Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified. Last date for submitting the applications is December 21, 2024.

On December 1, 2010, the Judicial Standards and Accountability Bill was introduced in the Lok Sabha.  The Bill revamps the present system of inquiry into complaints against judges.  The case of Justice Sen was the one of the more recent instances where the integrity of judges has been called into question.

A motion was moved by 58 members of the Rajya Sabha for the removal of Justice Soumitra Sen, (a Judge of the Calcutta High Court) on grounds of misappropriation of funds. The Chairman, Rajya Sabha constituted an Inquiry Committee on March 20, 2009 to look into the matter. The Committee comprising Hon’ble Justice B. Sudershan Reddy (Chairman), Hon’ble Justice T.S.Thakur and Shri Fali S. Nariman submitted its report on September 10, 2010.

Charges framed in the Motion

The two charges which led to an investigation into alleged misconduct of Justice Soumitra Sen were:

  • Misappropriation of large sums of money, which he had received in his capacity as Receiver appointed by the High Court of Calcutta; and
  • Misrepresentation of facts with regard to the misappropriation of money before the High Court of Calcutta

 

General observations of the Committee on the case:

  • Justice Sen’s assertion that he had the right to remain silent during the investigations was fallacious.
  • He did not cooperate with the Court proceedings; was not present for hearings, did not furnish information requested by the Court and did not provide any evidence in his defence.

 

Facts and Findings of the investigation by the Committee:

a. During the period he was an Advocate:

  • Justice Soumitra Sen was appointed Receiver in a case by an order of the Calcutta High Court on April 30, 1984. A Receiver appointed by the High Court has the power to collect outstanding debts and claims due in respect of certain goods.
  • As required by the High Court, the Receiver should file and submit for passing,     his half yearly accounts in the Office of the Registrar of the High Court. However, Justice Sen did not comply with this rule both as an Advocate and a Judge.
  • The High Court requires the Receiver to open only one account and not move funds without prior permission. However, the Committee found that two separate accounts were opened by Justice Soumitra Sen as Receiver, with ANZ Grindlays Bank and Allahabad Bank.
  • A total sum of Rs 33,22,800 was transferred in these accounts from the sale of proceeds of the goods which was not accounted for either when Justice Sen was an Advocate or when he was made a High Court Judge.
  • Justice Sen claimed he could not account for this amount since it was invested in a company called Lynx India Ltd. to earn interest. The Committee found this claim to be false as well.
  • The Committee concluded that this was a case of misappropriation of funds as both of the Receiver’s bank accounts were closed with a nil balance without any investments being made on behalf of the High Court.

b. During the period he was a Judge:

  • Justice Soumitra Sen was appointed a High Court Judge on December 3, 2003. The committee noted that Justice Sen’s actions were, “an attempt to cover up the large-scale defalcations of Receiver’s funds”.
  • After he became a Judge he did not seek any permission from the Court for approval of the dealings, as required by the Court, nor did he account for the funds.

Conclusion

Based on the findings on the two charges the Inquiry Committee was of the opinion that Justice Soumitra Sen of the Calcutta High Court is guilty of “misbehaviour”.

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.