There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers.  According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed.  Originally around 50 power units were expected to sign FSAs with CIL.  Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months.  According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent.  The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation.  As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days.  The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)

 

2009-10

2010-11

2011-12

Demand

604

656

696

Supply

514

523

535

Gap

90

133

161

Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India.  Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period.  Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue.  While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015.  These power plants should also have entered into long term Power Purchase Agreements with distribution companies.  After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs.  The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL.  They have argued that it differs from the 2009 version of FSAs in some major ways.  These include:

  • The penalty for supplying coal below 80 per cent of the contracted amount has been reduced from 10 per cent to 0.01 per cent.  The penalty will be applicable only after three years.
  • The new FSA has extensive force majeure provisions that absolve CIL of non-supply in case of multiple contingencies – including equipment breakdown, power cuts, obstruction in transport, riots, failure to import coal due to “global shortage or delays… or no response to enquiries (by CIL) for supply of coal.”
  • CIL would have the discretion to annually review the supply level that would trigger a financial penalty.  There was no provision for such a review in the earlier FSA.

Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA.  Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format.  CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production.  Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.

Recently the Chairman of Rajya Sabha issued a direction to extend the sitting hours and change the timing of Question Hour in the Upper House. Beginning with the Winter Session, which starts on November 24, Rajya Sabha will meet from 11 am to 6 pm, an hour more than its typical sitting hours. Question Hour will be scheduled from 12 pm to 1 pm, which was earlier held in the first hour of meeting. Members of Parliament (MPs), in addition to their legislative capacity, play an important role to keep the government accountable. One mechanism for them to hold the government responsible for its policies and actions is Question Hour in Parliament. During Question Hour, MPs raise questions to Ministers on various policy matters and decisions. Currently, all MPs can submit up to ten questions for every day that Parliament is in Session. Of these, 250 Questions are picked up by a random ballot to be answered each day that Parliament meets. While 230 Questions are answered in writing by Ministries, 20 Questions are scheduled to be answered orally by Ministers on the floor of the House. When a Question is answered orally by a Minister, MPs are also able to ask him/her two Supplementary Questions as a follow up to the response given. Therefore the proper functioning of Question Hour allows Parliament to be effective in its accountability function. Over the years Question Hour has become a major casualty to disruptions in Parliament. The last decade has seen a decline in the number of questions answered orally on the floor of the House. Rajya Sabha had tried to address this problem in 2011, when Question Hour was shifted to be held from 2 pm to 3 pm, but this was discontinued within a few days. Percentage of Questions Answered Orally The 2014 Budget Session saw both Houses of Parliament work for over hundred percent of their scheduled sitting time. However, while Question Hour functioned for 87% of its scheduled time in Lok Sabha, it functioned for only 40% of its scheduled time in Rajya Sabha. In 13 of the 27 sittings of the 2014 Budget Session, Question Hour in Rajya Sabha was adjourned within a few minutes due to disruptions. It was as a result of these increasing disruptions in the Upper House that the change in timing of the Question Hour and extension of its hours of sitting were proposed. While the Rules of Procedures of Rajya Sabha designate the first hour of sitting for Question Hour, they also allow the Chairman of the House to direct otherwise. It is using this Rule that the Chairman of Rajya Sabha, Mr. Hamid Ansari, issued directions for the Question Hour to be shifted to noon. It now remains to be seen whether this change in timing of Question Hour in the Upper House will be sufficient to allow for its smoother functioning. Sources: M.N. Kaul and S.L. Shakdher, Practice and Procedure of Parliament, Lok Sabha Secretariat, 6th Edition, 2009 Rajya Sabha Rules of Procedure, Rajya Sabha Secretariat, 2010