As of April 17, Madhya Pradesh has 1,120 confirmed cases of COVID-19 - the fifth-highest among all states in India. The Government of Madhya Pradesh issued one of its initial COVID-19 related orders around January 28, 2020, advising healthcare workers to use appropriate protective gear when examining patients from Wuhan, China. Since then, the government has taken several actions to contain the spread and impact of COVID-19. In this blog, we look at key measures taken so far.
Figure 1: Day-wise COVID-19 cases in Madhya Pradesh
Early stages: Focus on screening international travellers
On January 28, the state government issued directions to monitor international travellers from specified countries, test and maintain surveillance on those who are symptomatic. A further order required district administrators to monitor and report on all passengers who arrived from China between December 31, 2019 and January 29, 2020. While efforts were largely focused on screening and testing, the first quarantine restrictions for symptomatic travellers from China, entering India after January 15, were imposed on January 31. Those leaving quarantine were subsequently kept under surveillance and their health conditions reported on for a period of 14 days. By February 13, a constant presence of a medical team at the airport was required to test foreign passengers from an increasing list of countries and send daily reports.
February and early March: Improving public health capacity, restricting social gatherings
The next steps from the government were aimed towards adapting the public health infrastructure to handle the evolving situation. Following are some of the steps taken in this regard:
As the number of cases in India increased through March, the MP government turned focus and issued orders directly concerning their citizens. Several measures were undertaken to spread awareness about COVID-19 and implement social distancing.
March 21 Onwards
On March 21, MP reported four cases of COVID-19. On March 23, the government released the Madhya Pradesh Epidemic Diseases, COVID-19 Regulations 2020 to prevent the spread of COVID-19 in the state. These regulations specify special administrative powers and protocol for hospitals (government and private) to follow while treating COVID-19 patients. These regulations are valid for one year. Over and above general instructions to maintain social distancing and personal hygiene, the government has undertaken specific measures to: (i) increase healthcare capacity, (ii) institute welfare protection for the economically vulnerable population, (iii) strengthen the administrative structure and data collection, and (iv) ensure supply of essential goods and services. These measures include-
Healthcare measures
Welfare measures
Administrative measures
Supply of essential goods and services
For more information on the spread of COVID-19 and the central and state government response to the pandemic, please see here.
Over the last couple of weeks, MNREGA is back in the spotlight. The Union Minister for Rural Development wrote to certain states regarding potential misuse of funds, and it was announced that rural development schemes are open to CAG audit. In large schemes like MNREGA, officials at all levels of government - central, state, district, block, panchayat - have roles to play. This can make it difficult to locate the responsible authority in case implementation issues arise. We list the responsibilities of different government agencies involved in implementation of MNREGA in the Table below.
Stakeholder | Responsibilities | |
Gram Sabha | (a) recommending works; (b) conducting social audits on implementation every six months; and (c) functioning as a forum for sharing information. | |
Gram Panchayat | (a) planning works; (b) receiving applications for registration; (c) verifying applications; (d) registering households; (e) issuing job cards, (f) receiving applications for employment; (g) issuing detailed receipts; (h) allotting employment within 15 days of application; (i) executing works; (j) maintaining records; (k) convening Gram Sabha for social audit; and (l) monitoring implementation at the village level. | |
Intermediate Panchayat | (a) consolidating Gram Panchayat plans into a Block plan and (b) monitoring and supervision at the block level. | |
Programme Officer (PO) | (a) ensuring work to applicants within 15 days; (b) scrutinising Gram Panchayat annual development plans; (c) consolidating proposals into a Block plan and submitting to intermediate panchayat; (d) matching employment opportunities with demand for work at the Block level; (e) monitoring and supervising implementation; (f) disposing of complaints; (g) ensuring that Gram Sabha conducts social audits; and (h) payment of unemployment allowance. | |
District Panchayat | (a) finalizing district plans and labour budget; and (b) monitoring and supervising at district level. | |
District Programme Coordinator (DPC) | (a) ensuring that the scheme is implemented according to the Act at the district level; (b) information dissemination; (c) training; (d) consolidating block plans into a district plan; (e) ensuring that administrative and technical approval for projects are obtained on time; (f) release and utilisation of funds; (g) ensuring monitoring of works; (h) muster roll verifications; and (i) submitting monthly progress reports. | |
State Employment Guarantee Council (SEGC) | (a) advising the state government on implementation; (b) evaluate and monitor implementation; (c) determining the "preferred works" to be taken up; (d) recommending the proposal of works to be submitted to the state government; and (e) prepare an annual report to the state legislature. | |
State Government | (a) wide communication of the scheme; (b) setting up the SEGC; (c) setting up a State Employment Guarantee Fund; (d) ensuring that dedicated personnel are in place for implementation, including Gram Rozgar Sahayak, Programme Officer, and technical staff; (e) ensuring state share of the scheme budget is released on time; (f) delegation of financial and administrative powers to the DPC and Programme Officer if necessary; (g) training; (h) establishing a network of professional agencies for technical support and quality control; (i) regular review, monitoring, and evaluation of processes and outcomes; and (j) ensuring accountability and transparency. | |
Central Employment Guarantee Council | (a) advising the central government on MNREGA matters; (b) monitoring and evaluating implementation of the Act; and (c) preparing annual reports on implementation and submitting them to Parliament. | |
Ministry of Rural Development | (a) ensuring resource support to states and the CEGC; (b) regular review, monitoring, and evaluation of processes and outcomes; (c) maintaining and operating the MIS to capture and track data on critical aspects of implementation; (d) assessing the utilization of resources through a set of performance indicators; (e) supporting innovations that help in improving processes towards the achievement of the objectives of the Act; (f) support the use of Information Technology (IT) to increase the efficiency and transparency of the processes as well as improve interface with the public; and (g) ensuring that the implementation of NREGA at all levels is sought to be made transparent and accountable to the public.. | |
Source: Operational Guidelines, National Rural Employment Guarantee Scheme, Ministry of Rural Development. |