There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.