The Comptroller and Auditor General (CAG) released a Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production, on August 17, 2012.  Some of the main findings and recommendations of the report are highlighted below:

  • There were no criteria for allocating coal blocks for captive mining till 1993.  The process of bringing in transparency and objectivity began in January 2004.  However, the process has experienced delays and had yet to materialise as of February 2012.
  • In the intervening period, 194 coal blocks with geological reserves of 44,440 million tonnes were allocated to private and government parties until March 31, 2011.  The report finds that the benefit to private allottees has been estimated at Rs 1.86 lakh crore for Opencast mines.  The report states that the government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The rate of increase in production of coal by Coal India Limited (CIL) during the 11th Plan period remained below the target set by the Planning Commission.  Capacity addition projects were delayed due to the lack of coordination of government agencies involved in statutory clearances and land acquisition.  There were mismatches in excavation and transportation capacities of mines, and suboptimal use of Heavy Earth Moving Machinery.
  • The CAG recommends that Ministry of Coal (MOC) should work out modalities to implement the procedure of allocation of coal blocks for captive mining through competitive bidding.
  • The CAG recommends that the MOC should constitute an empowered group along the lines of Foreign Investment Promotion Board as a single window mechanism for granting clearances, with representatives from central nodal ministries and state governments.

A one-page summary of the main findings and recommendations can be accessed here.  The full report can be accessed on the CAG website.

Bihar became the first state to scrap the MLA Local Area Development Fund scheme (MLALAD).  According to news reports, Nitish Kumar, Bihar’s Chief Minister, is planning to replace it with the CM Area Development Programme, which would be implemented at the District level.  The schemes would be selected by a district selection committee headed by the minister-in-charge and MLAs and MLCs of that district as members.  The implementation shall rest with a body of engineers, headed by Engineer-in-chief.  The district magistrates would only monitor implementation and contractors would be chosen through open tendering in which a representative of the Comptroller and Auditor General of India (CAG) would be present.  The state government would allocate funds as per requirement. The MPLAD and MLALAD scheme was introduced in December 1993 by former Prime Minister, P.V. Narasimha Rao to enable legislators to execute small works of a local nature to meet the urgent needs of their constituents.  Under the scheme, each legislator may identify projects and sanction upto Rs 2 crore per year for public works in their constituencies.  The scheme was mooted after MPs demanded that they should be able to recommend certain development projects in their constituencies.  The projects include assets building such as drinking water facilities, primary education, public health sanitation and roads.  The initial amount allocated was Rs 5 lakh per year to each MP. It has however not been smooth sailing for the scheme.  Besides the many implementation lapses (as pointed out by the Standing Committee on Finance in 1998-1199, the CAG and the Planning Commission), the constitutionality of the scheme has been questioned by various scholars and experts. In 2002, the National Commission to Review the Working of the Constitution recommended immediate discontinuation of the MPLAD scheme on the ground that it was inconsistent with the spirit of federalism and distribution of powers between the centre and the state.  Former MP, Era Sezhiyan in a booklet titled ‘MPLADS – Concept, Confusion and Contradictions’ also opposed the scheme and recommended that it be scrapped since it ran contrary to the Constitutional provisions which envisaged separate roles for the Executive and Legislature.  However, the Committee on MPLADS in its 13th Report and its 15th Report stated that there was nothing wrong with the scheme per se except some procedural infirmities and recommended among other things a change of nomenclature to the Scheme for Local Area Development.  The debate continued with the 2nd Administrative Reforms Commission’s report on “Ethics in Governance” taking a firm stand against the scheme arguing that it seriously erodes the notion of separation of powers, as the legislator directly becomes the executive.  However, in response to a Writ Petition that challenged the constitutionality of the MPLAD scheme as ultra vires of the Constitution of India, in May 2010, a five-judge bench of the Supreme Court ruled that there was no violation of the concept of separation of powers because the role of an MP in this case is recommendatory and the actual work is carried out by the Panchayats and Municipalities which belong to the executive organ.  There are checks and balances in place through the guidelines which have to be adhered to and the fact that each MP is ultimately responsible to the Parliament. Meanwhile, some MPs are pushing for hiking the amount allocated under the scheme to Rs 5 crore.  However, no decision has been reached yet.  The Ministry of Statistics and Programme Implementation has suggested that a single parliamentary committee be formed comprising of members of both Houses of Parliament to monitor MPLAD schemes. While the question of constitutionality of the MPLAD scheme may have been put to rest by the Supreme Court ruling, other issues related to implementation of the scheme still remain.  Unless problems such as poor utilisation of funds, irregular sanction of works, delay in completion of works are tackled in an efficient manner, the efficacy of the scheme will remain in doubt.