On March 10, Lok Sabha passed a Bill to amend the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.  The Bill is now pending in Rajya Sabha.  This blog briefly outlines the context and the major legislative changes to the land acquisition law. I. Context Land acquisition, unlike the purchase of land, is the forcible take-over of privately owned land by the government.  Land is acquired for projects which serve a ‘public purpose’.  These include government projects, public-private partnership projects, and private projects.  Currently, what qualifies as ‘public purpose’ has been defined to include defence projects, infrastructure projects, and projects related to housing for the poor, among others. Till 2014, the Land Acquisition Act, 1894 regulated the process of land acquisition.  While the 1894 Act provided compensation to land owners, it did not provide for rehabilitation and resettlement (R&R) to displaced families.  These were some of the reasons provided by the government to justify the need for a new legislation to regulate the process of land acquisition.  Additionally, the Supreme Court had also pointed out issues with determination of fair compensation, and what constitutes public purpose, etc., in the 1894 Act.  To this end, the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 was passed by Parliament, in 2013. II. Current legislative framework for land acquisition The 2013 Act brought in several changes to the process of land acquisition in the country.   Firstly, it increased the compensation provided to land owners, from 1.3 times the price of land to 2 times the price of land in urban areas, and 2-4 times the price of land in rural areas.  Secondly, unlike the earlier Act which did not provide rehabilitation and resettlement, the 2013 Act provided R&R to land owners as well as those families which did not own land, but were dependent on the land for their livelihood.  The Act permits states to provide higher compensation and R&R. Thirdly, unlike the previous Act, it mandated that a Social Impact Assessment be conducted for all projects, except those for which land was required urgently.  An SIA assesses certain aspects of the acquisition such as whether the project serves a public purpose, whether the minimum area that is required is being acquired, and the social impact of the acquisition.  Fourthly, it also mandated that the consent of 80% of land owners be obtained for private projects, and the consent of 70% of land owners be obtained for public-private partnership projects.  However, consent of land owners is not required for government projects.   The 2013 Act also made certain other changes to the process of land acquisition, including prohibiting the acquisition of irrigated multi-cropped land, except in certain cases where the limit may be specified by the government. III. Promulgation of an Ordinance to amend the 2013 Act In addition to the 2013 Act, there are certain other laws which govern land acquisition in particular sectors, such as the National Highways Act, 1956 and the Railways Act, 1989.  The 2013 Act required that the compensation and R&R provisions of 13 such laws be brought in consonance with it, within a year of its enactment, (that is, by January 1, 2015) through a notification.  Since this was not done by the required date, the government issued an Ordinance (as Parliament was not in session) to extend the compensation and R&R provisions of the 2013 Act to these 13 laws.  However, the Ordinance also made other changes to the 2013 Act. The Ordinance was promulgated on December 31, 2014 and will lapse on April 5, 2015 if not passed as a law by Parliament.  Thus, the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Amendment) Bill, 2015 has been introduced in Parliament to replace the Ordinance.  The Bill has been passed by Lok Sabha, with certain changes, and is pending in Rajya Sabha.  The next section outlines the major changes the Bill (as passed by Lok Sabha) proposes to make to 2013 Act. IV. Changes proposed by the 2015 Bill to the 2013 Act Some of the major changes proposed by the 2015 Bill (as passed by Lok Sabha) relate to provisions such as obtaining the consent of land owners; conducting an SIA; return of unutilised land; inclusion of private entities; and commission of offences by the government. Certain exemptions for five categories of projects: As mentioned above, the 2013 Act requires that the consent of 80% of land owners is obtained when land is acquired for private projects, and the consent of 70% of land owners is obtained when land is acquired for public-private partnership projects.  The Bill exempts five categories of projects from this provision of the 2013 Act.  These five categories are: (i) defence, (ii) rural infrastructure, (iii) affordable housing, (iv) industrial corridors (set up by the government/government undertakings, up to 1 km on either side of the road/railway), and (v) infrastructure projects. The Bill also allows the government to exempt these five categories of projects from: (i) the requirement of a Social Impact Assessment, and (ii) the limits that apply for acquisition of irrigated multi-cropped land, through issuing a notification.  Before issuing this notification, the government must ensure that the extent of land being acquired is in keeping with the minimum land required for such a project. The government has stated that these exemptions are being made in order to expedite the process of land acquisition in these specific areas.  However, the opponents of the Bill have pointed out that these five exempted categories could cover a majority of projects for which land can be acquired, and consent and SIA will not apply for these projects. Return of unutilised land: Secondly, the Bill changes the time period after which unutilised, acquired land must be returned.  The 2013 Act states that if land acquired under it remains unutilised for five years, it must be returned to the original owners or the land bank.  The Bill changes this to state that the period after which unutilised land will need to be returned will be the later of: (i) five years, or (ii) any period specified at the time of setting up the project. Acquisition of land for private entities: Under the 2013 Act, as mentioned above, land can be acquired for the government, a public-private partnership, or a private company, if the acquisition serves a public purpose.  The third major change the Bill seeks to make is that it changes the term ‘private company’ to ‘private entity’.  This implies that land may now be acquired for a proprietorship, partnership, corporation, non-profit organisation, or other entity, in addition to a private company, if the project serves a public purpose. Offences by the government: Fourthly, under the 2013 Act, if an offence is committed by a government department, the head of the department will be held guilty unless he can show that he had exercised due diligence to prevent the commission of the offence.  The Bill removes this section.  It adds a provision to state that if an offence is committed by a government employee, he can be prosecuted only with the prior sanction of the government. Acquisition of land for private hospitals and educational institutions: While the 2013 Act excluded acquisition of land for private hospitals and private educational institutions, the Bill sought to include these two within its scope.  However, the Lok Sabha removed this provision of the Bill.  Thus, in its present form, the Bill does not include the acquisition of land for private hospitals and private educational institutions. Other changes proposed in Lok Sabha: In addition to removing social infrastructure from one of the five exempted categories of projects, clarifying the definition of industrial corridors, and removing the provision related to acquisition for private hospitals and private educational institutions, the Lok Sabha made a few other changes to the Bill, prior to passing it.  These include: (i) employment must be provided to ‘one member of an affected family of farm labour’ as a part of the R&R award, in addition to the current provision which specifies that one member of an affected family must be provided employment as a part of R&R; (ii) hearings of the Land Acquisition, Rehabilitation and Resettlement Authority to address grievances related to compensation be held in the district where land is being acquired; and (iii) a survey of wasteland must be conducted and records of these land must be maintained. For more details on the 2015 Bill, see the PRS Bill page, here. A version of this blog appeared on rediff.com on February 27, 2015. 

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.