The Comptroller and Auditor General (CAG) released a Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production, on August 17, 2012.  Some of the main findings and recommendations of the report are highlighted below:

  • There were no criteria for allocating coal blocks for captive mining till 1993.  The process of bringing in transparency and objectivity began in January 2004.  However, the process has experienced delays and had yet to materialise as of February 2012.
  • In the intervening period, 194 coal blocks with geological reserves of 44,440 million tonnes were allocated to private and government parties until March 31, 2011.  The report finds that the benefit to private allottees has been estimated at Rs 1.86 lakh crore for Opencast mines.  The report states that the government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The rate of increase in production of coal by Coal India Limited (CIL) during the 11th Plan period remained below the target set by the Planning Commission.  Capacity addition projects were delayed due to the lack of coordination of government agencies involved in statutory clearances and land acquisition.  There were mismatches in excavation and transportation capacities of mines, and suboptimal use of Heavy Earth Moving Machinery.
  • The CAG recommends that Ministry of Coal (MOC) should work out modalities to implement the procedure of allocation of coal blocks for captive mining through competitive bidding.
  • The CAG recommends that the MOC should constitute an empowered group along the lines of Foreign Investment Promotion Board as a single window mechanism for granting clearances, with representatives from central nodal ministries and state governments.

A one-page summary of the main findings and recommendations can be accessed here.  The full report can be accessed on the CAG website.

In Budget Session 2018, Rajya Sabha has planned to examine the working of four ministries.  The Ministry of Drinking Water and Sanitation is one of the ministries listed for discussion.  In this post, we look at the key schemes being implemented by the Ministry and their status.

What are the key functions of the Ministry of Drinking Water and Sanitation?

As per the Constitution, supply of water and sanitation are state subjects which means that states regulate and provide these services.  The Ministry of Drinking Water and Sanitation is primarily responsible for policy planning, funding, and coordination of programs for: (i) safe drinking water; and (ii) sanitation, in rural areas.  From 1999 till 2011, the Ministry operated as a Department under the Ministry of Rural Development.  In 2011, the Department was made an independent Ministry.  Presently, the Ministry oversees the implementation of two key schemes of the government: (i) Swachh Bharat Mission-Gramin (SBM-G), and (ii) National Rural Drinking Water Programme (NRDWP).

How have the finances and spending priorities of the Ministry changed over time?

In the Union Budget 2018-19, the Ministry has been allocated Rs 22,357 crore.  This is a decrease of Rs 1,654 crore (7%) over the revised expenditure of 2017-18.  In 2015-16, the Ministry over-shot its budget by 178%.  Consequently, the allocation in 2016-17 was more than doubled (124%) to Rs 14,009 crore.

In recent years, the priorities of the Ministry have seen a shift (see Figure 1).  The focus has been on providing sanitation facilities in rural areas, mobilising behavioural change to increase usage of toilets, and consequently eliminating open defecation.  However, this has translated into a decrease in the share of allocation towards drinking water (from 87% in 2009-10 to 31% in 2018-19).  In the same period, the share of allocation to rural sanitation has increased from 13% to 69%.Figure 1

What has been the progress under Swacch Bharat Mission- Gramin?

The Swachh Bharat Mission was launched on October 2, 2014 with an aim to achieve universal sanitation coverage, improve cleanliness, and eliminate open defecation in the country by October 2, 2019.

Expenditure on SBM-G:  In 2018-19, Rs 15,343 crore has been allocated towards SBM-G.  The central government allocation to SBM-G for the five year period from 2014-15 to 2018-19 has been estimated to be Rs 1,00,447 crore.  Of this, up to 2018-19, Rs 52,166 crore (52%) has been allocated to the scheme.  This implies that 48% of the funds are still left to be released before October 2019.  Figure 2

Construction of Individual Household Latrines (IHHLs):  For construction of IHHLs, funds are shared between the centre and states in the 60:40 ratio.  Construction of IHHLs account for the largest share of total expenditure under the scheme (97%-98%).  Although the number of toilets constructed each year has increased, the pace of annual growth of constructing these toilets has come down.  In 2015-16, the number of toilets constructed was 156% higher than the previous year.  This could be due to the fact that 2015-16 was the first full year of implementation of the scheme.  The growth in construction of new toilets reduced to 74% in 2016-17, and further to 4% in 2017-18.Table 1

As of February 2018, 78.8% of households in India had a toilet.  This implies that 15 crore toilets have been constructed so far.  However, four crore more toilets need to be construced in the next 20 months for the scheme to achieve its target by 2019.

Open Defecation Free (ODF) villages:  Under SBM-G, a village is ODF when: (i) there are no visible faeces in the village, and (ii) every household as well as public/community institution uses safe technology options for faecal disposal.  After a village declares itself ODF, states are required to carry out verification of the ODF status of such a village.  This includes access to a toilet facility and its usage, and safe disposal of faecal matter through septic tanks.  So far, out of all villages in the country, 72% have been verified as ODF.  This implies that 28% villages are left to be verified as ODF for the scheme to achieve its target by 2019.Table 2

Information, Education and Communication (IEC) activities:  As per the SBM-G guidelines, 8% of funds earmarked for SBM-G in a year should be utilised for IEC activities.  These activities primarily aim to mobilise behavioural change towards the use of toilets among people.  However, allocation towards this component has remained in the 1%-4% range.  In 2017-18, Rs 229 crore is expected to be spent, amounting to 2% of total expenditure.

What is the implementation status of the National Rural Drinking Water Programme?

The National Rural Drinking Water Programme (NRDWP) aims at assisting states in providing adequate and safe drinking water to the rural population in the country.  In 2018-19, the scheme has been allocated Rs 7,000 crore, accounting for 31% of the Ministry’s finances.Figure 3

Coverage under the scheme:  As of August 2017, 96% of rural habitations have access to safe drinking water.  In 2011, the Ministry came out with a strategic plan for the period 2011-22.  The plan identified certain standards for coverage of habitations with water supply, including targets for per day supply of drinking water.  As of February 2018, 74% habitations are fully covered (receiving 55 litres per capita per day), and 22% habitations are partially covered (receiving less than 55 litres per capita per day).  The Ministry aims to cover 90% rural households with piped water supply and 80% rural households with tap connections by 2022.  The Estimates Committee of Parliament (2015) observed that piped water supply was available to only 47% of rural habitations, out of which only 15% had household tap connections.

Contamination of drinking water:  It has been noted that NRDWP is over-dependant on ground water.  However, ground water is contaminated in over 20 states.  For instance, high arsenic contamination has been found in 68 districts of 10 states.  These states are Haryana, Punjab, Uttar Pradesh, Bihar, Jharkhand, Chhattisgarh, West Bengal, Assam, Manipur, and Karnataka.Table 3

Chemical contamination of ground water has also been reported due to deeper drilling for drinking water sources.  It has been recommended that out of the total funds for NRDWP, allocation for water quality monitoring and surveillance should not be less than 5%.  Presently, it is 3% of the total funds.  It has also been suggested that water quality laboratories for water testing should be set up throughout the country.