The Land Acquisition Bill is slated to be taken up for consideration and passing in the Lok Sabha today. The government had circulated an amendment list in the last session of Parliament. In a column in the Financial Express, MR Madhavan discusses the major features of the Land Acquisition Bill and the associated issues that Parliament may need to consider while deliberating on the Bill. Economic growth and job creation require efficient usage of land resources. It is important that a fair and transparent process for purchase and for acquisition of land is followed. For the purchase of land, a key concern is the authenticity of land titles, and the government has drafted a Land Titling Bill for this purpose. In the case of land acquisition, the following questions need to be addressed. What are the end-uses for which public interests will trump private property rights, and justify acquisition of land from a person who is not willing to part with it? What should be the process followed? Since there is no market mechanism of discovery of prices in these cases, how should compensation be computed? Is there a need to address non-land owners who may be displaced by the acquisition process? Does the acquisition process get completed in a reasonable amount of time, and is there finality to the acquisition? In sum, do both sides—the acquirer and the land owner—perceive the process to be fair? The current Bill addresses these questions in the following manner. It defines public purpose to include infrastructure projects (as defined by the finance ministry, with some exclusions); projects related to agriculture, agro-processing and cold storage; industrial corridors, mining activities, national investment and manufacturing zones; government administered or aided educational and research institutions; sports, healthcare, transport and space programmes. It also enables the government to include other infrastructural facilities to this list after tabling a notification in Parliament. The significant difference from the current Land Acquisition Act, 1894, is that land cannot be acquired for use by companies unless they satisfy any of the above end-uses. The Bill includes a requirement for consent of the land owners in some cases. If the land is acquired for use by a private company, 80% of land owners need to give consent. If it is for use by a public private partnership (PPP), 70% of the land owners have to agree to the acquisition. The rationale of having differential consent requirements based on ownership—including the lack of any such requirement if the land is for the use of the government or a public sector undertaking—is not clear. Why should a land owner, who is losing his land care, whether the intended project is to be executed by the government or a private company? The Bill specifies that the compensation will be computed in the following manner. Three factors are taken into account: the circle rate according to the Stamp Act; the average of the top 50% of sale deeds registered in the vicinity in the previous three years; the amount agreed upon, if any, in case of purchase by a private company or PPP. The higher of these three amounts is multiplied by a factor, which varies from 1 in urban areas to a number between 1 and 2 in rural areas, depending upon the distance from the urban centre. To this amount, the value of any fixed assets such as buildings, trees, irrigation channels etc is added. Finally, this figure is doubled (as solatium, i.e. compensation for the fact that the transaction was made with an unwilling seller). The justification given for the multiplier ranging from 1 to 2 is that many transactions are registered at a price significantly lower than the actual value in order to evade taxes—the moot question is whether such under-reporting is uniform across the country? The Bill states that all persons who are affected by the project should be rehabilitated and resettled (R&R). The R&R entitlements for each family includes a house, a one-time allowance, and choice of (a) employment for one person in the project, (b) one-time payment of R5 lakh, or (c) inflation adjusted annuity of R2,000 per month for 20 years. In addition, the resettlement areas should have infrastructure such as a school, post office, roads, drainage, drinking water, etc. The process has several steps. Every acquisition, regardless of size, needs a social impact assessment, which will be reviewed by an expert committee, and evaluated by the state government. Then a preliminary notification will be issued, land records will be updated, objections will be heard, rehabilitation and resettlement survey carried out, and a final declaration of acquisition issued. The owners can then claim compensation, the final award will be announced, and the possession of the land taken. The total time for this process can last up to 50 months. The big question is whether this time frame would hinder economic development and the viability of projects? The Bill provides for an Authority to adjudicate disputes related to measurement of land, compensation payable, R&R etc, with appeals to be heard by the High Court. There are several restrictions on the land acquired. The purpose for which land is acquired cannot be changed. If land is not used for five years, it would be transferred to a land bank or the original owners. Transfer of ownership needs prior permission, and in case of transfer in the first five years, 40% of capital gains have to be shared with the original owners. Recent cases of land acquisition have been followed by public protests, and the stalling of the acquisition. Whereas some of these may be driven by political agendas, the old Act was perceived to be unfair to land owners in several ways. The challenge for Parliament is to examine the new Bill and craft the law in such a way that it is fair (and perceived as such) to land owners, while making acquisition feasible and practical for projects that are required for economic development and other areas of public interest.

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.