Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.

On March 19, Gujarat reported its first two cases of COVID-19. Since then, the number of cases have risen steadily. As of May 2, Gujarat has 4,721 confirmed cases (second highest in the country, after Maharashtra) of COVID-19. Of this 3,750 are active cases and 236 have died. The state government has responded with various actions to contain the spread and impact of COVID-19.  In this blog, we look at the key measures taken by the Gujarat Government till May 1, 2020.

 image

Initial phase 

As COVID-19 cases were rising in other parts of the country, the Gujarat government notified the Gujarat Epidemic Diseases, COVID-19 Regulations, 2020 on March 14,. These regulations detail the responsibilities of hospitals and individuals, and the powers of officials with regards to COVID-19. These include: (i) flu corners in all hospitals for screening purposes, (ii) mandatory collection of travel history of people during screenings in all hospitals, (iii) mandating people with travel history to COVID-affected countries to be isolated /quarantined based on symptoms, (iv) forced detention and isolation of suspected patients who refuse voluntary isolation, and (v) containment measures in an area once positive cases are detected.   Some of the other early measures are summarised below:

Health measures

  • The COVID-19 regulations were immediately supplemented with the n-COVID-19 Guidelines. These guidelines cover: (i) case definitions, (ii) basic infection prevention control measures, and (iii) standard precautions to be followed during the care and treatment of suspected patients.

  • On March 15, the government instructed all higher education institutions and other educational institutions including schools, polytechnics, anganwadis, to shut down till March 29. However, examinations of class X, XII, and universities were permitted to continue. Further, spitting in public was made a punishable offence. 

  • On March 19, the government ordered the closure of gyms, amusement parks, wedding halls, till March 31. Additionally, all private doctors, practising modern as well as traditional systems of medicine, were instructed to report suspect cases to the government. 

  • Fever Helpline 104 was launched on March 20 for reporting of suspect cases of COVID-19. Further, guidelines were also issued on the reporting of cases of Severe Acute Respiratory Illnesses (SARI) to the government. These include: (i) preparation of travel history and contact lists of reported suspect cases, (ii) nodal officer to decide on steps and treatment protocol for such cases, (iii) relevant authorities to initiate follow up and contact tracing for the patient for last 14 days, and (iv) initiating cluster management guidelines when new cases emerge. 

Essential goods and services

  • On March 20, a committee was formed by the government for daily monitoring of the availability, supplies, and manufacturing of medicines, masks, and sanitisers. On March 21, a Khas Kharid Committee was set up to ensure procurement of necessary medicines, equipments, and human resources during emergencies, bypassing existing purchase guidelines, if necessary. 

  • Between March 21 and March 22, the government announced a partial lockdown and released a list of essential services and businesses that were allowed to operate till March 25 in the cities of Ahmedabad, Surat, Vadodara,Rajkot, Kutch and Gandhinagar. These include: (i) government and municipal departments, (ii) shops selling essential goods, (iii) various medical facilities such as hospitals, clinics, and pharmacies, (iv) public utilities, (v) railways and transportation facilities, (vi) media, telecom, IT services, and (vii) banks and insurance firms.

  • The government also invited NGOs to collaborate in the fight against COVID-19, by arranging for the supply of masks, sanitisers, and infrared thermometers, and running awareness campaigns.      

Administrative measures

  • On March 18, the government issued guidelines specifying preventive measures to be taken in all government offices and employees. Recommendations inlcude: (i) avoiding face-to-face meetings and non-essential travel, (ii) closure of gyms and yoga centres in the Secretariat, (iii) home quarantine for officials exhibiting any symptoms, and (iv) mandatory leave to be given to such persons going on quarantine.

  • On March 21, the government released the terms of reference of Regional Nodal Officers appointed to work towards preventing the spread of COVID-19.

  • On March 23, the Gujarat Legislative Assembly decided to indefinitely postpone the Rajya Sabha elections that were originally to be held on March 26. 

Other measures

  • An advisory was issued requesting private firms to not lay off workers (even if they fall sick to COVID-19) or reduce their salaries. 

