

22.30%

24.61%

22.40%

Maharashtra

0.81%

0.00%

0.35%

0.00%

23.44%

17.10%

24.61%

17.10%

Manipur

0.81%

0.00%

0.35%

0.20%

23.44%

33.80%

24.61%

34.00%

Meghalaya

0.81%

0.00%

0.35%

3.20%

23.44%

56.70%

24.61%

59.90%

Mizoram

0.81%

0.30%

0.35%

0.40%

23.44%

42.10%

24.61%

42.70%

Nagaland

0.81%

0.00%

0.35%

5.20%

23.44%

31.30%

24.61%

36.50%

Odisha

0.81%

0.10%

0.35%

0.10%

23.44%

25.30%

24.61%

25.40%

Puducherry

0.81%

0.00%

0.35%

0.00%

23.44%

6.60%

24.61%

6.60%

Punjab

0.81%

0.20%

0.35%

0.00%

23.44%

27.30%

24.61%

27.60%

Rajasthan

0.81%

0.00%

0.35%

0.00%

23.44%

18.30%

24.61%

18.30%

Sikkim

0.81%

0.00%

0.35%

3.70%

23.44%

84.70%

24.61%

88.40%

Tamil Nadu

0.81%

5.80%

0.35%

0.00%

23.44%

19.70%

24.61%

25.50%

Telangana

0.81%

0.00%

0.35%

0.00%

23.44%

20.20%

24.61%

20.20%

Tripura

0.81%

0.00%

0.35%

0.10%

23.44%

13.50%

24.61%

13.60%

Uttar Pradesh

0.81%

0.00%

0.35%

0.40%

23.44%

14.80%

24.61%

15.20%

Uttarakhand

0.81%

0.00%

0.35%

3.00%

23.44%

57.40%

24.61%

60.40%

West Bengal

0.81%

0.10%

0.35%

0.00%

23.44%

15.90%

24.61%

15.90%

Source: Starred Question No. 122, Rajya Sabha, Ministry of Power, August 1, 2023; PRS.


[1] Entry No. 38, List III- Concurrent List, Seventh Schedule, Constitution of India, https://cdnbbsr.s3waas.gov.in/s380537a945c7aaa788ccfcdf1b99b5d8f/uploads/2024/07/20240716890312078.pdf.

[2] “About Ministry”, Website of Ministry of Power as accessed on July 29, 2024, https://powermin.gov.in/en/content/about-ministry.

[4] “All India Installed Capacity (in MW) of Power stations”, Central Electricity Authority, December 31, 2025, https://cea.nic.in/wp-content/uploads/installed/2025/12/website.pdf

[6] Demand No. 79, Expenditure Budget, Ministry of Power, Union Budget 2026-27, https://www.indiabudget.gov.in/doc/eb/sbe79.pdf

[7] “Cabinet approves Revamped Distribution Sector Scheme: A Reforms based and Results linked Scheme”, Press Information Bureau, Union Cabinet, June 30, 2021, https://pib.gov.in/PressReleasePage.aspx?PRID=1731473

[8] Demand No. 71, Expenditure Budget, Ministry of New and Renewable Energy, Union Budget 2026-27, https://www.indiabudget.gov.in/doc/eb/sbe71.pdf

[9] “Cabinet approves PM-Surya Ghar: Muft Bijli Yojana for installing rooftop solar in One Crore households”, Press Information Bureau, Union Cabinet, https://pib.gov.in/PressReleasePage.aspx?PRID=2010130.

[10] “PM-KUSUM”, Ministry of New and Renewable Energy, August 6, 2024, https://www.pib.gov.in/PressReleasePage.aspx?PRID=2042069&reg=3&lang=2

[11] Unstarred Question No. 1397, Lok Sabha, Ministry of Power, answered on February 13, 2025, https://powermin.gov.in/sites/default/files/uploads/LS13.02.2025_Eng.pdf

[12] “Overview”, Ministry of Power website, as accessed on December 24, 2025, https://powermin.gov.in/en/content/overview-5

[13] “All India Smart Metering Status”, National Smart Grid Mission website, as accessed on December 24, 2025, https://www.nsgm.gov.in/en/sm-stats-all

[14] MIS reports, RDSS, Ministry of Power website, as accessed on January 10, 2026,  https://rdss.powermin.gov.in/mis-report

[15] “Fund Disbursement Guidelines under Revamped Distribution Sector Scheme (RDSS)”, REC Limited, Ministry of Power, June 2023, https://www.ipds.gov.in/webappdocs/RDSS_Docs/Fund%20Disbursement%20Guidelines_RDSS_28062023.pdf.

