The Lok Sabha has passed the bill to revise the salary of members of parliament. Much of the debate in the media has been on the wealth of current MPs and the lack of accountability. It is important to focus as well on structural issues related to remunerating legislators. Under the bill, the base salary of MPs is being raised to Rs.50,000 from Rs.16,000 per month. The daily allowance paid to MPs when they attend parliament is being hiked to Rs.2,000 from Rs.1,000. The constituency allowance is being increased to Rs.45,000 per month from Rs.20,000 and office expenses (for staff, stationery and postage) to Rs.45,000 per month from Rs.20,000. Pension for former MPs will be Rs.20,000 per month instead of the present Rs.8,000. Other than these, MPs get accommodation in Delhi, which varies from a hostel in Vitthalbhai Patel House to two-bedroom flats and bungalows, all in central Delhi. MPs get reimbursement of electricity, water, telephone and internet charges. They (and their family) are also reimbursed for 34 one-way air tickets from their constituency to Delhi. In a parliamentary democracy, compensation for legislators should be sufficient to ensure their independence and autonomy. It should attract professionals who can devote their full time to legislative work. There should be a sufficient support system to enable legislators perform their duties effectively. There are mainly three issues that need to be resolved while fixing the compensation package for legislators. First, MPs fix their own salaries and allowances, which results in a conflict of interest. Second, every time the salary is revised upwards, there is an adverse media and public reaction. The outcome is that MPs' salaries are significantly lower than that for any other position of similar responsibility in the public or private sector. The low salaries may deter honest persons, without other income sources, from contesting elections. Third, reimbursements of office expenses are classified as 'allowances'. Thus, expenses for office staff, telephone charges, etc. are often seen as part of their compensation. Contrast this with the treatment for government or private sector employees. The costs of office support staff, rental, communication and travel costs are not counted as their salary or perks. The process in India is similar to that in some countries. The US Congress and the German Bundestag determine their own salaries. There are two alternative approaches seen in some other democracies. Some countries appoint an independent authority to determine salaries. Some others peg the salary to that of public officials. For example, New Zealand has a remuneration tribunal which is tasked to fix salaries based on being (a) fair relative to levels of remuneration elsewhere; (b) fair to person being remunerated and the taxpayer; (c) adequate to recruit and retain competent persons. In Canada, a commission is appointed after every general election and salaries are then indexed to the federal government's annual wage rate index. Australia has a remuneration authority that links the salary to that in the Principal Executive Office. In the UK, the Senior Salaries Review Board determines salaries, which are then voted upon by parliament. The Scottish parliament indexes its salaries to that of British MPs. In France, the salary of the legislator is the average of the highest and lowest paid official in the seniormost level of the government. There were two distinct themes during last week's Lok Sabha debate. Several MPs discussed structural issues. Some MPs - L.K. Advani, Ramachandra Dome, Sanjay Nirupam, Shailendra Singh and Pinaki Misra - suggested that the government establish an independent commission for determining salaries. Advani pointed out that a decision to that effect had been taken in an all-party meeting held by the Speaker in may 2005 and demanded that the government announce the formation of such a commission before the end of the current session of parliament. Some MPs - Dhananjay Singh, Sanjay Nirupam and Shailendra Kumar -- focussed on the need for support structures such as office space, research staff and assistants in the constituency. They felt that these would help MPs examine proposed laws and rules and monitor the work of the government. Nirupam and Misra suggested that MPs' salaries be linked to performance; salaries should be cut for any time lost due to disruption. Some MPs highlighted the need for pension and accommodation for former MPs. Sharad Yadav, Raghuvansh Prasad Singh and Sansuma Khunggur Bwiswmuthiary requested that the pension be raised to Rs 25,000 per month. Yadav and Bwiswmuthiary also said that former MPs be allocated residential accommodation in Delhi. The bill will next be discussed in the Rajya Sabha. The government agreed that there is merit in forming an independent commission. It is however uncertain whether the government will accede to Advani's demand that the commission be announced in the next couple of days. - M.R. Madhavan This column has been published by IANS today.

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.