There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.

A Committee has been set up to examine appropriateness of procedures followed by the Department of Telecommunications in issuance of licences and allocation of spectrum during the period 2001-2009.  The Committee will be chaired by retired Judge of the Supreme Court, Justice (Retd.) Shri Shivraj V. Patil.  According to news reports the Committee is scheduled to submit its report by the first week of January 2011.  The Terms of Reference (TOR) of the Committee have been listed as: 1. To study the circumstances and developments in the Telecom sector that led to the formulation of the New Telecom Policy 1999 and subsequently, introduction of 4th Cellular Telecom Mobile Service (CMTS) licence in 2001. 2. To examine the internal (intra-departmental) procedures adopted by DoT during the period 2001-2009 for: a. Issue of telecom access service licences, and b. Allocation of spectrum to all telecom access services licencees during the above period. 3. To examine whether these procedures were in accordance with existing policies and directions of DoT/Government. 4. To examine whether these procedures were followed consistently and if not, identify specific instances of: a. Deviation from laid down procedures; b. Inappropriate application of laid down procedures; c. Violation of underlying principles of laid down procedures. 5. To examine whether the procedures adopted were fair and transparent and were in keeping with the principles of natural justice and if not, identify the specific instances of lack of fairness and transparency. 6. To identify the deficiencies, if any, in the procedures as formulated and identify the public officials responsible for such deficiencies. 7. To identify the shortcomings and lapses, if any, in the implementation of the laid down procedures and identify the public officials responsible for such lapses. 8. To suggest remedial measures to avoid in future: a. Deficiencies in formulation of procedures; and b. Lapses in implementation of laid-down procedures.