[16] 4th Report: Demand for Grants (2025-26) of the Ministry of Power, Standing Committee on Energy, March 2025, https://sansad.in/getFile/lsscommittee/Energy/18_Energy_4.pdf?source=loksabhadocs

[17] Unstarred Question No. 2868, Rajya Sabha, Ministry of Power, answered on August 18, 2025, https://sansad.in/getFile/annex/268/AU2868_Z4qwMX.pdf?source=pqars

[18] “State-wise installed capacity of renewable power as on November 30, 2025”, Ministry of New and Renewable Energy,  https://cdnbbsr.s3waas.gov.in/s3716e1b8c6cd17b771da77391355749f3/uploads/2025/12/202512101261291671.pdf.

[19] “Progress and Implementation of PM KUSUM Scheme”, Press Information Bureau, Ministry of New and Renewable Energy, December 23, 2023, https://pib.gov.in/PressReleaseIframePage.aspx?PRID=1989815&reg=3&lang=2.

[20] “PM-KUSUM - Grid-connected solar power plants of 89.45 MW capacity installed; 2.09 lakh agriculture pumps have been solarized; Reduction in carbon dioxide (CO2) emissions by 0.67 million tonnes and diesel consumption by 143 million litres of diesel per annum- Union Power & NRE Minister – Shri R. K. Singh”, Press Information Bureau, Ministry of New and Renewable Energy, March 16, 2023, https://www.pib.gov.in/PressReleaseIframePage.aspx?PRID=1907703&reg=3&lang=2.  

[21] 7th Report: Implementation of Pradhan Mantri Kisan Urja Suraksha Evam Utthaan Mahabhiyan (PM-KUSUM) & PM Surya Ghar : Muft Bijli Yojana, Standing Committee on Estimates, December 4, 2025, https://sansad.in/getFile/lsscommittee/Estimates/18_Estimates_7.pdf?source=loksabhadocs

[22] “PM Surya Ghar: Muft Bijli Yojana Delivers Zero Electricity Bills to Over 7.7 Lakh Households”, Press Information Bureau, Ministry of New and Renewable Energy, December 16, 2025, https://www.pib.gov.in/PressReleasePage.aspx?PRID=2204466&reg=3&lang=1

[23] 10th Report: Performance Evaluation of Solar Power Projects in the country, Standing Committee on Energy, September 2025, https://sansad.in/getFile/lsscommittee/Energy/18_Energy_10.pdf?source=loksabhadocs/.  

[24] 5th Report: Demand for Grants 2025-26 of the Ministry of New and Renewable Energy, Standing Committee on Energy, https://sansad.in/getFile/lsscommittee/Energy/18_Energy_5.pdf?source=loksabhadocs.  

[25] “Unlocking India’s Green Hydrogen Production Potential”, Press Information Bureau, November 12, 2025, https://www.pib.gov.in/PressNoteDetails.aspx?id=155990&NoteId=155990&ModuleId=3&reg=3&lang=2

[26] “Government Highlights Progress Under National Green Hydrogen Mission to Reduce Green Hydrogen Costs”, Press Information Bureau, December 16, 2025, https://www.pib.gov.in/PressReleasePage.aspx?PRID=2204464&reg=3&lang=1.

[27] “Water for hydrogen production”, International Renewable Energy Agency, 2023, https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2023/Dec/IRENA_Bluerisk_Water_for_hydrogen_production_2023.pdf

[28] “Enabling sustainable demand for green hydrogen in India”, Institute for Energy Economics and Financial Analysis, November 2025, https://ieefa.org/sites/default/files/2025-11/Enabling%20sustainable%20demand%20for%20green%20hydrogen%20in%20India.pdf

[30] “Low-emissions hydrogen projects grow as policy support races to catch up”, International Energy Agency, October 2, 2024, https://www.iea.org/news/low-emissions-hydrogen-projects-grow-as-policy-support-races-to-catch-up

[31] “Making the breakthrough: Green hydrogen policies and technology costs”, International Renewable Energy Agency, 2021, https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2020/Nov/IRENA_Green_Hydrogen_breakthrough_2021.pdf.  

[32] “Alternative Fuel Data Center”, US Department of Energy website, as accessed on December 26, 2025, https://afdc.energy.gov/fuels/hydrogen-basics

[33] “Hydrogen Storage”, US Department of Energy website, as accessed on December 27, 2025, https://www.energy.gov/eere/fuelcells/hydrogen-storage.

[35] “Monthly Renewable Energy Generation Report”, March 2025, https://cea.nic.in/wp-content/uploads/resd/2025/03/Monthly_RE_Generation_Report_March_2025.docx.pdf.    

