Latest in the string of litigations filed after the enactment of the Right of Children to Free and Compulsory Education Act, 2009 (RTE Act), the Delhi High Court ruled that the Act shall not apply to nursery admissions in unaided private schools for the unreserved category of students.  The decision, given on February 19, was in response to writ petitions filed by Social Jurist, a civil rights group and the Delhi Commission for the Protection of Child Rights.  It contended that the guidelines of the Ministry of Human Resource Development related to schools’ selection procedure should also be applicable to pre-primary and pre-school classes. The right to education is applicable to children between the age of 6 and 14 years.  The RTE Act states that schools have to reserve certain proportion of their seats for disadvantaged groups.  It adds that where the school admits children at pre-primary level, the reservation for children of weaker sections shall apply.  However, it does not mention whether other RTE norms are applicable to pre-schools.  It only states that the appropriate government may make necessary arrangements for providing pre-school education to children between the age of 3 and 6 years. Guidelines of the Ministry with regard to selection procedure of students:

  • Criteria of admission for 25% seats reserved for disadvantaged groups: For Class 1 or pre-primary class, unaided schools shall follow a system of random selection out of the applications received from children belonging to disadvantaged groups.
  • Criteria of admission for rest of the seats: Each unaided school should formulate a policy of admission on a rational, reasonable and just basis.  No profiling shall be allowed based on parental educational qualifications.  Also, there can be no testing or interviews for any child or parent.

The two issues that the court considered were: (a) whether RTE applies to pre-schools including nursery schools and for education of children below six years of age; (b) whether RTE applies to the admission of children in pre-schools in respect of the unreserved seats (25% of seats are reserved for children belonging to disadvantaged groups). According to the verdict, the guidelines issued by the government do not apply to the unreserved category of students i.e. 75% of the admission made in pre-schools in private unaided schools.  This implies that private unaided schools may formulate their own policies regarding admission in pre-schools for the unreserved category of students.  However, they apply to the reserved category of students i.e. 25% of the admission s made in these schools for disadvantaged groups. The court has however stated that in its view this is the right time for the government to consider the applicability of RTE Act to the nursery classes too.  In most schools, students are admitted from nursery and they continue in the same school thereafter.  Therefore, the RTE Act’s prohibition of screening at the time of selection is rendered meaningless if it is not applicable at the nursery level.

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.