Reports suggest that the first reactor of the Kudankulam power plant is close to operational. With state discoms struggling, advocates of nuclear power see Kudankulam as a necessary boost to India’s struggling power sector.  The Kudankulam power plant will have two reactors.  At full capacity, the plant would produce 2 GW of energy, making it India’s largest nuclear plant, and significantly increasing India’s nuclear capacity (currently at 4.8 GW or 2.3% of  total capacity). Internationally, nuclear power plants contributed 12.3 % of the world's electricity production in 2011.  In terms of number of nuclear reactors, India ranks 6th in the world with 20 nuclear reactors (in seven power stations across five states: Rajasthan, Uttar Pradesh, Gujarat, Karnataka and Tamil Nadu).  The Kudankulam power station would be Tamil Nadu’s second power station after the Madras Atomic Power Station (MAPS). Tamil Nadu is struggling to meet electricity demand, recently moved the Supreme Court, asking the Centre for more power. Peak demand deficit (the difference between electricity supply and demand at peak periods) in the state was 17.5% in 2011-12.  The per capita consumption of electricity in the state was 1,132 kWh in 2009-10, significantly greater than the India average of 779 kWh.  Currently, electricity in Tamil Nadu is fueled by a mixture of coal (35% of capacity), renewable sources (42%) and hydro sources (12%).  A fully operational Kudankulam reactor would boost Tamil Nadu’s capacity by 6% (including state, private and centrally owned generating entities). The interactive table below provides a state-level breakdown of key power sector indicators.  To view data in ascending or descending order, simply click the relevant column heading.  (For a detailed overview of the power sector and even more state-wise statistics, see here.) [table id=4 /]   Source: Central Electricity Authority; Planning Commission; PRS. Note: capacity for states includes allocated shares in joint and central sector utilities. T&D (transmission and distribution) losses refer to losses in electricity in the process of delivery  

The Comptroller and Auditor General (CAG) released a Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production, on August 17, 2012.  Some of the main findings and recommendations of the report are highlighted below:

  • There were no criteria for allocating coal blocks for captive mining till 1993.  The process of bringing in transparency and objectivity began in January 2004.  However, the process has experienced delays and had yet to materialise as of February 2012.
  • In the intervening period, 194 coal blocks with geological reserves of 44,440 million tonnes were allocated to private and government parties until March 31, 2011.  The report finds that the benefit to private allottees has been estimated at Rs 1.86 lakh crore for Opencast mines.  The report states that the government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The rate of increase in production of coal by Coal India Limited (CIL) during the 11th Plan period remained below the target set by the Planning Commission.  Capacity addition projects were delayed due to the lack of coordination of government agencies involved in statutory clearances and land acquisition.  There were mismatches in excavation and transportation capacities of mines, and suboptimal use of Heavy Earth Moving Machinery.
  • The CAG recommends that Ministry of Coal (MOC) should work out modalities to implement the procedure of allocation of coal blocks for captive mining through competitive bidding.
  • The CAG recommends that the MOC should constitute an empowered group along the lines of Foreign Investment Promotion Board as a single window mechanism for granting clearances, with representatives from central nodal ministries and state governments.

A one-page summary of the main findings and recommendations can be accessed here.  The full report can be accessed on the CAG website.