[36] “Category Wise- Fuel Wise Generation”, Central Electricity Authority, March 31, 2025, https://npp.gov.in/public-reports/cea/daily/dgr/31-03-2025/dgr17-2025-03-31.pdf.

[37] “India’s Stand at COP-26”, Press Information Bureau, Ministry of Environment, Forest, and Climate Change, February 3, 2022, https://www.pib.gov.in/PressReleasePage.aspx?PRID=1795071&reg=3&lang=2

[38] “Year end review - 2024”, Press Information Bureau, Ministry of Power, January 1, 2025, https://www.pib.gov.in/PressReleasePage.aspx?PRID=2089243&reg=3&lang=2.

[39] National Electricity Plan Vol. I- Generation, Central Electricity Authority, https://cdnbbsr.s3waas.gov.in/s3716e1b8c6cd17b771da77391355749f3/uploads/2023/09/202309011256071349.pdf

[40] Unstarred Question No. 469, Lok Sabha, Ministry of Power, July 25, 2024, https://sansad.in/getFile/loksabhaquestions/annex/182/AU469_JVGZen.pdf?source=pqals

[41] “Energy generation, programme, and plant load factor”, National Power Portal, Central Electricity Authority, April 22 2025, https://npp.gov.in/public-reports/cea/monthly/generation/18%20col%20act/2025/MAR//18%20col%20act-1_2025-MAR.pdf.

[42] “Power Sector at a glance All India”, Ministry of Power website, as accessed on January 11, 2025, https://powermin.gov.in/en/content/power-sector-glance-all-india

[43] 1st Report: Demand for Grants (2024-25) of the Ministry of Power, Standing Committee on Energy, December 2024, https://sansad.in/getFile/lsscommittee/Energy/18_Energy_1.pdf?source=loksabhadocs

[44] “Broad Status Report of Under Construction Thermal Power Projects”, Central Electricity Authority, November 2025, https://cea.nic.in/wp-content/uploads/thermal_broad/2025/11/BS_Nov_2025_Approved.pdf

[45] “Nuclear Power in Union Budget 2025-26”, Press Information Bureau, Department of Atomic Energy, February 3, 2025, https://www.pib.gov.in/PressReleasePage.aspx?PRID=2099244&reg=3&lang=2

[46] “The Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Bill, 2025”, Press Information Bureau, December 19, 2025, https://static.pib.gov.in/WriteReadData/specificdocs/documents/2025/dec/doc20251219739001.pdf

[47] “Energy Statistics India 2025”, Ministry of Statistics and Programme Implementation,  https://www.mospi.gov.in/sites/default/files/publication_reports/Energy_Statistics_2025/Energy%20Statistics%20India%202025_27032025.pdf.

[48] “Advantages and Challenges of Nuclear Energy”, US Department of Energy, June 11, 2024, https://www.energy.gov/ne/articles/advantages-and-challenges-nuclear-energy

[49] “Parliament question: Leveraging India’s Thorium reserves”, Press Information Bureau, Department of Atomic Energy, December 18, 2025, https://www.pib.gov.in/PressReleasePage.aspx?PRID=2205825&reg=3&lang=2

[50] “Source-wise Electricity Generation Trends”, India Climate and Energy Dashboard, Niti Ayog, accessed on January 13, 2025, https://iced.niti.gov.in/energy/electricity/generation/power-generation.

[51] Installed Capacity Report – December 2025, Central Electricity Authority, https://cea.nic.in/wp-content/uploads/installed/2025/12/website.pdf.

[52] “2025 Marks Highest-Ever Renewable Energy Expansion in India’s Energy Transition Journey”, Ministry of New and Renewable Energy, December 29, 2025, https://www.pib.gov.in/PressReleasePage.aspx?PRID=2209478&reg=3&lang=1.

[53] The Economic Survey 2025-26, Ministry of Finance, January 29, 2026, https://www.indiabudget.gov.in/economicsurvey/doc/echapter.pdf.

