There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.

The Lok Sabha  adjourns today for a three-week recess.  The Rajya Sabha is scheduled to adjourned on March 18.  Here’s a brief look at the activity of Parliament this session (data till March 15): Productive Hours: The session has witnessed more than its fair share of disruptions.  In the 14 sitting days, over 22 hours has been lost to interruptions in the Lok Sabha and over 26 hours in the Rajya Sabha.  The number of productive hours so far is 53 and 50 hours in the Lok Sabha and Rajya Sabha respectively. [Click here to compare with previous sessions.] The session began with protests by the Opposition, putting pressure on the Government to schedule a debate on price rise.  After the presentation of the Budget, the protests revolved around the petroleum price hike.  The disruptions in the Rajya Sabha were on account of the Women’s Reservation Bill, which resulted in the suspension of seven MPs. On March 9 the Rajya Sabha was adjourned five times, before the passage of the Bill. Legislative business: This session, the government had listed 63 Bills for introduction, 16 pending Bills for consideration and passing and 10 pending Bills for consideration and passing if their Standing Committee reports are submitted. Other than financial business transacted, which includes passage of Demand for Grants and Appropriation Bills, the only legislation that has been passed so far is the Women’s Reservation Bill in the Rajya Sabha. The Lok Sabha also has passed one Bill that replaces an Ordinance - the Ancient Monuments and Archaeological Sites and Remains Bill. In the 14 sitting days, the House has spent 6 hours on legislative business. Question Hour: Another important aspect of parliamentary business is the Question Hour.  Interestingly, the Lok Sabha rules were amended before the start of this session to ensure that the absence of MPs does not result in the collapse of Question Hour.  However, the amount of time spent on questions in both Houses this session has remained under 5 hours.