There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.

In Budget Session 2018, Rajya Sabha has planned to examine the working of four ministries.  The Ministry of Drinking Water and Sanitation is one of the ministries listed for discussion.  In this post, we look at the key schemes being implemented by the Ministry and their status.

What are the key functions of the Ministry of Drinking Water and Sanitation?

As per the Constitution, supply of water and sanitation are state subjects which means that states regulate and provide these services.  The Ministry of Drinking Water and Sanitation is primarily responsible for policy planning, funding, and coordination of programs for: (i) safe drinking water; and (ii) sanitation, in rural areas.  From 1999 till 2011, the Ministry operated as a Department under the Ministry of Rural Development.  In 2011, the Department was made an independent Ministry.  Presently, the Ministry oversees the implementation of two key schemes of the government: (i) Swachh Bharat Mission-Gramin (SBM-G), and (ii) National Rural Drinking Water Programme (NRDWP).

How have the finances and spending priorities of the Ministry changed over time?

In the Union Budget 2018-19, the Ministry has been allocated Rs 22,357 crore.  This is a decrease of Rs 1,654 crore (7%) over the revised expenditure of 2017-18.  In 2015-16, the Ministry over-shot its budget by 178%.  Consequently, the allocation in 2016-17 was more than doubled (124%) to Rs 14,009 crore.

In recent years, the priorities of the Ministry have seen a shift (see Figure 1).  The focus has been on providing sanitation facilities in rural areas, mobilising behavioural change to increase usage of toilets, and consequently eliminating open defecation.  However, this has translated into a decrease in the share of allocation towards drinking water (from 87% in 2009-10 to 31% in 2018-19).  In the same period, the share of allocation to rural sanitation has increased from 13% to 69%.Figure 1

What has been the progress under Swacch Bharat Mission- Gramin?

The Swachh Bharat Mission was launched on October 2, 2014 with an aim to achieve universal sanitation coverage, improve cleanliness, and eliminate open defecation in the country by October 2, 2019.

Expenditure on SBM-G:  In 2018-19, Rs 15,343 crore has been allocated towards SBM-G.  The central government allocation to SBM-G for the five year period from 2014-15 to 2018-19 has been estimated to be Rs 1,00,447 crore.  Of this, up to 2018-19, Rs 52,166 crore (52%) has been allocated to the scheme.  This implies that 48% of the funds are still left to be released before October 2019.  Figure 2

Construction of Individual Household Latrines (IHHLs):  For construction of IHHLs, funds are shared between the centre and states in the 60:40 ratio.  Construction of IHHLs account for the largest share of total expenditure under the scheme (97%-98%).  Although the number of toilets constructed each year has increased, the pace of annual growth of constructing these toilets has come down.  In 2015-16, the number of toilets constructed was 156% higher than the previous year.  This could be due to the fact that 2015-16 was the first full year of implementation of the scheme.  The growth in construction of new toilets reduced to 74% in 2016-17, and further to 4% in 2017-18.Table 1

As of February 2018, 78.8% of households in India had a toilet.  This implies that 15 crore toilets have been constructed so far.  However, four crore more toilets need to be construced in the next 20 months for the scheme to achieve its target by 2019.

Open Defecation Free (ODF) villages:  Under SBM-G, a village is ODF when: (i) there are no visible faeces in the village, and (ii) every household as well as public/community institution uses safe technology options for faecal disposal.  After a village declares itself ODF, states are required to carry out verification of the ODF status of such a village.  This includes access to a toilet facility and its usage, and safe disposal of faecal matter through septic tanks.  So far, out of all villages in the country, 72% have been verified as ODF.  This implies that 28% villages are left to be verified as ODF for the scheme to achieve its target by 2019.Table 2

Information, Education and Communication (IEC) activities:  As per the SBM-G guidelines, 8% of funds earmarked for SBM-G in a year should be utilised for IEC activities.  These activities primarily aim to mobilise behavioural change towards the use of toilets among people.  However, allocation towards this component has remained in the 1%-4% range.  In 2017-18, Rs 229 crore is expected to be spent, amounting to 2% of total expenditure.

What is the implementation status of the National Rural Drinking Water Programme?

The National Rural Drinking Water Programme (NRDWP) aims at assisting states in providing adequate and safe drinking water to the rural population in the country.  In 2018-19, the scheme has been allocated Rs 7,000 crore, accounting for 31% of the Ministry’s finances.Figure 3

Coverage under the scheme:  As of August 2017, 96% of rural habitations have access to safe drinking water.  In 2011, the Ministry came out with a strategic plan for the period 2011-22.  The plan identified certain standards for coverage of habitations with water supply, including targets for per day supply of drinking water.  As of February 2018, 74% habitations are fully covered (receiving 55 litres per capita per day), and 22% habitations are partially covered (receiving less than 55 litres per capita per day).  The Ministry aims to cover 90% rural households with piped water supply and 80% rural households with tap connections by 2022.  The Estimates Committee of Parliament (2015) observed that piped water supply was available to only 47% of rural habitations, out of which only 15% had household tap connections.

Contamination of drinking water:  It has been noted that NRDWP is over-dependant on ground water.  However, ground water is contaminated in over 20 states.  For instance, high arsenic contamination has been found in 68 districts of 10 states.  These states are Haryana, Punjab, Uttar Pradesh, Bihar, Jharkhand, Chhattisgarh, West Bengal, Assam, Manipur, and Karnataka.Table 3

Chemical contamination of ground water has also been reported due to deeper drilling for drinking water sources.  It has been recommended that out of the total funds for NRDWP, allocation for water quality monitoring and surveillance should not be less than 5%.  Presently, it is 3% of the total funds.  It has also been suggested that water quality laboratories for water testing should be set up throughout the country.