[54] “Empowering sustainable growth with renewable energy”, Solar Energy Corporation of India Ltd. (SECI) website, as accessed on December 23, 2025, https://www.seci.co.in/empowering-sustainable-growth-with-renewable-energy

[55] “India’s RE Integration Strategy Enters Next Phase: Government Adopts Nuanced, Case-by-Case Approach to REIA Bids with Focus on Grid Strength, Storage and Market Reform”, Press Information Bureau, Ministry of New and Renewable Energy, November 4, 2025, https://www.pib.gov.in/PressReleasePage.aspx?PRID=2186235&reg=3&lang=2

[56] “Solar PV Global Supply Chains”, International Energy Agency, July 7, 2022, https://www.iea.org/reports/solar-pv-global-supply-chains

[57] “Solar PV manufacturing capacity and production by country and region, 2021-2027”, International Energy Agency website, as accessed on December 23, 2025, https://www.iea.org/data-and-statistics/charts/solar-pv-manufacturing-capacity-and-production-by-country-and-region-2021-2027

[58] “India’s Photovoltaic Manufacturing Capacity Set to Surge”, Institute for Energy Economics and Financial Analysis, JMK Research and Analytics, April 2023, https://jmkresearch.com/wp-content/uploads/2024/02/Indias-Photovoltaic-Manufacturing-Capacity-Set-to-Surge-April-2023.pdf

[59] “Export and Import”, Ministry of Mines website, as accessed on February 3, 2026, https://mines.gov.in/webportal/content/export--import.

[60] Notification F. No. 28/15/2024-CMM-Part (1), The Gazette of India, Ministry of Mines, June 24, 2025,

https://egazette.gov.in/WriteReadData/2025/264204.pdf.  

[61] National Critical Mineral Mission, Ministry of Mines, January 2025,

https://mines.gov.in/admin/storage/ckeditor/24_pages__desktop_1752835254.pdf.

[62] Unstarred Question No. 506, Lok Sabha, Ministry of Mines, December 3, 2025, https://sansad.in/getFile/loksabhaquestions/annex/186/AU506_oQsaKi.pdf?source=pqals.

[63] 7th Report: Action Plan for Achievement of 175 GW Renewable Energy Target, Standing Committee on Energy, 17th Lok Sabha, March 2021, https://sansad.in/getFile/lsscommittee/Energy/17_Energy_17.pdf?source=loksabhadocs.

 

[64] 27th Report: Evaluation of Wind Energy in India, Standing Committee on Energy, July 2022, https://sansad.in/getFile/lsscommittee/Energy/17_Energy_27.pdf?source=loksabhadocs/.

[65] “Cabinet approves Viability Gap Funding (VGF) scheme for implementation of Offshore Wind Energy Projects”, Press Information Bureau, Ministry of New and Renewable Energy, June 19, 2024, https://www.pib.gov.in/PressReleaseIframePage.aspx?PRID=2026700&reg=3&lang=2

[66] “Integration Costs of Wind and Solar Power”, Economic and Social Commission for Western Asia, https://www.unescwa.org/sites/default/files/event/materials/ESCWA-AUE%20Workshop%20on%20VRE%20Integration%20Costs%20Training%20Materials_1.pdf

[67] “Report on Accelerating the Development of Hydropower Particularly Pumped Storage for  Grid Stability in India”, Forum of Regulators, March 2025, https://forumofregulators.gov.in/Data/study/Hydro%20PSP%20Report.pdf

[68] Integrating Variable Renewable Energy: Challenges and Solutions, National Renewable Energy Laboratory, September 2013, https://www.nrel.gov/docs/fy13osti/60451.pdf

[70] “Viability gap funding for battery energy storage systems”, Press Information Bureau, Ministry of Power, April 3, 2025, https://www.pib.gov.in/PressReleaseIframePage.aspx?PRID=2118325&reg=3&lang=2

[71] “Cabinet approves the scheme titled Viability Gap Funding for Development of Battery Energy Storage Systems”, Press Information Bureau, Union Cabinet, September 6, 2023, https://pib.gov.in/PressReleasePage.aspx?PRID=1955112

[72] Unstarred Question No. 1119, Lok Sabha, Ministry of Power, February 5, 2026, https://sansad.in/getFile/loksabhaquestions/annex/187/AU1119_FJPOh4.pdf?source=pqals.

[73] “Cost of Capital for Indian Renewable Energy Projects: A Review of Methodologies, Risk Drivers, and Policy Evolution”, Institute for Energy Economics and Financial Analysis, December 2025, https://sustainablefinance.ox.ac.uk/wp-content/uploads/2025/12/DP_Review-Paper_RE-Cost-of-Capital-2025.pdf/ 

[74] World Energy Investment 2025, International Energy Agency, June, 2025,  https://www.iea.org/reports/world-energy-investment-2025

[75] Renewable Energy Financing Landscape in India, Institute for Energy Economics and Financial Analysis, February 2022, https://ieefa.org/wp-content/uploads/2022/01/Renewable-Energy-Financing-Landscape-in-India_February-2022.pdf

[76] Unstarred Question No. 2905, Lok Sabha, Ministry of New and Renewable Energy, https://sansad.in/getFile/loksabhaquestions/annex/186/AU2905_YvJJ0B.pdf?source=pqals.  

