The Civil Damage for Nuclear Liability Bill, 2010 has been criticised on many grounds (Also click here), including (a) capping liability for the operator, (b) fixing a low cap on the amount of liability of the operator, and (c) making the operator solely liable.  We summarise the main principles of civil nuclear liability mentioned in IAEA's Handbook on Nuclear Law: Strict Liability of the Operator: The operator is held liable regardless of fault.  Those claiming compensation do not need to prove negligence or any other type of fault on the part of the operator.  The operator is liable merely by virtue of the fact that damage has been caused. Legal channeling of liability on the operator: "The operator of a nuclear installation is exclusively liable for nuclear damage. No other person may be held liable, and the operator cannot be held liable under other legal provisions (e.g. tort law)...This concept is a feature of nuclear liability law unmatched in other fields of law."  The reason for this has been quoted in the Handbook as:

"...Firstly, it is desirable to avoid difficult and lengthy questions of complicated legal cross-actions to establish in individual cases who is legally liable. Secondly, such channelling obviates the necessity for all those who might be associated with construction or operation of a nuclear installation other than the operator himself to take out insurance also, and thus allows a concentration of the insurance capacity available.”

Limiting the amount of liability: "Limitation of liability in amount is clearly an advantage for the operator.  Legislators feel that unlimited liability, or very high liability amounts, would discourage people from engaging in nuclear related activities. Operators should not be exposed to financial burdens that could entail immediate bankruptcy....Whatever figure is established by the legislator will seem to be arbitrary, but, in the event of a nuclear catastrophe, the State will inevitably step in and pay additional compensation. Civil law is not designed to cope with catastrophes; these require special measures." Limitation of liability in time: "In all legal systems there is a time limit for the submission of claims. In many States the normal time limit in general tort law is 30 years. Claims for compensation for nuclear damage must be submitted within 30 years in the event of personal injury and within 10 years in the event of other damage. The 30 year period in the event of personal injury is due to the fact that radiation damage may be latent for a long time; other damage should be evident within the 10 year period." Insurance coverage: "The nuclear liability conventions require that the operator maintain insurance or provide other financial security covering its liability for nuclear damage in such amount, of such type and in such terms as the Installation State specifies....This ensures that the liability amount of the operator is always covered by an equal amount of money. The congruence principle is to the advantage both of the victims of a nuclear incident and of the operator. The victims have the assurance that their claims are financially covered, and the operator has funds available for compensation and does not need to convert assets into cash.

Reports suggest that a debt restructuring plan is being prepared for power distribution companies (discoms) in seven states - Uttar Pradesh, Punjab, Rajasthan, Haryana, Andhra Pradesh, Tamil Nadu and Madhya Pradesh.  According to some estimates, the combined outstanding debt for discoms is Rs 2 lakh crore.  Discoms have been facing heavy losses.  According to a Planning Commission Report, the cost of supplying electricity increased at a rate of 7.4 per cent annually between 1998-99 and 2009-10.  The average tariff has also increased at an annual rate of 7.1 per cent over the same period.  However, the report shows that the average tariff per unit of electricity has consistently been much lower than average cost of supply per unit.  Between 2007-08 and 2011-12, the gap between average cost and average tariff per unit of electricity was between 20 and 30 per cent of costs.

Average cost and average tariff per unit of electricity (Rs per kWh)

Year

Unit cost

Average tariff per unit

Gap between cost and tariff

Gap as percentage of unit cost

2007-08

4.04

3.06

0.98

24%

2008-09

4.6

3.26

1.34

29%

2009-10

4.76

3.33

1.43

30%

2010-11

4.84

3.57

1.27

26%

2011-12

4.87

3.8

1.07

22%

Source: “Annual Report 2011-12 on the Working of State Power Utilities and Electricity Departments”, Planning Commission State discoms have been losing money due to higher costs than revenues, as well as high transmission and distribution (T&D) losses.  The commercial losses for discoms in India (after including subsidies) increased from Rs 16,666 crore in 2007-08 to Rs 37,836 crore in 2011-12. Reports suggest that the restructuring plan being prepared will be worth Rs 1.2 lakh crore in short-term liabilities.  Half of the proposed amount would be issued as bonds by the discoms, backed by a state government guarantee.  Banks and financial institutions would reschedule the remaining Rs 60,000 crore of debt, with a moratorium of three years on payment of the principal amount.  State governments that adopt the financial restructuring plan would not recover any loans given to discoms before they start showing profits. Under a proposed transition finance mechanism, the central government would reimburse 25 per cent of the principal amount of bonds to states that fully implement the plan.  Also, states that achieve a reduction in T&D losses above a targeted level in three years may be given grants.  Newspaper reports also suggest that states will have to prepare plans for eliminating the gap between the average cost and average tariff per unit of electricity.