There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.

According to news reports, the Supreme Court stayed a Calcutta High Court judgement on the Singur Land Rehabilitation and Development Act, 2011 [Singur Act] on August 24, 2012. The apex court also issued a notice to Tata Motors seeking its response within four weeks, on the West Bengal government's petition challenging the High Court order. In 2008, the Left Front government acquired land in Singur under the Land Acquisition Act, 1894, for Tata Motors to build a Nano car factory.  In its first year of coming to power in West Bengal, the Trinamool Congress (TMC) led government notified the Singur Act through which it sought to reclaim this land to return a portion of it to farmers. On June 22, 2012, a Division bench of the Calcutta High Court struck down the Singur Act terming it unconstitutional and void.  In its judgment, the Court found some sections of the Singur Act to be in conflict with the central Land Acquisition Act, 1894.  As land acquisition is a Concurrent List subject under the Constitution, both Parliament and state legislatures have the power to make laws on it.  However, if provisions in the state law conflict with provisions in the central law, then the state law cannot prevail unless it receives Presidential assent.  The Calcutta High Court held the Singur Act to be unconstitutional because: (a) it was in conflict with the central Land Acquisition Act, 1894, and (b) Presidential assent was not obtained for the Act to prevail in West Bengal. The central Act mentions that for the government to acquire land, it has to demonstrate: (1) that land is being acquired for a public purpose,[i] and (2) that the government will provide compensation to persons from whom land is being acquired.  Provisions in the Singur Act that relate to public purpose and compensation were found to be in conflict with the corresponding provisions in the central Act.  The Court was of the opinion that transfer of land to the farmers does not constitute ‘public purpose’ as defined in the central Act.  As argued by the Tata Motors’ counsel, return of land to unwilling owners is a ‘private purpose’ or in ‘particular interest of individuals’ rather than in the ‘general interest of the community’.  Second, clauses pertaining to compensation to Tata Motors for their investment in the Nano project were found to be vague.  The Singur Act only provides for the refund of the amount paid by Tata Motors and the vendors to the state government for leasing the land.  It does not provide for the payment of any other amount of money for acquiring the Tata Motors’ land nor the principles for the determination of such an amount.  The High Court ordered that these provisions tantamount to ‘no compensation’ and struck down the related provisions. The matter will come up for consideration in the Supreme Court next on October 15, 2012.


[i] According to Section 3 of the Land Acquisition Act, 1894, acquisition of land for ‘public purpose’ includes, among others: provision or planned development of village sites; provision of land for town or rural planning; the provision of land for planned development of land from public funds in pursuance of a scheme or policy of the Government; and the provision of land for a corporation owned or controlled by the State.