Census 2011 or the 15th National Census, a gigantic exercise to capture the socio-economic and cultural profile of India’s population, began on April 1, 2010.  India undertakes this exercise every 10 years through the Office of the Registrar General and Census Commissioner in the Ministry of Home Affairs.  The census documents details of a billion plus population on diverse subjects such as demography, literacy, fertility and mortality and provides primary data at village, town and ward level. The first census ever to take place in India was in 1872 and the last one was held in 2001.  The Census of India Act, 1948 lays down the rules and regulations pertaining to conduct of a census.  The Act makes it obligatory for the public to answer all the questions faithfully while guaranteeing the confidentiality of the information. The last census was held in 2001, which revealed that India’s population was about 1.03 billion.  Statistical data related to literacy rate, sex-ratio, urban-rural distribution, religious composition, SC/ST population and so on were captured by Census 2001. Features of Census 2011 Census process: India uses the canvasser method for collecting census data.  Under this method, the canvasser approaches every household and records the answer on the schedules himself after ascertaining the particulars from the head of the household or other knowledgeable persons in the household.  The full detail of the methodology is available here. National Population Register (NPR): It would be a register or database of residents of the country.  The government states that such a database would facilitate better targeting of the benefits and services under government schemes and programmes; improve planning and help strengthen the security of the country.  The register is being created under the provisions of the Citizenship Act and Rules. NPR process: Basic details such as name, date of birth and sex shall be gathered by visiting each household of a resident of the country. A database shall be created with addition of biometric information such as photograph, 10 fingerprints and probably Iris information for all persons aged 15 years and above.  The list shall be sent to the Unique Identity Authority of India (UIDAI) for de-duplication and issue of UID Numbers.  The cleaned database along with the UID Number would form the National Population Register. There was a controversy over whether Census 2011 should capture caste data.  Since India last collected caste data in 1931, proponents argued that up-to-date, reliable caste data was essential to target welfare schemes towards various backward castes. Opponents however contended that this would perpetuate the caste system.  The government finally decided not to include caste as one of the parameters in the 2011 census. Table 1: Schedule of Census 2011

Schedule State/UT
April 1 New Delhi (NDMC area), West Bengal, Assam,  Andaman & Nicobar Islands, Goa, Meghalaya, Bihar, Jharkhand
April 7 Kerala, Lakshadweep, Orissa, Himachal Pradesh, Sikkim
April 15 Karnataka, Arunachal Pradesh, Chandigarh
April 21 Gujarat, Dadra & Nagar Haveli, Daman & Diu
April 26 Tripura, Andhra Pradesh
May 1 Haryana, Chhattisgarh, Delhi, Punjab, Uttaranchal, Maharashtra
May 7 Madhya Pradesh
May 15 J & K, Manipur, Mizoram, Rajasthan, Uttar Pradesh
June 1 Tamil Nadu, Puducherry, Nagaland

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.