The Comptroller and Auditor General (CAG) released a Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production, on August 17, 2012.  Some of the main findings and recommendations of the report are highlighted below:

  • There were no criteria for allocating coal blocks for captive mining till 1993.  The process of bringing in transparency and objectivity began in January 2004.  However, the process has experienced delays and had yet to materialise as of February 2012.
  • In the intervening period, 194 coal blocks with geological reserves of 44,440 million tonnes were allocated to private and government parties until March 31, 2011.  The report finds that the benefit to private allottees has been estimated at Rs 1.86 lakh crore for Opencast mines.  The report states that the government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The rate of increase in production of coal by Coal India Limited (CIL) during the 11th Plan period remained below the target set by the Planning Commission.  Capacity addition projects were delayed due to the lack of coordination of government agencies involved in statutory clearances and land acquisition.  There were mismatches in excavation and transportation capacities of mines, and suboptimal use of Heavy Earth Moving Machinery.
  • The CAG recommends that Ministry of Coal (MOC) should work out modalities to implement the procedure of allocation of coal blocks for captive mining through competitive bidding.
  • The CAG recommends that the MOC should constitute an empowered group along the lines of Foreign Investment Promotion Board as a single window mechanism for granting clearances, with representatives from central nodal ministries and state governments.

A one-page summary of the main findings and recommendations can be accessed here.  The full report can be accessed on the CAG website.

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.