[77] “Bridging the clean energy investment gap: Cost of capital in the transition to net-zero emissions”, OEDC Working Paper, July 18, 2024, https://www.oecd.org/content/dam/oecd/en/publications/reports/2024/07/bridging-the-clean-energy-investment-gap_a524f35e/1ae47659-en.pdf

[78] “Waiver of inter-state transmission charges on transmission of the electricity generated from solar and wind sources of energy under Para 6.4(6) of the Tariff Policy, 2016”, Ministry of Power, November 23, 2021, https://powermin.gov.in/sites/default/files/uploads/Orders/B.4.3.pdf.

[80] Starred Question No. 122, Rajya Sabha, Ministry of Power, August 1, 2023, https://powermin.gov.in/sites/default/files/uploads/RS0108.2023_Eng.pdf

[81] 17th Report, Standing Committee on Energy, March 2021, https://sansad.in/getFile/lsscommittee/Energy/17_Energy_17.pdf?source=loksabhadocs.

[82] Central Electricity Regulatory Commission (Terms and Conditions for Renewable Energy Certificates for Renewable Energy Generation) Regulations, 2022, https://cercind.gov.in/regulations/REC-Regulations-2022.pdf.

[83] “MNRE Steps Up Global Collaboration for Advancing Geothermal Energy in India”, Ministry of New and Renewable Energy, December 8, 2025, https://www.pib.gov.in/PressReleasePage.aspx?PRID=2200435&reg=3&lang=2.

[84] Unstarred Question No. 1911, Rajya Sabha, Ministry of New and Renewable Energy, December 16, 2025, https://sansad.in/getFile/annex/269/AU1911_yHbV09.pdf?source=pqars.

[85] “National Policy on Geothermal Energy”, Ministry of New and Renewable Energy, September 15, 2025, https://cdnbbsr.s3waas.gov.in/s3716e1b8c6cd17b771da77391355749f3/uploads/2025/09/202509152136711668.pdf

[86] “Green Energy Corridor”, Ministry of Power website, as accessed on December 23, 2025, https://powermin.gov.in/en/content/green-energy-corridor#:~:text=The%20InSTS%20GEC%20scheme%20with,extension%20up%20to%20June%202025.

[87] Draft National Electricity Plan Vol. II – Transmission, Central Electricity Authority, https://cea.nic.in/wpcontent/uploads/psp___a_i/2024/01/Draft_NEP_Vol_II.pdf.

[88] “Union Cabinet approves Production-linked Incentive (PLI) Scheme for Specialty Steel”, Press Information Bureau, Cabinet, July 22, 2021, https://www.pib.gov.in/PressReleasePage.aspx?PRID=1737722&reg=3&lang=2

[89] Unstarred Question No. 331, Lok Sabha, December 2, 2025, https://steel.gov.in/sites/default/files/2025-12/lu%20331.pdf.

[92] State Finances: A Study of Budgets of 2019-20, Reserve Bank of India, September 30, 2019, https://rbidocs.rbi.org.in/rdocs/Publications/PDFs/STATEFINANCE201920E15C4A9A916D4F4B8BF01608933FF0BB.PDF

[93] “National Level AT&C Losses in Power Network down from 22.3% in 2020-21 to 16.4% in 2021-22”, Press Information Bureau, Ministry of Power, August 11, 2023, https://www.pib.gov.in/PressReleaseIframePage.aspx?PRID=1947709&reg=3&lang=2

 

[95] “Coal 2023”, International Energy Agency, December 2023, https://www.iea.org/reports/coal-2023.  

[97] Writ Petition (C) 104 OF 2014, Supreme Court of India, August 6, 2025, https://api.sci.gov.in/supremecourt/2015/14553/14553_2015_6_1501_62958_Judgement_06-Aug-2025.pdf

[98] Reports on the Performance of Power Utilities, Power Finance Corporation, https://pfcindia.com/ensite/Home/VS/29.

[99] Turning Around the Power Distribution Sector, NITI Aayog, August 2021, niti.gov.in/sites/default/files/2021-08/Electricity-Distribution-Report_030821.pdf.

DISCLAIMER: This document is being furnished to you for your information.  You may choose to reproduce or redistribute this report for non-commercial purposes in part or in full to any other person with due acknowledgement of PRS Legislative Research (“PRS”).  The opinions expressed herein are entirely those of the author(s).  PRS makes every effort to use reliable and comprehensive information, but PRS does not represent that the contents of the report are accurate or complete.  PRS is an independent, not-for-profit group.  This document has been prepared without regard to the objectives or opinions of those who may receive.