There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,

The general discussion on the Railway Budget concluded in Parliament this week. During the discussion, several MPs made a reference to two important documents tabled by the Railway Minister in 2009 - the ‘White Paper' on Indian Railways and the 2020 Vision document. The documents provide good insight into the operational and financial performance of Railways over the previous five years. They also throw light on the challenges that confront the Railways today. It emerges that Railways has relied heavily on increasing utilization of existing assets to manage the increase in demand. The system is otherwise severely constrained by lack of adequate capacity. Scenario so far (2004-09) Growth in traffic and earnings Rail transport demand is linked to the growth in GDP. As a result, the two main businesses of Railways – Passenger and Freight – have both seen significant increases in traffic in recent years. Passenger traffic has grown at an average rate of 10% each year. Earnings have increased at a slightly higher pace, implying that most passengers have been spared increases in fare. Standalone, passenger operations have continued to be loss making. Freight traffic has grown too, but at a lower rate of about 7% and unlike the passenger segment, freight fares have increased significantly over these years. Freight forms the backbone of Railways' revenues. Even today, it continues to account for almost two-thirds of total earnings. However, Railways’ market share in freight has decreased steadily over the past few decades - it dropped from 90% in 1950-51 to less than 30% in 2007-08. The main reasons for this decline are high pricing (to subsidize passenger travel) and lack of sufficient infrastructure. Railways are unable to provide time-tabled freight services. In addition, there are no multi-modal logistics parks that could have provided door-to-door cargo services. Infrastructure constraints Since 1950-51, route-kms have increased by just 18% and track-kms by 41%, even though freight and passenger output has gone up almost 12 times. Specific issues include:

  • Common corridor for both freight and passenger traffic - With freight trains on the same corridor, operating fast passenger trains becomes extremely difficult.
  • Concentration of traffic - More than half the total traffic moves on the golden quadrilateral and its diagonals; large parts of these sections are now already saturated.
  • Limited capacity for production of rolling stock, particularly locomotives and EMUs.

The above constraints require investment in network and capacity augmentation, including dedicated freight corridors. Hence, a substantial increase in funding is necessary. The Vision 2020 document planned to deploy Rs 14 lakh crore in the next 10 years towards development of rail infrastructure. Recent trends (as presented in the Budget 2011) This year's budget presented the actual financial performance in 2009-10, the provisional performance in 2010-11 and the targets for 2011-12 (Details can be accessed here). It also highlighted achievements on other metrics, including growth in traffic and augmentation of infrastructure (See 'Status of some key projects proposed in 2010-11'). On financials, 2009-10 was a bad year for Railways. Figures show a high Operating Ratio of 95.3%. Operating Ratio is a metric that compares operating expenses to revenues. A higher ratio indicates lower ability to generate surplus. The 2009-10 Operating Ratio is the highest since 2002. According to the Railways Minister, this can be partly attributed to higher payout in salaries and pension due to implementation of Sixth Pay Commission recommendations. Growth in passenger traffic remained high in 2010-11, at 11%. However, growth in freight traffic slowed down to 2%. Again, passenger fares remained untouched, but freight fares were increased. Railways, in 2011-12, targets an increase of 8% in both passenger and freight traffic. Financials are expected to improve. An amount of Rs. 57,630 crore has been budgeted as net plan outlay for investment in infrastructure. Last year, this figure was Rs 41,426 crore. In her opening remarks during the Budget speech in Parliament, the Minister commented that Railways forms an important backbone of any country. Lets hope it is headed in the right direction!