There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.

By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:

  • Mobility (including purchase of bullet proof and mine proof vehicles)
  • Weaponry
  • Communication Systems
  • Training
  • Forensic Science Laboratory/ Finger Printing Bureau
  • Equipments
  • Buildings

Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the MHA were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan.

c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower.

Weapons

§ Police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006.

c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower.

Weapons

§ It was observed that the police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.