During the lockdown

On March 23, the state government extended and expanded the partial lockdown announced in select cities to the entire state. The lockdown was to be in place from March 23 to March 31. In addition to the exemptions announced in the partial lockdown orders, services such as (i) cattle feeding and veterinary services, (ii) stock broking, (iii) postal and courier services, and (iv) operation of industries where workers are available on site, were permitted.  The state-wide lockdown has been followed by a nation-wide lockdown since March 25 . This has been further extended until May 17.  Some of the key measures undertaken during the lockdown period are: 

Health measures

  • On March 27, all private clinics and hospitals in the state were directed to utilise the Dr. TeCHO mobile app developed by the government. The app can be used for uploading information related to: (i) sample collection and (ii) reporting and surveillance of all SARI cases. Another app was launched to keep track of home quarantined people. 

  • On March 30, COVID-19 was included as a notified disaster under the State Disaster Response Fund (SDRF). Thus, all expenditure related to relief measures for displaced / homeless people, migrant labour or other stranded persons due to the lockdown, will be made out of the SDRF. 

  • On March 31, the government released new guidelines for the clinical management of COVID-19. These cover: (i) triage activities, (ii) case definitions and classification, (iii) infection and prevention control measures, (iii) specimen collection and handling, (iv) management and prevention of medical complications, (v) clinical management for COVID-19, (vi) discharge policy for patients, and (vii) dead body management. 

  • To exclusively cater to COVID-19 cases, four government hospitals and three private hospitals were declared as designated COVID-19 treatment facilities. Further, the government instructed all COVID-19 hospitals to provide treatment to the people free of cost. On May 1, 26 hospitals were additionally designated as COVID-19 facilities.

  • Resource Management: Between March 31 and April 7, the government initiated multiple measures to address the shortage of medical practitioners in government hospitals. These include: (i) extending tenures of retiring medical personnel, (ii) ad-hoc recruitment of teachers in medical colleges, (iii) contract-based appointments of class-1 specialist and class-2 medical officers from private sector, (iv) additional responsibilities to select class-1 doctors from the epidemiologist department, and (v) temporary shifting of Ayurvedic medical officers to various locations.

  • On March 28, the state released guidelines for Human Resource management (HRM) in COVID-19 facilities. These include: (i) creation of district level task forces, (ii) patient flow algorithm, (iii) deployment and rotation of HR, including residents and nursing staff, and (iv) pooling of HR from various institutes and cadres. 

  • The state has also allowed the use of AYUSH remedies and medicines, particularly for persons quarantined through contact tracing and to frontline personnel. Teams of corona warriors have been formed to assist people with preventive care. In addition, local officials have been asked to utilise the services of important stakeholders such as teachers, priests, and others, who can influence the social behaviour of people to deal with COVID-19.

  • A new State Health System Resource Centre has been established as the nodal agency in the state for all COVID-19 related research. Further, a COVID-19 research activity committee has been set up to lead this endeavour.

Welfare measures

  • On March 25, the state government decided to provide ration to 60 lakh poor families who live on daily wages. Further, on March 28,  to minimise the adverse effects of lockdown on casual labour, autorickshaw drivers, and street vendors, the government announced free wheat, rice, pulses, sugar, and iodised salt for the month of April 2020. 

  • Vadil Vandana scheme was launched to provide free of cost meals to the elderly and the aged living alone in various cities of the state.

  • The state also announced that electricity bills from March 1 to April 30, can be paid by May 15.

  • The government announced compensatory packages worth Rs 25 lakh for each frontline worker who may lose life on COVID-19 duty. Such workers include: (i) police personnel and (ii) other government employees under the state government, panchayats, and nagar palikas .

Other measures

  • Industry: Relaxations from the lockdown were announced for factories and IT/ITES firms, from April 20 onwards. For factories, the conditions specified that adult workers shall be allowed to work for not more than 12 hours per day (six hours at a time) or 72 hours per week. Female workers are not allowed to work between 7 pm and 6 am. Wages are to be proportional to the existing wage structure.  IT/ITES firms are allowed operate in non-containment zones at 50% strength and social distancing norms will be required to be followed. 

  • Administrative: On March 30, the government issued an order to continue paying full wages to all fixed-pay government employees who are on leave or working from home during the lockdown. However, the employees are required to report to work whenever required by the government during the lockdown.

  • On April 15, nodal officers were appointed and given additional financial powers to take control of infectious disease control hospitals. 

For more information on the spread of COVID-19 and the central and state government response to the pandemic, please see here.