The Insolvency and Bankruptcy Code, 2016 is listed for passage in Rajya Sabha today. Last week, Lok Sabha passed the Code with changes recommended by the Joint Parliamentary Committee that examined the Code.[1],[2] We present answers to some of the frequently asked questions in relation to the Insolvency and Bankruptcy Code, 2016. Why do we need a new law? As of 2015, insolvency resolution in India took 4.3 years on an average. This is higher when compared to other countries such as United Kingdom (1 year) and United States of America (1.5 years). Figure 1 provides a comparison of the time to resolve insolvency for various countries. These delays are caused due to time taken to resolve cases in courts, and confusion due to a lack of clarity about the current bankruptcy framework. What does the current Code aim to do? The 2016 Code applies to companies and individuals. It provides for a time-bound process to resolve insolvency. When a default in repayment occurs, creditors gain control over debtor’s assets and must take decisions to resolve insolvency within a 180-day period. To ensure an uninterrupted resolution process, the Code also provides immunity to debtors from resolution claims of creditors during this period. The Code also consolidates provisions of the current legislative framework to form a common forum for debtors and creditors of all classes to resolve insolvency. Who facilitates the insolvency resolution under the Code? The Code creates various institutions to facilitate resolution of insolvency. These are as follows:
What is the procedure to resolve insolvency in the Code? The Code proposes the following steps to resolve insolvency:
What are some issues in the Code that require consideration?
A version of this blog appeared in the Business Standard on May 7, 2016.
There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers. According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed. Originally around 50 power units were expected to sign FSAs with CIL. Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months. According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent. The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation. As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days. The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)
2009-10 |
2010-11 |
2011-12 |
|
Demand |
604 |
656 |
696 |
Supply |
514 |
523 |
535 |
Gap |
90 |
133 |
161 |
Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India. Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period. Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue. While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015. These power plants should also have entered into long term Power Purchase Agreements with distribution companies. After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs. The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL. They have argued that it differs from the 2009 version of FSAs in some major ways. These include:
Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA. Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format. CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production. Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.