Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified when applications open.
In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA). This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.
I. MGNREGA: A brief introduction
A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households. Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development. Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.
B. Key features:
MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population. The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works. Table 1 provides information regarding employment generation and expenditure under MGNREGA.
Table 1: MGNREGA: Key indicators
Year |
Number of households provided employment (in crore) |
Average number of person days of work per household |
Total Expenditure (in lakh) |
2006-07 |
2.10 |
43 |
8823.35 |
2007-08 |
3.39 |
42 |
15856.88 |
2008-09 |
4.51 |
48 |
27250.10 |
2009-10 |
5.25 |
54 |
37905.23 |
2010-11 |
5.49 |
47 |
39377.27 |
2011-12* |
4.99 |
43 |
38034.69 |
2012-13** |
4.25 |
36 |
28073.51 |
Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013
II. Findings and Recommendations of the Standing Committee on Rural Development
A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:
B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include
Table 2: Work completion rate
Year |
Work completion rate (%) |
2006-07 |
46.34 |
2007-08 |
45.99 |
2008-09 |
43.76 |
2009-10 |
48.94 |
2010-11 |
50.86 |
2011-12* |
20.25 |
2012-13* |
15.02 |
Total | 33.22 |
Source: Standing Committee on Rural Development. Note: * As on 30.01.2013
C. Recommendations: The Committee made the following recommendations, based on its findings:
Reports suggest that a debt restructuring plan is being prepared for power distribution companies (discoms) in seven states - Uttar Pradesh, Punjab, Rajasthan, Haryana, Andhra Pradesh, Tamil Nadu and Madhya Pradesh. According to some estimates, the combined outstanding debt for discoms is Rs 2 lakh crore. Discoms have been facing heavy losses. According to a Planning Commission Report, the cost of supplying electricity increased at a rate of 7.4 per cent annually between 1998-99 and 2009-10. The average tariff has also increased at an annual rate of 7.1 per cent over the same period. However, the report shows that the average tariff per unit of electricity has consistently been much lower than average cost of supply per unit. Between 2007-08 and 2011-12, the gap between average cost and average tariff per unit of electricity was between 20 and 30 per cent of costs.
Average cost and average tariff per unit of electricity (Rs per kWh)
Year |
Unit cost |
Average tariff per unit |
Gap between cost and tariff |
Gap as percentage of unit cost |
2007-08 |
4.04 |
3.06 |
0.98 |
24% |
2008-09 |
4.6 |
3.26 |
1.34 |
29% |
2009-10 |
4.76 |
3.33 |
1.43 |
30% |
2010-11 |
4.84 |
3.57 |
1.27 |
26% |
2011-12 |
4.87 |
3.8 |
1.07 |
22% |
Source: “Annual Report 2011-12 on the Working of State Power Utilities and Electricity Departments”, Planning Commission State discoms have been losing money due to higher costs than revenues, as well as high transmission and distribution (T&D) losses. The commercial losses for discoms in India (after including subsidies) increased from Rs 16,666 crore in 2007-08 to Rs 37,836 crore in 2011-12. Reports suggest that the restructuring plan being prepared will be worth Rs 1.2 lakh crore in short-term liabilities. Half of the proposed amount would be issued as bonds by the discoms, backed by a state government guarantee. Banks and financial institutions would reschedule the remaining Rs 60,000 crore of debt, with a moratorium of three years on payment of the principal amount. State governments that adopt the financial restructuring plan would not recover any loans given to discoms before they start showing profits. Under a proposed transition finance mechanism, the central government would reimburse 25 per cent of the principal amount of bonds to states that fully implement the plan. Also, states that achieve a reduction in T&D losses above a targeted level in three years may be given grants. Newspaper reports also suggest that states will have to prepare plans for eliminating the gap between the average cost and average tariff per unit of electricity.