Most legislative assemblies make Parliament look like a paragon of virtue A COUPLE of days ago, an MLA from Orissa made news for climbing on to the speaker's table in the assembly. Not so long ago, television screens beamed images of Karnataka MLAs snacking and sleeping all night in the assembly. But these are only indicative of the incidents of the raucous behaviour of several MLAs in the recent past across the country. And the poor behaviour of some MLAs is only one aspect of the pitiable state of several of our state legislatures. The other aspect of our state legislatures that goes largely unnoticed is how poorly the secretariats of legislatures are equipped and how several systems that are seen as essential in Parliament are nonexistent in states. Even to know the complete picture of how our legislatures function, you need data. And several state assemblies are notoriously poor at putting out data on the functioning of the institution or the MLAs. After one gets used to the quality of Parliament websites and the regularity of their updates, it would be shocking to see that there are some state legislatures that do not even have functional websites. It has been observed that some state legislatures are lagging behind by a couple of years in compiling the "resume of work" which summarises the work done in a session of the legislature. So the first bottleneck in several instances is the inability to access data of the assembly. From the data we have managed to access, it is obvious that state assemblies meet for very few days a year. A case in point is the Punjab assembly which has met for an average of 19 days per year for a 10-year period between 1997 and 2007. Delhi was only marginally better averaging 21 days per year during the same period. Kerala has averaged some 50 days a year for several years now. Some states like Karnataka have legislated that they should meet for at least 60 days a year, but since passing that legislation in 2005, they have not managed to do so for even one year. I am not even accounting for the time lost due to disruptions. Bills are passed with little or no discussion in many state legislatures. While in Parliament, referring bills to the standing committees is the norm, most state legislatures do not have standing committees. The only examination of a bill, if any, happens on the floor of the House. And if data from the Delhi assembly is anything to go by, the average debate on a bill before is passed is a little over half hour. There are any number of instances where bills are introduced and passed in state assemblies on the same day -so there is not even a pretence of the need for MLAs to read, understand and deliberate on the provisions of legislation they are supposedly passing. MLAs are often far more narrowly constituency-focused than MPs are. On average, MLAs have lower education levels than members of Parliament. There is no formal definition of a role of an MLA, and they mostly have no exposure to ideas such as the separation of powers between the executive and the legislature. In one particularly revealing conversation with an MLA, he said, "At the time of elections, each of the contestants represents his party. But after the elections, the chiefministerbecomestheleader of all MLAs in the House. If an MLAneedssomeadditionalprojects/ favours for his constituency he needs to be in the good books of the chief minister and his cabinet ministers. So where is the question of taking on the chief minister on the floor of the House on any issue?" There are many aspects of state legislatures that point to a steady and visible decline of these important institutions. But beyond the frequent highlighting of theatrics by some MLAs, there is almost no public discourse on this issue. It is necessary to ensure that the legislatures run smoothly, and the speaker, as first among equals, has the biggest responsibility to ensure this. If there are rules and everyone knows that those rules will never be used to enforce discipline, then the rules will be broken, and repeatedly so. This practice needs to be urgently reviewed. The larger question is whether our legislatures are the highest deliberating and policymaking bodies or whether they are being reduced to platforms for political theatrics. Policy can almost never be devoid of politics and public posturing. But if this means poor deliberation of critical policy issues and the woefully inadequate functioning of our legislatures, then we may need to come up with creative ways in which this problem can be addressed. This article appeared in the Indian Express on December 20, 2010.

There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.