There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

Recently the Chairman of Rajya Sabha issued a direction to extend the sitting hours and change the timing of Question Hour in the Upper House. Beginning with the Winter Session, which starts on November 24, Rajya Sabha will meet from 11 am to 6 pm, an hour more than its typical sitting hours. Question Hour will be scheduled from 12 pm to 1 pm, which was earlier held in the first hour of meeting. Members of Parliament (MPs), in addition to their legislative capacity, play an important role to keep the government accountable. One mechanism for them to hold the government responsible for its policies and actions is Question Hour in Parliament. During Question Hour, MPs raise questions to Ministers on various policy matters and decisions. Currently, all MPs can submit up to ten questions for every day that Parliament is in Session. Of these, 250 Questions are picked up by a random ballot to be answered each day that Parliament meets. While 230 Questions are answered in writing by Ministries, 20 Questions are scheduled to be answered orally by Ministers on the floor of the House. When a Question is answered orally by a Minister, MPs are also able to ask him/her two Supplementary Questions as a follow up to the response given. Therefore the proper functioning of Question Hour allows Parliament to be effective in its accountability function. Over the years Question Hour has become a major casualty to disruptions in Parliament. The last decade has seen a decline in the number of questions answered orally on the floor of the House. Rajya Sabha had tried to address this problem in 2011, when Question Hour was shifted to be held from 2 pm to 3 pm, but this was discontinued within a few days. Percentage of Questions Answered Orally The 2014 Budget Session saw both Houses of Parliament work for over hundred percent of their scheduled sitting time. However, while Question Hour functioned for 87% of its scheduled time in Lok Sabha, it functioned for only 40% of its scheduled time in Rajya Sabha. In 13 of the 27 sittings of the 2014 Budget Session, Question Hour in Rajya Sabha was adjourned within a few minutes due to disruptions. It was as a result of these increasing disruptions in the Upper House that the change in timing of the Question Hour and extension of its hours of sitting were proposed. While the Rules of Procedures of Rajya Sabha designate the first hour of sitting for Question Hour, they also allow the Chairman of the House to direct otherwise. It is using this Rule that the Chairman of Rajya Sabha, Mr. Hamid Ansari, issued directions for the Question Hour to be shifted to noon. It now remains to be seen whether this change in timing of Question Hour in the Upper House will be sufficient to allow for its smoother functioning. Sources: M.N. Kaul and S.L. Shakdher, Practice and Procedure of Parliament, Lok Sabha Secretariat, 6th Edition, 2009 Rajya Sabha Rules of Procedure, Rajya Sabha Secretariat, 2010