In a recent judgement (Judgement on Feb 23 - Baldev Singh and Ors. V. State of Punjab), the Supreme Court reduced the sentence of three persons convicted of rape from 10 years to 3 and a half years, and also asked the three convicts to pay a fine of Rs 50,000 each to the victim.   In reducing the sentence, the court drew from the provision in S. 376 (punishment for rape) of the Indian Penal Code which allows the court to reduce the sentence for "adequate and special reasons". There have been a number of past cases where the Supreme Court has reversed High Court decisions reducing sentences under this provision for not giving suitable reasons.  In 2007, the Supreme Court struck down a decision of the Karnataka High Court which had reduced the sentence of a convicted rapist to 3 and a half years.  The High Court had stated that the sentence should be reduced since the accused was "a young boy of 18 years belonging to Vaddara Community and Illiterate".  The Supreme Court stated that there is a legislative mandate to impose a sentence for not less than 10 years.  Only in exceptional cases, for "adequate and special reasons" can a sentence less than 10 years be imposed.  It overturned the Karnataka High Court decision saying that there was an "absence of any reason which could have been treated as "special and adequate reason"". In Baldev Singh's case, the Supreme Court said: 1.  The fact that the incident is an old one (the incident took place in 1997) is a circumstance which fits into "adequate and special reasons" for reducing a sentence. 2. The parties have entered into a compromise among themselves. The issue is whether this judgement has gone beyond the legislative mandate, and whether it has adhered to the principles laid down by earlier decisions of the Supreme Court.  In 2007, the Supreme Court itself stated that for a crime like rape, strong reasons have to be given to reduce the sentence envisaged by the legislature.  Moreover, the provision does not envisage the settlement of a crime by payment of compensation to the victim of a crime.  A criminal act is seen in law as a crime against the whole of society (which is why the state's prosecution agency, and not the victim, goes to court against alleged criminals).  Therefore, criminal actions such as rape (or murder, robbery, kidnapping etc.) cannot be "settled" by the payment of compensation under the Indian Penal Code.  In this light, it should be interesting to see whether the State files an appeal against this judgement.

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.