The Financial Resolution and Deposit Insurance Bill, 2017 was introduced in Lok Sabha during Monsoon Session 2017.  The Bill is currently being examined by a Joint Committee of the two Houses of Parliament.  It seeks to establish a Resolution Corporation which will monitor the risk faced by financial firms such as banks and insurance companies, and resolve them in case of failure.  For FAQs explaining the regulatory framework under the Bill, please see here.

Over the last few days, there has been some discussion around provisions of the Bill which allow for cancellation or writing down of liabilities of a financial firm (known as bail-in).[1],[2]  There are concerns that these provisions may put depositors in an unfavourable position in case a bank fails. In this context, we explain the bail-in process below.

What is bail-in?

The Bill specifies various tools to resolve a failing financial firm which include transferring its assets and liabilities, merging it with another firm, or liquidating it.  One of these methods allows for a financial firm on the verge of failure to be rescued by internally restructuring its debt.  This method is known as bail-in.

Bail-in differs from a bail-out which involves funds being infused by external sources to resolve a firm.  This includes a failing firm being rescued by the government.

How does it work?

Under bail-in, the Resolution Corporation can internally restructure the firm’s debt by: (i) cancelling liabilities that the firm owes to its creditors, or (ii) converting its liabilities into any other instrument (e.g., converting debt into equity), among others.[3]

Bail-in may be used in cases where it is necessary to continue the services of the firm, but the option of selling it is not feasible.[4]  This method allows for losses to be absorbed and consequently enables the firm to carry on business for a reasonable time period while maintaining market confidence.3  The Bill allows the Resolution Corporation to either resolve a firm by only using bail-in, or use bail-in as part of a larger resolution scheme in combination with other resolution methods like a merger or acquisition.

Do the current laws in India allow for bail-in? What happens to bank deposits in case of failure?

Current laws governing resolution of financial firms do not contain provisions for a bail in.  If a bank fails, it may either be merged with another bank or liquidated.

In case of bank deposits, amounts up to one lakh rupees are insured by the Deposit Insurance and Credit Guarantee Corporation (DICGC).  In the absence of the bank having sufficient resources to repay deposits above this amount, depositors will lose their money.  The DICGC Act, 1961 originally insured deposits up to Rs 1,500 and permitted the DICGC to increase this amount with the approval of the central government.  The current insured amount of one lakh rupees was fixed in May 1993.[5]  The Bill has a similar provision which allows the Resolution Corporation to set the insured amount in consultation with the RBI.

Does the Bill specify safeguards for creditors, including depositors?

The Bill specifies that the power of the Corporation while using bail-in to resolve a firm will be limited.  There are certain safeguards which seek to protect creditors and ensure continuity of critical functions of the firm. Order of priority under liquidation

When resolving a firm through bail-in, the Corporation will have to ensure that none of the creditors (including bank depositors) receive less than what they would have been entitled to receive if the firm was to be liquidated.[6],[7]

Further, the Bill allows a liability to be cancelled or converted under bail-in only if the creditor has given his consent to do so in the contract governing such debt.  The terms and conditions of bank deposits will determine whether the bail-in clause can be applied to them.

Do other countries contain similar provisions?

After the global financial crisis in 2008, several countries such as the US and those across Europe developed specialised resolution capabilities.  This was aimed at preventing another crisis and sought to strengthen mechanisms for monitoring and resolving sick financial firms.

The Financial Stability Board, an international body comprising G20 countries (including India), recommended that countries should allow resolution of firms by bail-in under their jurisdiction.  The European Union also issued a directive proposing a structure for member countries to follow while framing their respective resolution laws.  This directive suggested that countries should include bail-in among their resolution tools.  Countries such as UK and Germany have provided for bail-in under their laws.  However, this method has rarely been used.7,[8]  One of the rare instances was in 2013, when bail-in was used to resolve a bank in Cyprus.

———————————————–

[1] ‘Modi government’s FRDI bill may take away all your hard-earned money’, India Today, December  5, 2017, http://indiatoday.intoday.in/story/frdi-bill-banking-reforms-modi-government-india-parliament/1/1103422.html.

[2] ‘Bail-in doubts — on financial resolution legislation’, The Hindu, December 5, 2017, http://www.thehindu.com/opinion/editorial/bail-in-doubts/article21261606.ece.

[3] Section 52, The Financial Resolution and Deposit Insurance Bill, 2017.

[4] Report of the Committee to Draft Code on Resolution of Financial Firms, September 2016, http://www.prsindia.org/uploads/media/Financial%20Resolution%20Bill,%202017/FRDI%20Bill%20Drafting%20Committee%20Report.pdf.

[5] The Deposit Insurance and Credit Guarantee Corporation Act, 1961, https://rbidocs.rbi.org.in/rdocs/Publications/PDFs/dicgc_act.pdf.  s

[6] Section 55, The Financial Resolution and Deposit Insurance Bill, 2017.

[7] The Bank of England’s approach to resolution, October 2014, Bank of England.

[8] Recovery and resolution, BaFin, Federal Financial Supervisory Authority of Germany, https://www.bafin.de/EN/Aufsicht/BankenFinanzdienstleister/Massnahmen/SanierungAbwicklung/sanierung_abwicklung_artikel_en.html.

In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.