There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

The Comptroller and Auditor General (CAG) released a Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production, on August 17, 2012.  Some of the main findings and recommendations of the report are highlighted below:

  • There were no criteria for allocating coal blocks for captive mining till 1993.  The process of bringing in transparency and objectivity began in January 2004.  However, the process has experienced delays and had yet to materialise as of February 2012.
  • In the intervening period, 194 coal blocks with geological reserves of 44,440 million tonnes were allocated to private and government parties until March 31, 2011.  The report finds that the benefit to private allottees has been estimated at Rs 1.86 lakh crore for Opencast mines.  The report states that the government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The rate of increase in production of coal by Coal India Limited (CIL) during the 11th Plan period remained below the target set by the Planning Commission.  Capacity addition projects were delayed due to the lack of coordination of government agencies involved in statutory clearances and land acquisition.  There were mismatches in excavation and transportation capacities of mines, and suboptimal use of Heavy Earth Moving Machinery.
  • The CAG recommends that Ministry of Coal (MOC) should work out modalities to implement the procedure of allocation of coal blocks for captive mining through competitive bidding.
  • The CAG recommends that the MOC should constitute an empowered group along the lines of Foreign Investment Promotion Board as a single window mechanism for granting clearances, with representatives from central nodal ministries and state governments.

A one-page summary of the main findings and recommendations can be accessed here.  The full report can be accessed on the CAG website.