On March 14, 2022 Rajya Sabha discussed the working of the Ministry of Development of North Eastern Region (DoNER).  During the discussion, several issues around budgetary allocation, implementation of schemes and connectivity with the North Eastern Region were discussed.  The Ministry of DoNER is responsible for matters relating to the planning, execution and monitoring of development schemes and projects in the North Eastern Region.  In this blog post, we analyse the 2022-23 budgetary allocations for the Ministry and discuss related issues.  

A new scheme named PM-DevINE announced to boost infrastructure and social development

In 2022-23, the Ministry has seen a 5% increase in allocation from the revised estimates of 2021-22.  The Ministry has been allocated Rs 2,800 crore which will be used for various development schemes, such as the North East Special Infrastructure Development Scheme and North East Road Sector Development Scheme.  A scheme-wise break-up of the budget allocation for the Ministry is given below in Table 1.  

One of the key highlights of the Finance Minister’s Budget Speech was the announcement of a new scheme named the Prime Minister’s Development Initiative for North East (PM-DevINE).  It will be implemented through the North East Council (nodal agency for the economic and social development of the North Eastern Region).  PM-DevINE will fund infrastructure and social development projects in areas such as road connectivity, health, and agriculture.  The scheme will not replace or subsume existing central sector or centrally sponsored schemes.  The Scheme will be given an initial allocation of Rs 1,500 crore.

Table 1: Break-up of allocation to the Ministry of DoNER (in Rs crore)

Major Heads

2020-21 Actuals

2021-22 BE

2021-22 RE

2022-23 BE

% change from 2021-22 RE to 2022-23 BE

North East Special Infrastructure Development Scheme

446

675

674

1,419

111%

Schemes of North East Council

567

585

585

702

20%

North East Road Sector Development Scheme

416

696

674

496

-26%

Central pool of resources for North East and Sikkim

342

581

581

-

-

Others

270

322

344

241

-30%

Total

1,854

2,658

2,658

2,800

5%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: BE – Budget Estimate; RE – Revised Estimate; Schemes for North East Council includes Special Development Projects.

Sources: Demand No. 23 of Union Budget Documents 2022-23; PRS. 

Allocation towards capital outlay less than demand

The Standing Committee on Home Affairs (2022) noted that the amount allocated at the budget stage in 2022-23 (Rs 660 crore) was 17% less than the demand by the Ministry (Rs 794 crore).  Capital expenditure includes capital outlay which leads to the creation of assets such as schools, hospitals, and roads and bridges.  The Committee observed that this may severely affect the implementation of several projects and schemes that require capital outlay.  It recommended the Ministry to take up this matter with the Finance Ministry and demand additional assistance at the revised stage of the 2022-23 financial year.

Underutilisation of funds over the years

Since 2011-12 (barring 2016-17), the Ministry has not been able to utilise the funds allocated to it at the budgeted stage (See Figure 1).  For instance, in 2020-21, fund utilisation in case of the North East Road Sector Development Scheme was 52%, whereas only 34% of funds were utilised under the North East Special Infrastructure Development Scheme (for infrastructure projects relating to water supply, power, connectivity, social infrastructure).  Key reasons for underspending highlighted by the Ministry include late receipt of project proposals and non-receipt of utilisation certificates from state governments.

Figure 1: Underutilisation of funds by the Ministry since 2011-12

image
 Note: Revised Estimate has been used as the Actual Expenditure for 2021-22.
 Sources: Union Budget Documents (2011-12 to 2022-23); PRS
.

Delay in project completion

The Ministry implements several schemes for infrastructural projects such as roads and bridges.  The progress of the certain schemes has been inadequate.   The Standing Committee (2022) observed that the physical progress of many road sector projects under the North East Road Sector Development Scheme is either at zero or in single digit percent in spite of release of the amount for the project.  Similarly, projects under the Karbi Anglong Autonomous Territorial Council (autonomous district council in Assam) and Social and Infrastructure Development Fund (construction of roads, bridges, and construction of schools and water supply projects in the North Eastern Region) have seen inadequate progress.

Need to address declining forest cover

The Standing Committee (2021) has also recommended the Ministry of DoNER to work towards preserving forest cover.  The Committee took note of the declining forest cover in the North East India.  As per the India State of Forest Report (2021), states showing major loss of forest cover from 2019 to 2021 are: (i) Arunachal Pradesh (loss of 257 sq km of forest cover), (ii) Manipur (249 sq km), (iii) Nagaland (235 sq km), (iv) Mizoram (186 sq km), and (v) Meghalaya (73 sq km).  The loss of forest cover may be attributed to shifting cultivation, cutting down of trees, natural calamities, anthropogenic (environmental pollution) pressure, and developmental activities.  The Committee recommended that various measures to protect the forest and environment must be given priority and should implemented within the stipulated timeline.  It also suggested the Ministry to: (i) carry out regular plantation drives to increase forest cover/density, and (ii) accord priority towards the ultimate goal of preserving and protecting the forests under various centrally sponsored initiatives.

Key issues raised by Members during discussion in Rajya Sabha

The discussion on the working of the Ministry of DoNER took place in Rajya Sabha on March 14, 2022.  One of the issues highlighted by members was about the Ministry not having its own line Department.  This leads to the Ministry being dependent on the administrative strength of the states for implementation of projects.  Another issue highlighted by several members was the lack of connectivity of the region through railways and road networks which hampers the economic growth of region.  The DoNER Minister in his response to the House assured the members that the central government is making continuous efforts towards improving connectivity to the North East region through roads, railways, waterways, and telecommunication.         

Allocation by Union Ministries to the North East 

Union Ministries allocate 10% of their budget allocation for the North East (See Figure 2 for fund allocation and utilisation).  The Ministry of DoNER is the nodal Ministry that monitors and keeps track of the allocation done by various Ministries.  In 2022-23, Rs 76,040 crore has been allocated by all the Ministries for the North Eastern region.  The allocation has increased by 11% from the revised estimate of 2021-22 (Rs 68,440 crore).   In 2019-20 and 2021-21 the actual expenditure towards North Eastern areas was lower than budget estimates by 18% and 19% respectively.  

Figure 2: Budgetary allocation by all Union Ministries for the North East (amount in Rs crore)

image   

Source: Report No. 239: Demand for Grants (2022-23) of Ministry of Development of North Eastern Region, Standing Committee on Home Affairs; PRS.

With 4,203 confirmed cases of COVID-19, Maharashtra has the highest number of cases in the country as of April 20, 2020.  Of these, 507 have been cured, and 223 have died.  In this blog, we summarise some of the key decisions taken by the Government of Maharashtra for containing the spread of COVID-19 in the state. 

 image

Measures taken prior to lockdown

By March 12, the state had registered 11 cases of COVID-19. Consequently, the state government took measures to: (i) prepare hospitals for screening and testing of patients, and (ii) limit mass gathering given the highly contagious nature of the disease. The measures taken by the government before the lockdown are summarised below.

Health Measures

On March 14, the government notified the Maharashtra COVID-19 regulations to prevent and contain the spread of COVID-19 in the state.  Key features of the regulations include: (i) screening of COVID-19 patients in hospitals, (ii) home quarantine for people who have travelled through the affected areas, and (iii) procedures to be followed in the containment zones, among others. 

Movement Restrictions

On March 15, with 31 COVID-19 cases in the state, the Department of Public Health ordered the closure of cinema halls, swimming pools, gyms, theatres, and museums until March 31.   On March 16, all educational institutions and hostels in the state were closed till March 31.  The teaching staff was advised to work from home.  All exams were also deferred until March 31.

Administrative Measures

On March 13, the Maharashtra government constituted a high-level committee to formulate guidelines for mitigating of the spread of COVID-19 in the state.  The responsibilities of the committee included: (i) taking a daily review of the status of COVID-19 in the state, and (ii) implementing the guidelines issued by the World Health Organisation and the Ministry of Health.

On March 17, the first casualty due to COVID-19 occurred in the state.  On March 19, the government put restrictions on meetings in the government offices and issued safety guidelines to be followed in these meetings.

On March 20, considering the unmitigated spread of COVID-19 in Mumbai, Pune and Nagpur, the attendance in government offices was restricted to 25%. Subsequently, on March 23, the government limited the attendance in government offices to 5% across the state.

Measures taken post-lockdown

To further restrict the movement of individuals, in order to contain the spread of the disease, the state government enforced a state-wide lockdown on March 23. This lockdown, applicable till March 31, involved: (i) closing down of state borders, (ii) suspension of public transport services, and (iii) banning the congregation of more than five people at any public place. Entities engaged in the supply of essential goods and services were excluded from this lockdown.  This was followed by a nation-wide lockdown enforced by the central government between March 25 and April 14, now extended till May 3.  Before the extension announced by the central government, the state government extended the lockdown in the state till April 30.

On April 15, the Ministry of Home Affairs issued guidelines on the measures to be taken by state governments until May 3.  As per these guidelines, select activities will be permitted in less-affected districts from April 20 onwards to reduce the hardships faced by people.  Some of the permitted activities are (i) agriculture and related activities, (ii) MNERGA works, (iii) construction activities, (iv) industrial establishments, (v) health services, (vi) certain financial sector activities among others subject to certain conditions. 

Welfare Measures

To address the hardship being faced by residents of the state due to lockdown, the state took several welfare measures summarised as follows:

  • On March 30, the School Education Department issued directions to all schools in the state to postpone the collection of school fees until the lockdown is over.

  • The Department of Tribal Development issued directions to provide food/dietary components at home to women beneficiaries and children under Bharat Ratna Dr A.P.J. Abdul Kalam Amrut Aahar Yojana. 

  • The state government issued directives to the private establishments, industries and companies to pay full salaries and wages to their employees. 

  • On April 7, the state Cabinet decided to provide wheat and rice at a subsidised price to all Above Poverty line ration card holders and Shiv Bhojan at Rs 5 for next three months in all Shiv Bhojan centres.

  • On April 17, the Housing Department notified that landlords/house owners should defer the rent collection for three months.  No eviction will be allowed due to non-payment of rent during this period. 

Administrative Measures

  • On March 29, the public works department issued directions suspending the collection of tolls at PWD and MSRDC toll plazas for goods transport until further direction.

  • MLA Local Development Program:  Under MLALAD program, a one-time special exception to use the MLALAD funds was given to legislators for the purchase of medical equipment and materials for COVID-19 during the year 2020-21.

  • Analysing the impact on the economy of the state:  On April 13, the government constituted an Expert Committee and a Cabinet Sub-Committee to analyse the implications of COVID-19 on the economy of the state. These committees will also suggest measures to revive the economy of the state.

Orders relating to Mumbai city

  • On April 8, the city administration made it compulsory for all people to wear masks in public places. 

  • On April 10, the Commissioner of Police, Greater Mumbai issued an order prohibiting any kind of fake or distorted information on all social media and messaging applications. The order is valid until April 24.

For more information on the spread of COVID-19 and the central and state government response to the pandemic, please see here.